Table 4.
eHealth project progress aspect planning.
Question | Midterm (n=29) | End-term (n=27) | ||
|
Yes, n (%) | No, n (%) | Yes, n (%) | No, n (%) |
Is the available time sufficient for successful progress of your project? | 23 (79) | 6 (21) | 15 (56) | 12 (44) |
Is your project planning, as described in the project plan, still up to date? | 17 (59) | 12 (41) | 4 (15) | 23 (85) |
As the project is progressing now, I expect to achieve the measurable goals as described in the project plan | 25 (86) | 4 (14) | 19 (70) | 8 (30) |
I do not foresee any problems in contributing to program deliverables at the end of the Citrien Fund program eHealth, as described in my project plan | 29 (100) | 0 (0) | 23 (85) | 4 (15) |