Table 4.

RII ranking for Clients/Owners-related delay factors.

S/N Owner-related causes of delay RII RII ranking Level of contribution
1 Delay in honoring payment progressively 0.846 1 Very high
2 Delay in the provision or delivery of project site 0.742 4 High
3 Slow decision-making process 0.658 9 High
4 Errors in design and specifications 0.696 7 High
5 Lateness in the revision and approval of design documents 0.729 5 High
6 Poor communication and coordination with contracting parties 0.767 3 High
7 Difficulties in accessing credit facilities (E.g. Loan) 0.683 8 High
8 Change orders during construction by owner 0.792 2 High
9 Conflicts between project joint-owners 0.708 6 High
10 Indefinite suspension of work by owner 0.696 7 High
11 Lack of complete documentation before commencement of project 0.642 10 High
12 Delay in the approval of sample materials 0.625 11 High