Skip to main content
. 2020 Jan 13;1:100010. doi: 10.1016/j.ese.2020.100010

Table 6.

Life-cycle cost of seven LID implementing scenarios.

LID practice Installing dimensions (m2) Assigned capital cost per unit ($) Assigned annual cost per unit ($) Assigned lifespan (year) PVC (million $)a
IT 11,224 11.97 0.80 15 0.232
RB 13,469 3.68 0.06 15 0.058
PP 6734 110.15 0.44 15 0.774
IT ​+ ​RB 11,224 ​+ ​13,469 15 0.291
IT ​+ ​PP 11,224 ​+ ​6734 15 1.006
PP ​+ ​RB 13,469 ​+ ​6734 15 0.832
IT ​+ ​PP ​+ ​RB 11,224 ​+ ​13,469 ​+ ​6734 15 1.065
a

PVC for LID combination is the sum of PVC for all involved LID practices.