Table 4.

Industrial transport times of the missions in the digital twin and in the physical implementation in Scenario 1.

Mission (Targets in Order) Digital Twin Time (s) Real Implementation Time (s) Accuracy (%)
Milling—Drilling—Turning 52.3 51 97.51
Milling—Turning—Drilling 54.1 55 98.36
Turning—Drilling—Milling 55.4 56 98.93
Turning—Milling—Drilling 50.8 50 98.43
Drilling—Turning—Milling 53.1 51 96.05
Drilling—Milling—Turning 37.4 38 98.42