A new technique based on Artificial Bee Colony Algorithm for optimal sizing of stand-alone photovoltaic system

Ahmed F Mohamed 1,, Mahdi M Elarini 1, Ahmed M Othman 1
PMCID: PMC4294754  PMID: 25685507

Abstract

One of the most recent optimization techniques applied to the optimal design of photovoltaic system to supply an isolated load demand is the Artificial Bee Colony Algorithm (ABC). The proposed methodology is applied to optimize the cost of the PV system including photovoltaic, a battery bank, a battery charger controller, and inverter. Two objective functions are proposed: the first one is the PV module output power which is to be maximized and the second one is the life cycle cost (LCC) which is to be minimized. The analysis is performed based on measured solar radiation and ambient temperature measured at Helwan city, Egypt. A comparison between ABC algorithm and Genetic Algorithm (GA) optimal results is done. Another location is selected which is Zagazig city to check the validity of ABC algorithm in any location. The ABC is more optimal than GA. The results encouraged the use of the PV systems to electrify the rural sites of Egypt.

Keywords: PV array, Storage battery, Inverter, Bee colony, Genetic algorithm and life cycle cost

Introduction

Photovoltaic (PV) system has received a great attention as it appears to be one of the most promising renewable energy sources. The absence of an electrical network in remote areas leads the organizations to explore alternative solutions such as stand-alone power system. The performance of a stand-alone PV system depends on the behavior of each component and on the solar radiation, size of PV array, and storage capacity. Therefore, the correct sizing plays an important role on the reliability of the stand-alone PV systems. There are classified as intuitive methods, numerical methods, and analytical methods. The first group algorithms are very inaccurate and unreliable. The second is more accurate, but they need to have long time series of solar radiation for the simulations. In the third group, there are methods which use equations to describe the PV system size as a function of reliability. Many of the analytical methods employ the concept of reliability of the system or the complementary term: loss of load probability (LLP). A review of sizing methods of stand-alone PV system has been presented by Shrestha and Goel [1], which is based on energy generation simulation for various numbers of PVs and batteries using suitable models for the system devices (PVs, batteries, etc.). The selection of the numbers of PVs and batteries ensures that reliability indices such as the Loss of Load Hours (LOLH), the lost energy and the system cost are satisfied. In a similar method, Maghraby et al. [2] used Markov chain modeling for the solar radiation. The number of PVs and batteries is selected depending on the desired System Performance Level (SPL) requirement, which is defined as the number of days that the load cannot be satisfied, and it is expressed in terms of probability. An optimization approach in which the optimal number and type of units ensuring that the 20-year round total system cost is minimized was presented by Koutroulis et al. [3], and the proposed objective function is subjected to the constraint that the load energy requirements are completely covered, resulting in zero load rejection. The drawback of this technique is that the power produced by the PV and WG power sources is assumed to be constant during the analysis time period. An optimal approach for sizing both solar array and battery in a stand-alone photovoltaic (SPV) system based on the loss of power supply probability (LPSP) of the SPV system was given by Lalwani et al. [4]. An economic analysis on a solar based stand-alone PV system to provide the required electricity for a typical home was presented by Abdulateef et al. [5]. An intelligent method of optimal design of PV system based on optimizing the costs during the 20-year operation system was presented by Javadi et al. [6]. A methodology for designing a stand-alone photovoltaic (PV) system to provide the required electricity for a single residential household in India was introduced by Kirmani et al. [7] in which the life cycle cost (LCC) analysis is conducted to assess the economic viability of the system. A technique for PV system size optimization based on the probabilistic approach was presented by Arun et al. [8]. An optimization technique of PV system for three sites in Europe in which optimization considers sizing curves derivation and minimum storage requirement was proposed by Fragaki and Markvart [9]. An analytical method for sizing of PV systems based on the concept of loss of load probability was presented by Posadillo and Luque [10], in this method, the standard deviation of loss of load probability and another two new parameters, annual number of system failures and standard deviation of annual number of failures are considered, and the optimization of PV array tilt angle is also presented to maximize the collected yield. The previous literature methods have some drawbacks such as

  • 1.

    The design is based on insufficient database of the devices; as only two types of PV modules, batteries and controller were suggested by Koutroulis et al [3].

  • 2.

    The design is based on the instantaneous PV module power which is not practical point as the design must be based on the worst case which is the maximum power extracted from the module.

