DE1 |
Request to de-energize |
T1 |
Area authority make work order |
T2 |
Apply for permit to work |
T3 |
Identify and determine location of de-energization |
DE2 |
De-energization |
T4 |
Wear appropriate PPE |
T5 |
Feeder disconnection |
T6 |
Lock and tag |
T7 |
Communicate the disconnection to operation unit |
DE3 |
Perform voltage test |
T8 |
Wear appropriate PPE |
T9 |
Ensure that instrument is operable |
T10 |
Check in no voltage condition |
T11 |
Retest that instrument is operable |
T12 |
Informed the operation unit of testing results |
DE4 |
Discharge the de-energized line |
T13 |
Install the grounding rod in opposite side of shooting |
T14 |
Open the spool of fuse wire from shooting site toward grounding rod |
T15 |
Fasten one end of the fuse wire to grounding rod and the other end to spare arrow. |
T16 |
Insert the spare arrow in gun tester |
T17 |
Ensure that the opened fuse wire is not put behind the shooter or other crew members |
T18 |
Shooting and interpretation of outcomes |
T19 |
Informed the discharging to operation unit |
DE5 |
Install temporary grounds |
T20 |
Sitting the location of inserting ground electrode |
T21 |
Visually inspect any defect in safety ground wire which is to be applied. |
T22 |
Ensure that all not necessary maintainers have been cleared from the working zone |
T23 |
Fasten the ground end of the safety temporary ground electrode first |
T24 |
Contact and tighten the grounding clamp from the closest to the farthest phase one at a time with the phase end of the safety temporary ground. |
T25 |
Install temporary ground, also at the other end of de energized section |
T26 |
Informed the installation temporary grounds to operation unit |