Table 1.
Correct steps to be performed in the intravenous cannulation station and the points awarded for each step
| Step | Correct | Partial |
|---|---|---|
| Assembling Materials | ||
| Peripheral venous cathether | 0.16 | |
| Tourniquet | 0.16 | |
| Alcohol | 0.16 | |
| Band-aid | 0.16 | |
| Swab | 0.16 | |
| Sharps container | 0.20 | |
|
Putting on gloves (partial if hand disinfection missing) |
1.0 | 0.5 |
|
Putting on the tourniquet (partial if kept on for too long) |
0.5 | 0.25 |
|
Taking off the tourniquet (partial if taken off after needle has been removed) |
0.5 | 0.25 |
| Cleaning the patient’s skin with alcohol | 0.5 | |
| Letting the alcohol dry for 30 seconds | 0.5 | |
|
Inserting the needle (partial if only successful on second try) |
0.5 | 0.25 |
| Sterile insertion of the needle | 0.5 | 0.25 |
|
Disposing the needle into the sharps container (partial if needle is placed on a tray) |
1.0 | 0.5 |
| Fixing the catheter in place | 1.0 | |
| Starting the intravenous therapy | 1.0 | |
| Informing the patient about the procedure | 0.5 | |
| Performing all steps in a structured manner | 1.0 | |
| Sanitizing the hands after the procedure has been completed | 0.5 | |