Skip to main content
Data in Brief logoLink to Data in Brief
. 2018 Feb 16;17:1320–1325. doi: 10.1016/j.dib.2018.02.035

Data exploration on factors that influences construction cost and time performance on construction project sites

Lekan M Amusan a,, Adedeji Afolabi a, Raphael Ojelabi a, Ignatius Omuh a, Hilary I Okagbue b
PMCID: PMC5988424  PMID: 29876486

Abstract

This data article explores the factors that contribute to maintaining steady cost projection on construction projects. The data was obtained using structured questionnaire designed in Likert scale. The responses were solicited from category of construction practitioners. Simple random sampling was employed in the distribution of the questionnaires to the respondents. Data samples were analysed using severity index, ranking and simple percentages. The analysis of the data brought to fore some important data on factors that causes cost overrun, they include: contractor's inexperience, inadequate planning, inflation, incessant variation order, and change in project design. They are critical to causing cost overrun, while project complexity, shortening of project period and fraudulent practices are found to be responsible. The data fall within the percentages of possible consequences of cost overrun when compared with those available in scientific literature. The data can provide insights on how to mitigate the risks of project deviation from initial cost and as-built project.

Keywords: Likert scale, Questionnaire, Construction, Cost overrun, Severity index, Survey, Statistics


Specifications Table

Subject area Building Construction
More specific subject area Construction Management
Type of data Table, text file.
How data was acquired Field survey
Data format Raw, filtered and analyzed data
Experimental factors Simple percentages and severity index were used as analytical tool of the generated data. SPSS (Statistical Packages for Social Science Students) was used in determining the nature, strength and pattern of relationships among the cost determinants and variables. The factors were ranked in order of their degree of severity.
Experimental features The key method used in data collection structured questionnaire designed in Likert scale, the questionnaire was designed in such a way that it helps to collate basic information from the respondents. A population size of seventy (70) was selected, and a total sample size of 59 respondents was used in data generation, with questionnaire distributed to construction professionals. Variables pertaining to the above listed targets were identified and incorporated into questionnaires as the primary source of data. The data was collated and analysed, using mean item score ranking, percentages and descriptive statistics.
Data source location Covenant University, Ota, Nigeria
Data accessibility The article is in public repository http://eprints.covenantuniversity.edu.ng/

Value of the data

  • i.

    The data is useful in research that involves studying cost performance of construction projects.

  • ii.

    Data presented is useful in studying cost overrun that would help client and professional in project cost planning.

  • iii.

    The data could be used in development of cost and time models.

  • iv.

    The data is valuable to construction project professionals and could be used in policy formulation.

  • v.

    The data could be used as basis of comparison with that of other countries in terms of project management.

1. Data

The data was obtained using structured questionnaire designed in Likert scale. The responses were solicited from category of 70 construction practitioners using survey sampling methodology. The data retrieved from the 70 practitioners are presented as follows: data of professional affiliation of respondents is presented in Table 1, data on years of experience (Table 2), data on economic sector where they belonged (Table 3), data on procurement methods used by the respondents (Table 4) and time data on period of cost overrun experienced by them in executing construction projects (Table 5).

Table 1.

Data profession of respondents.

Professional cadre of respondents Frequency Percentage
Architect 20 29.9
Builders 15 22.4
Engineers 15 22.39
Quantity Surveyor 10 14.9
Estate Surveyor 10 10.45
Total 70 100

Table 2.

Data on respondents’ years of experience.

Years of experience Frequency Percentage
Above 10yrs 30 42.8
225-10yrs 20 28.6
1–5yrs 17 24.3
Missing data 3 4.3
Total 70 100

Table 3.

Data on economic sector of the respondents.

Economy Sector Frequency Percentage
Private sector 47 67.1
Public sector 20 28.6
Missing data 3 4.3
Total 70 100

Table 4.

Data of procurement methods used by the respondents.

