The project timeline

S/N Description of activity Duration Year Quarter
1st 2nd 3rd 4th 5th 6th 7th 8th
1

Formation of team and coordination

Planning and need assessment

3 months 1 X
2 Finalizing protocol and manuals 2 months 1 X
3 Hiring staff; selection and training of CORPs; identification of health Facilities and training of health workers 1 month 1 X
4 Baseline studies and data analysis and interim report 2 months 1 X
5 Preparation for intervention, Development of IEC 1 month 1 X
6 Recruitment of patients 3 months 1 X
7 Conducting follow-up visits 6 months 1 & 2 X X
8 Laboratory samples collected 1 & 2 X X
9 Mid-study report 1 month 1 X
10 Post-intervention survey 3 months 2 X
11 Final data analysis 2 months 2 X
12 Final report writing 1 months 2 X