Table 3.
Causes of time overrun in road projects and measures taken by the employer.
SN | Project Name | Cause of Delay | Measure(s) taken by the employer |
---|---|---|---|
1. | Ageremariam – Yabelo |
|
No legal measure (Time at large) |
2. | Aposto-Wondo-Negele Con.1 |
|
No legal measure (Time at large) |
3. | Arbaminch-Kemba-Sawla contract I |
|
No legal measure (Time at large) |
4. | Arbaminch-Kemba-Sawla Lot II |
|
Additional EOT being considered |
5. | Arbereketi-Gelemso |
|
Additional EOT being considered |
6. | Chanka- Dembidolo |
|
Liquidated damages imposed |
7. | Gelemso-Mechara-Micheta |
|
Extension of time being considered |
8. | Kong – Begondi – Wombera |
|
On an interim extension period |
9. | Mekenajo-Ayra |
|
liquidated damages imposed |
10. | Otolo-Sawla lot III |
|
No legal measure (Time at large) |
11. | Sawla-Kako |
|
No legal measure (Time at large) |
12. | Sembo – Sholagebeya – Gorfo – Gindeber |
|
No legal measure (Time at large) |
13. | Shambu- Bako |
|
EOT being considered |
14. | Dallol-Musli-Bada |
|
EOT being considered |
15. | Dejen-Felegebirhan |
|
No legal measure (Time at large) |
16. | DichotoGalafi Junction - Elidar – Belho |
|
No legal measure (Time at large) |
17. | Jinka – Medir |
|
On the 5th interim EOT |
18. | Sawla-Maji, contract II |
|
No legal measure (Time at large) |