Procurement methods Frequency Percentage
Traditional method 3 4.3
Project management 6 8.5
Direct labor 10 14.3
Design and build 20 28.6
Labor only contract 28 40.0
Missing data 3 4.3
Total 70 100

Table 5.

Data on period of cost overrun experienced on projects.

No of Years Frequency Percentage
Above 2Yrs 0 0.00
1–2 years 2 2.9
6months-1year 21 30.0
Below 6months 39 55.7
Missing data 8 11.4
Total 70 100

Furthermore, severity index was used to obtain the ranks of cost-overrun determinants presented in Table 6. The data on impact of cost and time on project performance is shown in Table 7. The cost and time overrun survey information data on residential building projects are shown in Table 8 while the data is in agreement with those available in scientific literature as regards to the consequence of cost overrun.

Table 6.

Data on determinants of cost overrun on construction projects.

Cost-overrun determinants C.R. {5} R {4} J.R {3} IRR {2} V.R {1} S.I % R.K
Contractors Project inexperience 42 22 30 0 0 91.60 1
Inadequate planning 45 15 7 0 0 91.34 2
Inflation 42 20 5 0 0 91.00 3
Incessant variation order 44 16 6 1 0 90.70 4
Change in project design 43 17 7 0 0 90.70 4
Project complexity 42 20 3 2 0 90.40 6
Shortening of contract period 44 14 9 0 0 90.40 6
Fraudulent practices 42 18 7 0 0 90.40 6
Unstable economy 42 25 10 0 0 89.55 9
Inaccurate estimate 40 15 12 0 0 88.44 10
Overdesign 40 18 6 3 0 88.40 10
Project site location 35 25 5 1 1 88.05 12
Delay from employer 39 16 11 1 0 87.76 13
Force Majeure 30 25 11 1 0 85.10 16
Material Price fluctuations 30 18 19 0 0 83.30 14
Site conflicts 30 20 12 3 2 83.00 15
Poor workmanship 30 17 20 0 0 83.00 16
Inadequate financial provision 29 17 20 0 1 82.1 17
Contractors inefficiency 30 20 10 6 1 82.09 18
Unsteady material supply 30 15 20 2 0 81.80 19
Unpredictable weather condition 30 17 17 1 0 80.90 19
Breach of local regulation 25 22 11 8 1 79.10 20
Lack of executive capacity by employer 7 10 20 0 0 58.20 21

C.R= Completely relevant, J=Just relevant, IRR= Irrelevant, VR= Very Relevant, R.I= Relevant Index.

R.K= Ranking

Table 7.

Data of impacts of time and cost on project performance.

Effects R.A.I Rank
Time overrun 0.796 1
Tied-up Capital 0.772 2
Loss of investment 0.756 3
Materials are effectively put to use 0.728 4
High tendency for the occurrence of dispute between the clients and contractors. 0.724 5
Project abandonment. 0.704 6
Excessive increase on the entire project cost. 0.656 7
Client's dis-satisfaction 0.640 8
Profit loss. 0.632 9
Consultant dissatisfaction 0.632 9
Payment delay 0.628 11
Good completion time 0.616 12
Maximized project profit 0.600 13
Reduced building component quality. 0.576 14
High level of material wastage 0.528 15

R.A.I= Relative Agreement Index

Table 8.

Data of cost and time overrun survey information on residential building projects.

Assessment Statements Architect Builder Structural Quantity surveyor
I have been involved in a building project before 30% 40% 10% 10%
I have experienced extension in project delivery time 20% 50% 17% 13%
Length Of Extension
 1–6 months 0.89(i) 0.87(i) 0.85(ii) 0.86(i)
 6–12 months 0.84(vi) 0.86(ii) 0.86(i) 0.83(ii)
 12–18months 0.85(v) 0.85(iii) 0.82(iv) 0.82(iii)
 18–24 months 0.87(iii) 0.85(iii) 0.84(iii) 0.81(iv)
 More than 24 months 0.86(iv) 0.83(iv) 0.78(v) 0.82(iii)
I have experienced cost overrun in a building project


