Table 1.
Relative technology transfer complexity | Risk scorea | Support description | In-plant support |
---|---|---|---|
Same product, new strain, similar process, same site | 0 | “Light” | 1 person on site for the first run |
New product, similar process, same site | 1 | “Lean” | 2–3 people on site. Minimal Debug Plan |
New product, modified process, same site | 2 | “Moderate” | 1 person per unit operation. Critical aspects of Debug Plan implemented |
New product, modified process, new unit operations or new CMO | 3 | “Heavy” | 1–2 people per new unit operation. Full Debug Plan. Specialized or vendor support on new unit Ops |
New product, modified process, new unit operations, new CMOs | 4 | “Full Court Press” | Two support staff per unit operation. Full Debug lan including parallel fermentations and parallel DSP operations. Specialized or vendor support on new unit Ops |
aRisk increases if the product is new, the process is new, there are new unit operations, and/or the manufacturing site is new