The bee colony system and its demonstration of the features are discussed by Karaboga and Akay [11]; additionally, it summarized the algorithms simulating the intelligent behaviors in the bee colony and their applications. ABC has been used to solve many problems from different areas successfully [12]. It has been used to solve certain bench mark problems like Traveling Salesman Problem, routing problems, NP-hard problems. A comprehensive comparative study on the performances of well-known evolutionary and swarm-based algorithms for optimizing a very large set of numerical functions was presented [13]. Another application for ABC was introduced by Karaboga and Ozturk [14]. It is used for data clustering on bench mark problems, and the performance of ABC algorithm is compared with Particle Swarm Optimization (PSO) algorithm. Artificial Bee Colony Programming was described as a new method on symbolic regression which is a very important practical problem [15]. Symbolic regression is a process of obtaining a mathematical model using given finite sampling of values of independent variables and associated values of dependent variables. A set of symbolic regression bench mark problems are solved using Artificial Bee Colony Programming, and then, its performance is compared with the very well-known method evolving computer programs, genetic programming. According to the various applications of ABC algorithm, it can be applied to solve the proposed difficult design optimization problem.

In this paper, a new Evolutionary Technique for optimizing a stand-alone PV system is presented. The technique aims to maximize the output electrical power of the PV module and minimize the life cycle cost (LCC). It is based on two proposed objective function subjected to constraints; either equality or inequality constraints. Firstly, dummy variables of the PV system operation are classified into two categories: dependent and independent variables. The independent variables are those that do not depend on any variable of solar module operation, while the dependant variables are those controlled by independent one. Secondly; the Artificial Bee Colony Algorithm (ABC) is used to solve the optimization problem [16]. Finally; a comparison between ABC solution and Genetic Algorithm (GA) solution is performed. The proposed technique is applied to Helwan city at latitude 29.87°, Egypt, and to ensure the validity of ABC algorithm, the methodology is repeated for Zagazig city. The results showed that the proposed constrained optimization method is efficient and applicable for any location.

Mathematical model of PV system

The PV system comprises PV array, battery bank, battery charger controller, and DC/AC inverter as shown in Fig. 1.

Fig. 1.

Fig. 1

Block diagram of proposed PV system.

PV module

In this section, a model of the PV module is presented. The total rate of radiation GC striking a PV module on a clear day can be resolved in to three components [17]; direct beam, GBC, diffuse, GDC, and reflected beam, GRC.

GC=GBC+GDC+GRC (1)
GC=Ae-kmcosβcosφS-φCsinΣ+sinβcosΣ+C1+cosΣ2+ρ(sinβ+C)1-cosΣ2 (2)
m=h2h1=1sinβ (3)

where m is the air mass, β is the altitude angle, φS is the solar azimuth angle, φC is the PV module azimuth angle, Σ is the PV module tilt angle, ρ is the reflection factor, C is the sky diffuse factor, and A and k are parameters dependent on the Julian day number [1].

C=0.095+0.04sin360365(d-100) (4)
A=1160+75sin360365(d-275)(W/m2) (5)
k=0.174+0.035sin360365(d-100) (6)

where d is the day number. The PV module consists of NS of series cells and NP of parallel branches as shown in Fig. 2.

Fig. 2.

Fig. 2

The equivalent circuit for a PV module.

A PV module’s current IM can be described as follows [18]:

IM=NpISC-NpI0expqVMNS+IM·RSMnkbTc-1-VMNS+IM·RSMRPM (7)
AndRsM=NSNpRsC,RPM=NpNSRPCandVM=NSVC (8)

where ISC is the PV module short circuit current, I0 is the reverse diode saturation current, VC is the cell voltage, VM is module voltage, RsC is the cell series resistance, RPC is the cell parallel resistance, RsM is the module series resistance, RPC is the module parallel resistance, n is the diode ideality factor, kb is the Boltzmann constant (1.38e−23 J/K), and Tc is the cell junction temperature (°C) that is calculated as follows:

TC=Ta+NOCT-20°0.8*GC (9)

where Ta is the ambient temperature and NOCT is cell temperature in a module when ambient temperature is 20 °C.

Battery

In general, a PV battery can be modeled as a voltage source, E, in series with an internal resistance, R0, as shown in Fig. 3. The terminal voltage V is given as follows [17]:

V=E-IR0 (10)

Fig. 3.

Fig. 3

Schematic diagram of the battery.

The proposed methodology

The proposed technique is based on two objective functions: the first describes the PV module output Power and the second describes the LCC of the PV system. Each proposed objective function has some constraints.