 

 

 

 


Percentage Of Increase
 0–15% 0.78(vi) 0.65(vi) 0.66(vi) 0.65(vi)
 15–30% 0.79(v) 0.76(iv) 0.73(v) 0.72(v)
 30–45% 0.80(iv) 0.85(ii) 0.85(ii) 0.89(i)
 45–60% 0.82(ii) 0.89(i) 0.87(i) 0.88(ii)
 60–80% 0.81(iii) 0.71(v) 0.78(iii) 0.75(iv)
 80% and above 0.83(i) 0.75(iii) 0.76(iv) 0.79(iii)

2. Experimental design, materials and methods

2.1. Data collection

Simple random sampling was used in the data collection through carefully structured questionnaire. A population size of seventy (70) was selected, and a total sample size of 59 respondents was used in this study, with questionnaire distributed to construction professionals. Variables pertaining to the above listed targets were identified and incorporated into questionnaires as the primary source of data. Some similar methods and contributions can be seen in [1], [2], [3], [4], [5], [6], [7], [8].

2.2. Data analysis

The data was collated and analysed, using mean item score ranking, percentages and the use of descriptive statistics. Cost overrun determinants were ranked in percentages using the severity index. The five-scale in the questionnaire forms the response variables which are mapped with the 23 cost overrun determinants to obtain the severity index. The five-scale response variables are listed with the assigned ranks: completely relevant (CR) is ranked 4, relevant is ranked 3, just relevant is ranked 2 and irrelevant is ranked 1. The summary is shown in Table 6.

Relative agreement index (RAI) is used to obtain the rank of 15 variables that determine the impact of cost and time on project performance. This is presented in Table 7.

The construction practitioners’ experiences on project cost overrun and duration were ranked distinctly and shown in Table 8. This enables for quick comparison and decision making.

The data composition is in agreement with those available in scientific literature as regards to the consequence of cost overrun. This is summarized in Table 9. The selected works relevant and similar can be found in [9], [10], [11], [12], [13], [14], [15], [16], [17], [18], [19], [20], [21].

Table 9.

Data of consequences of cost overrun.

Effects of Cost overrun. Percentage
Tying down of clients capital 80%
Company/firms liability to insolvency 50%
Liability of companies or firms to bad debt or bankruptcy 70%
Under-utilization of manpower resources 55%
Tendency for an increase project cost resulting from payments for idle and unproductive time arising out of contractors claims. 93%
Tendency for an increase project cost resulting from payments for idle and unproductive time 90%
Projects abandonment 60%
Under-utilization of plants and equipment 93%

Acknowledgements

The support of Covenant University Centre for Research and Innovation (CUCRID), Covenant University is acknowledged for sponsoring this research.

Footnotes

Transparency document

Supplementary data associated with this article can be found in the online version at doi:10.1016/j.dib.2018.02.035.

Transparency document. Supplementary material

Supplementary material

mmc1.pdf (19.4KB, pdf)

.

