TABLE 3.

Whole Life-Cycle Costs of Pressure Swing Absorption Plants in Kenya, Rwanda, and Ethiopia

Kenya, US$ Rwanda, US$ Ethiopia,a US$
Capital costs
 Plant, generator, and infrastructure
  Back-up generator
  Spare parts
  Surrounding infrastructure
  Electrical
  Installation labor
  Legal costs
  Shipping and taxes
319,813.59 269,393.68 438,749.95
 Piping and manifold 218,016.66 92,000.00 0.00b
 Cylinders, tools, and accessories
  Cylinders
  Cylinder accessories
  Oxygen plant toolkit
  Analyzers
  Pulse oximeters
  Shipping costs and taxes
213,706.29 134,250.77 107,605.87
 Transportation
  Vehicles (e.g., trucks)
  Registration and insurance
  Inspection
53,814.60 38,498.00 53,485.41
 Plant training 6,000.00 6,000.00 10,495.53
 In-kind value of building/land 45,000 50,000 50,000
Total capital costs (excluding in-kind) 811,351.14 540,142.45 610,336.75
Total capital costs (including in-kind) 856,351.14 590,142.45 660,336.75
Yearly operating costs
 Plant labor 28,119.60 17,883.04 15,708.08
 Accessories 5,839.04 1,215.80 23,813.32
 Electricity 96,000.00 30,000.00 19,867.68
 Fuel 3,830.56 2,827.40 10,250.60
 Service contracts, labor 7,000.00 7,000.00 7,000.00
 Service contracts, spare parts 17,000.00 17,000.00 17,000.00
 Indirect/miscellaneous costs 14,873.96 5,085.00 8,892.20
Total yearly operating costs 172,663.16 81,011.24 102,531.88
Whole life-cycle cost over 20 yearsc 5,073,877.68 2,568,949.36 3,277,697.31

a Ethiopia costs represent the cost per hub site.

b Piping was not installed in Ethiopia.

c Whole life-cycle cost incorporates year-over-year inflation.