The proposed objective function of the PV module power

The main object of this section is to extract a possible maximum power from a PV module based on a proposed objective function of the power which subjected to constraints; the proposed objective function is obtained as follows: During the operation of the PV module, there are some variables that control the operation. Initially, these dummy variables are classified into two categories: independent or control variables (U) and their corresponding dependant variables (X). The proposed two vectors are as follows: U = [NSNPd, Σ, φC] and X = [βmφSGCISCI0Tc]. The proposed objective function is expressed in the following form:

maximizePpvi(max)(t,Σopt)=fTc,VM,m,Σ,φC,β,L,ω,GC,I0=(NsVC)In+1M=VMInM1-11+ψ(Tc)1-μVM,Tc,IM(Tc)+ψ(Tc)m,φS,β,Σ,φCμVM,Tc,IM+γ(VM)1+ψ(Tc)1-μ(VM,Tc,IM)(Tc) (11)

where Ppvi(max)(t,Σopt) is the maximum PV module output power at optimal tilt angle Σopt and hour t during a day no. i, L is the latitude, ψ(Tc), μ(VMTcIM) μ(VMTcIM), ∂(Tc), ɛ(mφSβΣφC), and γ(VM) are nonlinear functions, each related to its corresponding variables. The proposed parametric constrains are as follows:

dmin<d<dmax1d365
Σmin<Σ<Σmax0Σ80
φCmin<φC<φCmax-45φC45 (12)

The proposed equality constraint is given as

g(U,X)=Voc-184.0293*NsVCTc=0 (13)

The limits of independent variables are selected according to the following aspects:

  • 1.

    When Σ = 0°, the module becomes horizontal and produces power while when Σ = 90; the module becomes vertical and produces zero power; so the selected limits are assumed between 0° and 80°.

  • 2.

    The solar azimuth angle is positive for east of south, and becomes negative for west of south; so the limits are selected as ±45°.

The total power, Prei(t), transferred to the battery bank from the PV array during day i and hour t is calculated as follows:

Prei(t)=Npv*Ppvi(max)(t,Σopt) (14)

where Npv is the total number of PV modules used in the array, Then, the DC/AC inverter input power, PLi(t), is calculated using the corresponding load power requirements, as follows:

PLi(t)=Ploadi(t)ξinv (15)

where Ploadi(t) is the power consumed by the load at hour t of day i, defined at the beginning of the optimal sizing process and ξinv is the inverter efficiency. According to the above power production and load consumption calculations, the resulting battery capacity is calculated.

  • If Prei(t)=PLi(t) then the battery capacity remains unchanged.

  • If Prei(t)>PLi(t) then the power surplus PBi(t)=Prei(t)-PLi(t) is used to charge the battery bank, and the new battery capacity is calculated as following.

Ci(t)=Ci(t-1)+PBi(t)*Δt*ξbatVBus1t24 (16)

where Ci(t), Ci(t − 1) is the available battery capacity (Ah) at hour t and t − 1, respectively, of day i, ξbat=80% is the battery round-trip efficiency during charging and ξbat=100% during discharging [19], VBus is the DC bus voltage, PBi(t) is the battery input/output power, and Δt is the simulation time step, set to Δt = 1h. At any hour, the storage capacity is subject to the following constraints:

CminCi(t)(t)Cmax (17)

where CmaxCmin are the maximum and minimum allowable storage capacities. Using for Cmax the storage nominal capacity, then Cmin = DOD * Cn; Cn as is the nominal capacity of battery. The number of PV modules connected in series in the PV array, npvs, depends on the battery charger maximum input voltage which is equal to the dc bus voltage, VBus (V), and the PV modules maximum power corresponding voltage VMP (V), the relation is given below.

npvs=VBusVMP (18)

The number of batteries connected in series, nbs, depends on the nominal DC bus voltage and the nominal voltage of each individual battery, Vb, and it is calculated as follows:

nbs=VBusVb (19)

The number of battery chargers, Nch, depends on the total number of PV modules.

Nch=NpvPmPmc (20)

where Pm is the maximum power of one module under STC and Pmc is the power rating of battery charger.

The proposed LCC objective function

This section presents the second objective function of the PV system life cycle cost which is required to be minimized to obtain the best numbers of PV modules, batteries, and chargers with minimum (optimal) cost.

