Table 6.

RII ranking for Consultants-related delay factors.

S/N Consultant-related causes of delay RII RII ranking Level of contribution
1 Delay in the approval of major changes in the work scope 0.800 1 Very high
2 Poor communication and coordination 0.767 2 High
3 Lack of significant experience of consultant 0.750 3 High
4 Mistakes and discrepancies in contract documents 0.700 6 High
5 Delays in creating design documents 0.733 4 High
6 Inadequate site survey and data collection before design 0.713 5 High
7 Delay in instructions from consultants 0.671 8 High
8 Back report of the consultant 0.692 7 High