The estimated cost of the official monitoring program and the designed monitoring program for AFB1 in feed in 2016–2018.

Monitoring program of 2016–2018 Total number of samples ML model prediction result Total cost (euro) Calculation
Designed 841 TP 1 32300 Eqs. (14)
FP 24
TN 816
FNa 0
Officialb 841 NANb NAN 925100 Eq. (5)

aTP represents an actual non-compliant batch that was predicted as non-compliant. FP represents a compliant batch that was predicted to be non-compliant, TN represents an actual compliant batch that was predicted as compliant. FN represents an actual non-compliant batch that was predicted as compliant.

bNo predictive model was performed.