EOT, time overrun and/slippage of work of public building projects.

No Project Name Contract Duration in Days
Project status till Feb. 2020 Time overrun Slippage of work
Original EOT
1. Teaching Hospital Expansion 730 861 81% 22.56% 19%
2. Sports Courts Project 270 1662 113% 7 ? ?
3. Hospitality And Tourism institute 600 684 31.06% 13.7% 69%
4. Head Quarter BLD 730 931 80.46% 0% 19.5%
5. Student Canteen Complex 400 793 73.86% 7.5% 26.15%
6. Veterinary teaching hospital 360 729 45.07% 52.52% 55%
7. Agaro Campus Remaining Vol -I & Vol-II 540 259 38.62% 0% 60%
8. Research Center and Conference Hall 600 730 100% 37.21% None
9. Research Center and Conference Hall (supplementary contract) 210 63 100% 60.2% None
10. Maintenance & Road upgrade work with Asphalt con 365 710 92.12% 17.67% 8%