Table 9. RII and ranking of external factors.

Delay factors RII Rank
Q33 Delay in obtaining permissions/approvals from the government. 0.7558 2
Q34 Unknown subsurface conditions. (Soil condition, water table etc.) 0.6859 3
Q35 Bad weather conditions. 0.6528 4
Q36 Accidents during construction. 0.5043 7
Q37 Changes in laws and regulations from the government. 0.5313 6
Q38 Delay in utility services. (Electricity, water etc.) 0.6491 5
Q39 Covid-19 pandemic situation 0.7902 1

Source: Authors’ calculations.