Table 8.
S/N | Materials-related causes of delay | RII | RII ranking | Level of contribution |
---|---|---|---|---|
1 | Materials procurement difficulties (Lateness) | 0.763 | 2 | High |
2 | Shortage/lack of materials in the market place | 0.758 | 3 | High |
3 | Increase/Fluctuation in the prices of materials | 0.792 | 1 | High |
4 | Delay in the delivery of materials | 0.738 | 4 | High |
5 | Changes in material types during construction | 0.708 | 5 | High |
6 | Damage of sorted materials that are needed urgently | 0.650 | 6 | High |