Table A.1.
Technical Data of the Equipment Used
Factors | Tunnel Composting |
---|---|
Tunnel | The tunnel will be of concrete or other non‐corrosive construction as an enclosed vessel |
Water content at start‐up in the feedstock mixture | 50–65% |
Watering | As required during the process. During the post‐hygienisation phase, only clean water can be added |
Ventilation | Forced aeration is provided by an aeration floor beneath the mass in the tunnel. The warm air is recirculated |
Turning Equipment | Front end loader in order to load and unload the tunnels. Automatic filling system |
Temperature during hygienisation | Standard 1: 55°C; Standard 2: 60°C |
Temperature Monitoring | Temperature should be monitored to ensure that it is representative of the temperatures within the composting mass |