References

  • 1.Amusan L.M., Dosunmu D., Opeyemi J. Int. J. Mech. Eng. Technol. 2017;8(10):918–927. [Google Scholar]
  • 2.Odusami K.T., Olusanya O.O. Clients contribution to delays on completion cost of housing projects in Nigeria. Quant. Surv. 2000;30:31–44. [Google Scholar]
  • 3.Ogunsemi D.R., Jagboro G.O. Time-cost model for building projects in Nigeria. J. Constr. Manag. Econ. 2006;24:253–258. [Google Scholar]
  • 4.Okagbue H.I., Opanuga A.A., Adamu M.O., Ugwoke P.O., Obasi E.C.M., Eze G.A. Personal name in Igbo Culture: a dataset on randomly selected personal names and their statistical analysis. Data Brief. 2017;15:72–80. doi: 10.1016/j.dib.2017.08.045. [DOI] [PMC free article] [PubMed] [Google Scholar]
  • 5.Bishop S.A., Owoloko E.A., Okagbue H.I., Oguntunde P.E., Odetunmibi O.A., Opanuga A.A. Survey datasets on the externalizing behaviors of primary school pupils and secondary school students in some selected schools in Ogun State, Nigeria. Data Brief. 2017;13:469–479. doi: 10.1016/j.dib.2017.06.025. [DOI] [PMC free article] [PubMed] [Google Scholar]
  • 6.Iroham C.O., Okagbue H.I., Ogunkoya O.A., Owolabi J.D. Survey data on factors affecting negotiation of professional fees between Estate Valuers and their clients when the mortgage is financed by bank loan: a case study of mortgage valuations in Ikeja, Lagos State, Nigeria. Data Brief. 2017;12:447–452. doi: 10.1016/j.dib.2017.04.047. [DOI] [PMC free article] [PubMed] [Google Scholar]
  • 7.Popoola S.I., Atayero A.A., Faruk N., Badejo J.A. Data on the key performance indicators for quality of service of GSM networks in Nigeria. Data Brief. 2018;16:914–928. doi: 10.1016/j.dib.2017.12.005. [DOI] [PMC free article] [PubMed] [Google Scholar]
  • 8.Tunji-Olayeni P.F., Lawal O.P., Amusan L.M. Developing infrastructure in Nigeria: why is the cost so high? Medit. J. Soc. Sci. 2013;3(12):257–263. [Google Scholar]
  • 9.Ashworth A. Cost Studies of Building. Second ed. Longman Scientific and Technical; Harlow. England: 1994. [Google Scholar]
  • 10.Bathurst P.E., Butler D.A. Building Cost Control Techniques and Economics. Second Edition. Heinemann; London: 1980. [Google Scholar]
  • 11.Dissanayaka S.M., Kumaransammy M.M. Comparing Contributory Time and Cost Performance in building projects. Build. Environ. 1999;31(6):569–578. [Google Scholar]
  • 12.Ferry D.J., Brandon P.S., Ferry J.D. Cost Planning of Building. Seventh ed. Blackwell Science Limited; Hosney Mead. London: 1998. [Google Scholar]
  • 13.Harris J.O., MacCaffer R. Modern Construction Management. Iowa State Press. Fifth ed. Blackwell Publishing Company; Ames, Iowa.USA: 2005. [Google Scholar]
  • 14.Jagboro G.O. An evaluation of the factors that cause delays on construction project in Nigeria. Afr. J. Dev. Stud. 1998;1(1-2):105–114. [Google Scholar]
  • 15.Kerzner H.C. Project Management. Sixth ed. John Wiley and Sons. Incorporated; Canada: 1998. [Google Scholar]
  • 16.Love P.E.D., Tse R.Y.C., Edwards D.J. Time-Cost relationship in Australian building construction projects. Niger. J. Constr. Manag. 2005;2(1):81–86. [Google Scholar]
  • 17.Majid M.Z.A. Factors of non-excusable delays that influence contractor's performance. J. Magt. Enginee. 1998;14(3):42–44. [Google Scholar]
  • 18.Mawdesley M., Askew W., O’Reilly M. Longman Publishers; Berkshire. London: 1997. Planning and Controlling Construction Projects. [Google Scholar]
  • 19.Mbachu J.K., Olaoye G.S. Analysis of major delay factors in building project execution. Niger. J. Constr. Manag. 1999;2(1):81–86. [Google Scholar]
  • 20.Pilcher R. Preicioles of Construction Management. 3rd ed. McGraw-Hill Books Company; Berkshire. England: 1992. [Google Scholar]
  • 21.Skitmore R.M., Ng S.T. Forecast model for actual construction time and cost. Build. Environ. 2003;8(8):1075–1089. [Google Scholar]

Associated Data

This section collects any data citations, data availability statements, or supplementary materials included in this article.

Supplementary Materials

Supplementary material

mmc1.pdf (19.4KB, pdf)

Articles from Data in Brief are provided here courtesy of Elsevier

RESOURCES