Table 7. RII and ranking of consultant-related factors.
Delay factors | RII | Rank | |
---|---|---|---|
Q17 | Delay in inspections and completed work approvals. | 0.6466 | 6 |
Q18 | Delay in material and payment approval. | 0.6994 | 1 |
Q19 | Errors in contract documents. | 0.6123 | 8 |
Q20 | Constant design changes by the consultant | 0.6736 | 4 |
Q21 | Delay in preparing and approving drawings and design documents. | 0.6896 | 2 |
Q22 | Lack of experienced consultants. | 0.6626 | 5 |
Q23 | Errors in design documents. | 0.6393 | 7 |
Q24 | Poor coordination and communication. | 0.6773 | 3 |
Source: Authors’ calculations.