The total PV system cost function is equal to the sum of the total capital Cc(u), maintenance cost Cm(u) ($), functions.

min{J(u)}=min{Cc(u)+Cm(u)} (21)

where u is a set of the cost independent variables which are the total number of PV modules and the total number of batteries. The total number of battery chargers is calculated after calculating the optimal value of u variables. Thus, the multi-objective optimization is achieved by minimizing the total cost function consisting of the sum of individual system cost devices capital cost and 20-year round maintenance cost. The proposed life time cost objective function is:

J(u)=i=1NPViCPVi+20·MPViL.TPV+j=1NBATj·CBATj1+yBATj+MBATj·(20-yBATj)L.TBAT+l=1NCHl·CCHl1+yNCHl+MNCHl·(20-yNCHl)L.TCH+CInv1+yInv+MInv·(20-yInv)L.TInv (22)

Subject to NPV0

NBAT0 (23)

where L.TPV, L.TBAT, L.TCH, L.TInv are the year life time for PV module, battery, battery charger and the inverter respectively, u = [NPVNBAT], CPV and CBAT are the capital costs ($) of one PV module, and battery, respectively, MPV, and MBAT are the maintenance costs per year ($/year) of one PV module and battery, respectively, Cch is the capital cost of one battery charger ($), ych, yinv are the expected numbers of the battery charger and DC/AC inverter replacements during the 20-year system lifetime and are assumed to be equal 4, Cinv is the capital cost of the inverter, ($),yBAT is the expected number of battery replacements during the 20-year system operation, because of limited battery lifetime, Mch, Minv are maintenance costs per year ($/year) of one battery charger and DC/AC inverter, respectively. Maintenance cost of each unit per year has been assumed 1% of the corresponding capital cost. The total optimal number of PV modules, NPV, and the total optimal number of batteries NBAT are calculated by minimizing the objective function of cost. Then, the number of parallel strings npvp and the number of batteries connected in parallel nbp can be calculated using the following formulas;

npvp=Npvnpvs (24)
nbp=NBATnbs (25)

So, the optimal number and optimal configuration for the PV system components are obtained. The different combinations of PV modules, batteries, and chargers are studied, and the optimal cost of each case is calculated from Eq. (22), then the minimum cost is selected, and the corresponding combination are obtained.

Genetic algorithm

The term genetic algorithm, almost universally abbreviated nowadays to GA, was first used by Holland [20]. GAs in their original form summarized most of what one needs to know. Genetic Algorithm (GA) is gradient-free, parallel optimization algorithms that use a performance criterion for evaluation and a population of possible solutions to the search for a global optimum. GA is capable of handling complex and irregular solution spaces, and they have been applied to various difficult optimization problems. The manipulation is done by the genetic operators that work on the chromosomes in which the parameters of possible solutions are encoded. The main elements of GAs are populations of chromosomes, selection according to fitness, crossover to produce new offspring, and random mutation of new offspring. The simplest form of genetic algorithm involves three types of operators: selection, crossover, and mutation. A simple GA flow chart is shown in Fig. 4. The used form of genetic algorithm involves three types of operators: selection, crossover (single point), and mutation.

  • Selection: This operator selects chromosomes in the population for reproduction. The fitter the chromosome, the more times it is likely to be selected to reproduce.

  • Crossover: This operator randomly chooses a locus and exchanges the subsequences before and after that locus between two chromosomes to create two offspring. The crossover operator roughly mimics biological recombination between two single chromosome organisms.

  • Mutation: This operator randomly flips some of the bits in a chromosome. Typically, a chromosome is structured by a string of values in binary form, which the mutation operator can operate on any one of the bits, and the crossover operator can operate on any boundary of each two bit in the string. Here, the mutation can change the value of a real number randomly, and the crossover can take place only at the boundary of two real numbers. The control parameters of GA are assumed as; the proposed mutation function is mutation adapt feasible, the population size is assumed to be 100; the number of generation is assumed to be 200.

Fig. 4.

Fig. 4

A simple genetic algorithm flow chart.

Artificial Bee Colony Algorithm

Artificial Bee Colony (ABC) is one of the most recently defined algorithms by Dervis Karaboga in 2005 [16], motivated by the intelligent behavior of honey bees. ABC as an optimization tool provides a population based search procedure in which individuals are foods positions are modified by the artificial bees with time, and the bee’s aim is to discover the places of food sources with high nectar amount and finally the one with the highest nectar. The ABC algorithm steps are summarized as follows:

  • Initial food sources are produced for all employed bees.

