Management commitment dimension.

Management Commitment Items Mean
My project manager considers the safety of employees a top priority 5.07
My project manager acts quickly to correct safety problems 5.02
My direct supervisor stops work when it is unsafe 4.93
My project manager implements corrective actions when told about unsafe behavior or conditions 4.85
My direct supervisor begins the work only when working conditions are safe 4.85
My direct supervisor pays attention to my safety 4.80
My project manager considers safety issues seriously 4.79
My project manager focuses on safety at all times, not only after accidents have occurred 4.73
My project manager expresses concern if safety procedures are not adhered to 4.36