Table 7. RII and ranking of consultant-related factors.

Delay factors RII Rank
Q17 Delay in inspections and completed work approvals. 0.6466 6
Q18 Delay in material and payment approval. 0.6994 1
Q19 Errors in contract documents. 0.6123 8
Q20 Constant design changes by the consultant 0.6736 4
Q21 Delay in preparing and approving drawings and design documents. 0.6896 2
Q22 Lack of experienced consultants. 0.6626 5
Q23 Errors in design documents. 0.6393 7
Q24 Poor coordination and communication. 0.6773 3

Source: Authors’ calculations.