  • Repeat the following items;
    • 1.
      Each employed bee goes to a food source in her memory and determines a neighbor source, then evaluates its nectar amount and dances in the hive.
    • 2.
      Each onlooker watches the dance of employed bees and chooses one of their sources depending on the dances, and then goes to that source. After choosing a neighbor around that, she evaluates its nectar amount.
    • 3.
      Abandoned food sources are determined and are replaced with the new food sources discovered by scouts.
    • 4.
      The best food source found so far is registered.
  • UNTIL (requirements are met).

The flow chart shown in Fig. 5 gives detailed steps that are followed in the ABC algorithm. Fig. 6 shows the steps of the proposed PV sizing optimization methodology. The optimization algorithm input is fed by a database containing the technical characteristics of commercially available system devices along with their associated per unit capital and maintenance costs. Various types of PV modules, batteries with different nominal capacities, etc., are stored in the input database.

Fig. 5.

Fig. 5

Artificial Bee Colony Algorithm flow chart.

Fig. 6.

Fig. 6

Flow chart of the proposed PV sizing optimization methodology.

The control parameters of ABC algorithm are assumed as follows:

  • The number of colony size (employed bees and onlooker bees) is assumed to be 20.

  • The number of food sources equals the half of the colony size.

  • The limit is assumed to be 100. A food source which could not be improved through “limit” trials is abandoned by its employed bee.

  • The number of cycles for foraging is assumed to be 1000.

These controlled values are selected as the possible minimum cost is obtained at these values.

Results and discussions

The analysis of the proposed algorithm is performed on a real data for direct beam solar radiation and ambient temperature measured by solar radiation and meteorological station located at National Research Institute of Astronomy and Geophysics Helwan, Cairo, Egypt, located at latitude 29.87°N and longitude 31.30°E. The station is over a hill top of about 114 m height above sea level. Example of The daily recorded measured solar radiation is shown in Fig. 7. The data are recorded for the sunny day of June 10, 2012 start from hour 6:10 AM to hour 5:50 PM. The distribution of the consumer power requirements during a day is shown in Fig. 8; the total energy demand per day for the load is equal to 5.56 kW h/day. The technical characteristics and the related capital and maintenance costs of the PV system devices, which are used, are shown in Table 1. The expected battery lifetime has been set at 3 years resulting in yBAT = 6 for 20 year. The expected replaced number of both charger and inverter is ych yinv = 4. The bus voltage is assumed to be 48 V. First, the optimal power and corresponding tilt angle for each suggested that PV module is obtained in Table 2 using GA program. One can derive that the obtained maximum powers are 118.2689, 226.6207, 276.4720, 317.0012, and 399.9663 for each type of PV system, respectively. All maximum powers occur at 12:00 PM. To investigate the advantages of the proposed technique, the obtained results are compared to techniques proposed by Koutroulis et al. [3] based on the measured solar radiation data for Helwan city. The comparison is given in Tables 3. The PV module of type 1 is considered Bpsx150, the PV module of type 2 is considered CHSM6610M-235, the battery of type 1 is 230 Ah, the battery of type 2 is 100 Ah, the charger of type 1 is 300 W, and the charger of type 2 is 240 W.

Fig. 7.

Fig. 7

Measured solar radiation and ambient temperature.

Fig. 8.

Fig. 8

Distribution of the consumer power requirements during the day.

Table 1.

The specifications of the PV system devices.

Type Power rating (W) Capital cost ($) Maintenance cost per year ($/year)
PV module specifications
1. CS5C-90 90 450 4.50
2. Bpsx150 150 750 7.50
3. CS6P-200 200 1000 10.00
4. CHSM6610M-235 235 1175 11.75
5. IM72C3-310-T12B45 310 1550 15.50
Type Nominal capacity (Ah) Voltage (V) DOD (%) Capital cost ($) Maintenance cost per year ($/year)

Batteries specifications
1 230 12 80 341 3.41
2 100 12 80 163 1.63
3 150 12 80 256 2.56
4 300 6 80 512 5.12
5 420 6 80 716 7.16
Type Power rating (W) Capital cost ($) Maintenance cost per year ($/year)

PV battery chargers specifications
1 300 259 2.59
2 240 121.5 1.215
3 288 140 1.4
4 120 198 1.98
5 1152 289 2.89
1 300 259 2.59
Type Efficiency (%) Power rating (W) Capital cost ($) Maintenance cost per year ($year)

DC/AC inverter specifications
1 80 1500 2510 25.10

Table 2.

The optimal power extracted from the proposed PV modules.

