TABLE 2.

Values assigned for concave solar power project

Variables Values
Cost of producing 1 kWh $0.08
Cost of producing from 5 MWh per year 3,066,000
Installation cost 766,500
Operation and maintenance (5% increment after every 5 years) 306,600
Government formalities 20,000
Labour (10% increment after every 5 years) 613,200
Technology import 613,200
Renting land 613,200
Other cost 153,300
Interest rate (when applied) 10%
Premium (when applied) 5%

Source: Estimated by authors.