Table 5.
RII ranking for Contractors-related delay factors.
S/N | Contractor-related causes of delay | RII | RII ranking | Level of contribution |
---|---|---|---|---|
1 | Difficulties in project financing | 0.783 | 2 | High |
2 | Errors during construction | 0.696 | 8 | High |
3 | Improper planning and preparation during construction project | 0.721 | 6 | High |
4 | Poor site management and coordination | 0.700 | 7 | High |
5 | Delays in sub-contractor's work | 0.779 | 3 | High |
6 | Underestimation or overestimation of the project cost | 0.808 | 1 | Very High |
7 | Conflicts between contractor and other parties | 0.746 | 5 | High |
8 | Delays in the mobilization of workers | 0.650 | 10 | High |
9 | Regular change of sub-contractor's technical staff | 0.746 | 5 | High |
10 | Conflicts in sub-contractor's schedule in execution of project | 0.692 | 9 | High |
11 | Underestimation of the project durations | 0.763 | 4 | High |