Hour CS5C-90
Bpsx150
CS6P-200
CHSM6610M-235
IM72C3-310-T12B45
Σopt Popt Σopt Popt Σopt Popt Σopt Popt Σopt Popt
6:10 AM 73.5 13.6 75.75 19.9 73.5 31.8 73.5 36.4 73.5 45.9
7:00 AM 62.2 30.7 63.5 50.1 62.2 71.8 62.2 82.3 62.2 103.8
8:00 AM 47.6 52.8 47.3 84.8 47.5 123.6 47.5 141.7 47.5 178.7
9:00 AM 32.6 75.3 36.9 137.1 32.6 176.1 32.6 201.9 32.6 254.7
10:00 AM 23.3 98.5 28.3 182.8 23.34 230.3 23.3 264.0 23.3 333.1
11:00 AM 14.7 113.1 19.2 225.1 14.8 264.5 14.7 303.3 14.7 382.6
12:00 PM 7.2 118.3 13.0 226.6 7.2 276.5 7.2 317.0 7.2 399.9
1:00 PM 14.7 116.6 19.3 217.2 14.6 272.6 14.7 312.6 14.8 394.3
2:00 PM 23.3 103.1 28.2 194.0 23.3 241.0 23.3 276.4 23.5 348.7
3:00 PM 32.6 81.3 36.7 153.8 32.6 190.0 32.6 217.9 32.6 274.9
4:00 PM 49.3 58.5 47.8 98.8 47.6 136.9 47.7 157.0 47.8 198.1
5:00 PM 62.3 35.9 63.5 56.6 62 84.1 62.27 96.4 62.2 121.6
5:50 PM 73.6 16.3 75.8 20.3 73.6 38.2 73.6 43.9 73.6 55.3

Table 3.

A comparison between the optimal cost of the proposed technique and the method proposed by Koutroulis et al. [3].

Study cases Device type
Technique proposed by Koutroulis et al. [3]
Proposed technique by GA
%Cost reduction
PV Charger Battery Optimal no. of PV Optimal no. of batteries Optimal no. of charger Optimal cost ($/wh) Optimal no. of PV Optimal no. of batteries Optimal no. of charger Optimal cost ($/wh)
Case (1) 1 1 1 13 16 6 12.8653 10 12 5 10.1647 −0.1897861
Case (2) 1 1 2 13 40 6 14.2297 11 36 6 11.7964 −0.1710015
Case (3) 1 2 1 13 16 8 12.3263 12 12 7 9.7692 −0.1797016
Case (4) 1 2 2 13 40 8 13.6906 15 32 9 10.7752 −0.2048813
Case (5) 2 1 1 8 16 6 12.7897 9 16 7 11.9896 −0.0562274
Case (6) 2 1 2 8 40 6 14.1541 7 32 5 10.9291 −0.2266386
Case (7) 2 2 1 8 16 7 12.1381 7 16 6 10.0856 −0.1442405
Case (8) 2 2 2 8 40 7 13.5025 8 40 7 11.5752 −0.1354420

According to the proposed technique by Koutroulis et al. [3], the optimal operating case is case (7) which comprises 8 modules of CHSM6610M-235 PV module, 16 batteries of the second type of battery which has nominal capacity of 100 Ah, and 7 chargers of the first type of the battery charger of power rating of 300 W. The optimal cost is 67,488 $ which lead to 12.1381 $/wh. According to the proposed technique, the optimal case is case (3) which comprises 12 modules of Bpsx150PV module, 12 batteries of the second type of battery which has nominal capacity of 100 Ah, and 7 chargers of the first type of the battery charger of power rating of 300 W. The optimal cost is 54,317 $ which lead to 9.7692 $/wh. The proposed method is more optimal than one described by Koutroulis et al. [3] as the obtained minimum cost is due to the proposed technique. Additionally, the analysis described by Koutroulis et al. [3] is built on limited database of PV modules, Batteries, and chargers; so the analysis is based on five types of modules, batteries, and chargers. All the permutations and combinations, 125 cases, are analyzed using both ABC and GA algorithms for each available device. The minimum cost for each PV module using GA is obtained and compared to ABC as given in Table 4. For large available database of the PV system components, the possibility of obtaining a correct optimal solution is valid. Referring to Table 4; it is clear that due to the GA results, the optimal solution is case (5) which comprises 11 PV modules of CS5C-90, 12 batteries of 230 Ah and one charger of 1152 W; the final optimal cost is 7.0237 $/wh which means 1952.6 $ per year. According to ABC algorithm, the optimal solution is the same case of GA, but the optimal cost is 7.0189 $/wh which means 1951.3 $/year. In order to ensure that the load is covered during our analysis, Fig. 9 shows the battery power and the PV array power distribution to cover load during some selected cases. The load is fully covered by the proposed technique during the day. Fig. 10 shows a comparison between the GA and ABC optimal cost at Helwan city. Due to the nature of the bee colony, it can be found in many areas and many locations, so it is important to select another location to perform the proposed methodology. The selected location is Zagazig city located at latitude 30.57N, 31.5E. A comparison of the maximum power extracted from each PV module for two locations is shown in Fig. 11. After the maximum power from each module is obtained, the ABC algorithm is applied to optimal size of the PV system for Zagazig city as shown in Table 5. From Table 5, one can derive that the optimal cost is 7.7104 $/wh in case (28) which means 2143.5 $/year. A comparison between the ABC optimal cost at Helwan city and at Zagazig city is given in Fig. 12. Table 6 shows a comparison of the ABC algorithm controlling parameters for two locations. From the analysis, one can derive that the proposed methodology is applicable for any location.

