Table 7.
Cost of delivering intervention* | Cost of training** | Total cost |
Cost/
participant |
|
---|---|---|---|---|
Site 1 (n = 13) | £4,347 | £1,418 | £5,765 | £ 443 |
Site 2 (n = 3) | £1,272 | £1,193 | £2,465 | £ 822 |
Overall (n = 16) | £5,619 | £2,611 | £8,230 | £ 514 |
*Total cost based on number of full hours of care provided (69 in Site 1, 24 in Site 2).
**Number of hours of training (3 days at 7.5 per day = 22.5 h) x unit cost of trainer and trainee's time.