Measurement result data of total indoor suspended dust particle in three departments by using RTDM.

Measurement Time TSP, 1st Month (mg/m3), (N = 9 points, 4 days) TSP, 4st Month (mg/m3), (N = 9 points, 4 days) TSP, 7st Month (mg/m3), (N = 9 points, 4 days) TSP, 10st Month (mg/m3), (N = 9 points, 4 days) Inf. p-Values
Department of Process Cement

30 min after working 1.066 ± 0.1 1.511 ± 0.3 1.409 ± 0.4 1.081 ± 0.1 < NAB 0.99
2 h after working 9.406 ± 2.5 9.441 ± 2.4 8.217 ± 3.4 8.527 ± 3.5 < NAB 0.95
4 h after working 13.959 ± 2.3 12.102 ± 2.1 13.048 ± 2.2 12.765 ± 2.4 > NAB 0.99
6 h after working 14.073 ± 1.3 9.239 ± 2.6 10.406 ± 1.4 9.328 ± 2.2 > NAB 0.91
6 h after working 0.939 ± 0.3 0.871 ± 1.0 1.895 ± 0.7 1.494 ± 0.4 < NAB 0.61
Average per day 7.889 ± 5.5 7.433 ± 4.9 6.995 ± 4.3 6.639 ± 4.3 < NAB 0.60

Department of Loam

30 min after working 0.567 ± 1.0 0.932 ± 0.5 1.817 ± 0.3 0.608 ± 0.5 < NAB 0.11
2 h after working 5.828 ± 2.7 9.097 ± 3.1 12.143 ± 2.4 11.725 ± 2.6 > NAB 0.56
4 h after working 9.477 ± 2.4 10.201 ± 1.6 10.400 ± 1.7 10.540 ± 3.1 > NAB 0.12
6 h after working 10.716 ± 3.9 9.775 ± 2.4 9.775 ± 3.2 8.050 ± 3.1 > NAB 0.79
6 h after working 1.902 ± 0.4 1.049 ± 0.3 1.555 ± 0.5 1.287 ± 0.6 < NAB 0.08
Average per day 5.698 ± 3.6 6.211 ± 4.2 7.138 ± 4.4 6.442 ± 4.4 < NAB 0.56

Department of Black Sand

30 min after working 0.860 ± 0.4 0.776 ± 0.5 1.293 ± 0.5 0.736 ± 0.7 < NAB 0.95
2 h after working 4.490 ± 3.3 6.097 ± 2.1 8.620 ± 1.2 7.027 ± 1.1 < NAB 0.36
4 h after working 9.327 ± 3.2 10.029 ± 2.5 10.327 ± 2.2 11.595 ± 2.2 > NAB 0.62
6 h after working 8.891 ± 2.1 8.295 ± 1.5 9.871 ± 2.6 9.322 ± 1.6 < NAB 0.22
6 h after working 0.980 ± 0.8 1.231 ± 0.5 2.231 ± 0.4 0.902 ± 0.3 < NAB 0.54
Average per day 4.910 ± 3.4 5.286 ± 3.4 6.468 ± 3.8 5.916 ± 4.1 < NAB 0.98

NAB: Threshold Value; TSP: Total Suspended Particle.