Table 4.

A comparison between GA and ABC optimal cost @ Helwan city.

Study cases Device type Genetic algorithm solution
ABC Algorithm Solution
% Error
PV module type Battery (Ah) Charger (W) NPV NBatt NCh Cost ($/wh) NPV NBatt NCh Cost ($/wh)
Case (5) CS5C-90 230 1152 12 12 1 7.0237 11 10 1 7.0189 −0.04559
Case (30) Bpsx150 230 1152 9 16 1 9.6621 10 13 1 8.3583 −13.5071
Case (55) CS6P-200 230 1152 6 20 1 10.5286 5 18 1 10.5178 −0.11204
Case (80) CHSM6610M-235 230 1152 6 16 1 9.6527 4 15 1 9.2027 −4.27407
Case (105) IM72C3-310-T12B45 230 1152 3 16 1 9.6394 3 15 1 9.2022 −4.1525

Fig. 9.

Fig. 9

PV array power, battery power, and load power for the first five cases.

Fig. 10.

Fig. 10

A comparison between GA and ABC optimal cost.

Fig. 11.

Fig. 11

A comparison of the maximum power extracted from each module for two locations.

Table 5.

A comparison between GA and ABC optimal cost @ Zagazig city.

Study cases Device type Genetic algorithm solution
ABC Algorithm Solution
% Error
PV module type Battery (Ah) Charger (W) NPV NBatt NCh Cost ($/wh) NPV NBatt NCh Cost ($/wh)
Case (5) CS5C-90 230 1152 13 14 1 8.7777 11 12 1 7.8935 −8.0089
Case (28) Bpsx150 230 288 10 14 5 9.1763 7 11 4 7.7104 −13.2775
Case (60) CS6P-200 100 1152 8 40 1 11.0399 6 38 1 10.6004 −3.9816
Case (80) CHSM6610M-235 230 1152 6 16 1 10.5525 6 17 1 10.1025 −4.0761
Case (105) IM72C3-310-T12B45 230 1152 4 17 1 10.0933 3 16 1 9.6394 −4.1120

Fig. 12.

Fig. 12

A comparison of the ABC optimal cost for two locations.

Table 6.

The controlling parameters of ABC algorithm for two locations.

@ Helwan city @ Zagazig city
The number of colony size 20 26
The number of food sources 10 13
The number of trial 100 100
The number of cycles 1000 1500

Conclusions

The major aspects which must be taken in consideration in designing a PV power generation systems are reliability and achieve a minimum cost. The past PV system sizing methods suffer the disadvantages of insufficient database of the PV system components, and they did not take into account some affecting aspects such as tilt angle, number of batteries and chargers. In this paper, a new technique for the optimal sizing of stand-alone PV system has been presented and solved by a new optimization technique Artificial Bee Colony (ABC) algorithm. The purpose of the proposed methodology is to support the selection the optimal number and type of PV modules, and PV battery chargers, the PV modules tilt angle and the battery type and nominal capacity to supply a residential household. Two objective functions are presented: the first is the PV module power which is to be maximized and the second is the life cycle cost (LCC) which is to be minimized. The analysis is performed based on real solar radiation and ambient temperature measured at Helwan city, Egypt. The result of ABC algorithm is compared to GA optimal solution. The simulation results show that the ABC algorithm is more efficient than GA in obtaining the optimal cost of the PV system to cover a load at any location.

