Table 4. Top ranked delay factors for each group of respondents.

Client/owner Contractor Consultant Rank
Financial difficulties of contractors Shortage of skilled subcontractors/suppliers Financial difficulties of contractors 1
Shortage of skilled subcontractors/suppliers Shortage of labourers. (Skilled, semi-skilled, unskilled) Shortage of skilled subcontractors/suppliers 2
Shortage of labourers (Skilled, semi-skilled, unskilled) Delay in delivering materials to the site Shortage of labourers (Skilled, semi-skilled, unskilled) 3
Poor site management, monitoring, and control Poor planning and scheduling Covid-19 pandemic situation 4
Delay in delivering materials to the site Inadequate numbers of equipment Delay in delivering materials to the site 5
Poor planning and scheduling Fluctuation of material prices in the market Poor planning and scheduling 6
Fluctuation of material prices in the market Financial difficulties of contractors Financial difficulties of client 7
Inadequate numbers of equipment Slowness of the client’s decision-making Poor site management, monitoring, and control 8
Covid-19 pandemic situation Low productivity of labourers Fluctuation of material prices in the market 9
Delay in obtaining permissions/approvals from government Covid-19 pandemic situation Delay in obtaining permissions/approvals from government 10

Source: Authors’ calculations.