Conflict of interest

The authors have declared no conflict of interest.

Footnotes

Peer review under responsibility of Cairo University.

References

  • 1.Shrestha G.B., Goel L. A study on optimal sizing of stand-alone photovoltaic stations. IEEE Trans Energy Convers. 1998;13(4):373–378. [Google Scholar]
  • 2.Maghraby H.A.M., Shwehdi M.H., Al-Bassam G.K. Probabilistic assessment of photovoltaic (PV) generation systems. IEEE Trans Power Syst. 2002;17(1):205–208. [Google Scholar]
  • 3.Koutroulis E., Kolokotsa D., Potirakis A., Kalaitzakis K. Methodology for optimal sizing of stand-alone photovoltaic/wind-generator systems using genetic algorithms. Sol Energy. 2006;80:1072–1088. [Google Scholar]
  • 4.Lalwani M., Kothari D.P., Singh M. Size optimization of stand-alone photovoltaic system under local weather conditions in India. Int J Adv Eng Res. 2011;1(4):951–961. [Google Scholar]
  • 5.Abdulateef J, Sopian K, Kader W, Bais B, Sirwan R, Bakhtyar B, et al. Economic analysis of a stand-alone PV system to electrify a residential home in Malaysia. In: Advances in fluid mechanics and heat & mass transfer conference; 2012. p. 169–74.
  • 6.Javadi MR, Mazlumi K, Jalilvand A. Application of GA, PSO and ABC in optimal design of a stand-alone hybrid system for north-west of Iran. In: ELECO 2011 7th international conference on electrical and electronics engineering, Turkey.
  • 7.Kirmani S., Jamil M., kumar C., Jamil A.M. Techno economic feasibility analysis of a stand-alone PV system to electrify a rural area household in India. Int J Eng Sci Technol. 2010;2(10):5231–5237. [Google Scholar]
  • 8.Arun P., Banerjee R., Bandyopadhyay S. Optimum sizing of photovoltaic battery systems incorporating uncertainty through design space approach. Sol Energy. 2009;83:1013–1025. [Google Scholar]
  • 9.Fragaki A., Markvart T. Stand-alone PV system design: results using a new sizing approach. Renew Energy. 2008;33:162–167. [Google Scholar]
  • 10.Posadillo R., Luque L.R. Approaches for developing a sizing method for stand-alone PV systems with variable demand. Renew Energy. 2008;33:1037–1048. [Google Scholar]
  • 11.Karaboga D., Akay B. A survey: algorithms simulating bee swarm intelligence. Artif Intell Rev. 2009;31(1):68–85. [Google Scholar]
  • 12.Kaur A., Goyal S. A survey on the applications of bee colony optimization techniques. Int J Comput Sci Eng. 2011;3(8):3037–3046. [Google Scholar]
  • 13.Karaboga D., Akay B. A comparative study of artificial bee colony algorithm. Appl Math Comput. 2009;214:108–132. [Google Scholar]
  • 14.Karaboga D., Ozturk C. A novel clustering approach: Artificial Bee Colony (ABC) algorithm. Appl Soft Comput. 2011;11(1):652–657. [Google Scholar]
  • 15.Karaboga D., Ozturk C., Karaboga N., Gorkemli B. Artificial bee colony programming for symbolic regression. Inf Sci. 2012;209:1–15. [Google Scholar]
  • 16.Karaboga D., Basturk B. A powerful and efficient algorithm for numerical function optimization: artificial bee colony (ABC) algorithm. J Global Optim. 2007;39(3):459–471. [Google Scholar]
  • 17.Gilbert M. John Wiley & Sons, Inc.; Hoboken, New Jersey: 2004. Renewable and efficient electric power systems. [Google Scholar]
  • 18.Othman AM, El-arini MM, Ghitas A, Fathy A. Realworld maximum power point tracking simulation of PV system based on fuzzy logic control. NRIAG, 8–11 October 2012, Helwan, Cairo, Egypt.
  • 19.Borowy B.S., Salameh Z.M. Methodology for optimally sizing the combination of a battery bank and PV array in a wind/PV hybrid system. IEEE Trans Energy Convers. 1996;11(2):367–373. [Google Scholar]
  • 20.Holland J.H. University of Michigan Press; Ann Arbor: 1975. Adaptation in natural and artificial systems. [Michigan; re-issued by MIT Press 1992] [Google Scholar]

Articles from Journal of Advanced Research are provided here courtesy of Elsevier

RESOURCES