Abstract

Urban sanitation in growing cities of the Global South presents particular challenges. This led to the Bill & Melinda Gates Foundation’s Reinvent The Toilet Challenge, which sparked the development of various non-sewered sanitation technologies like the Nano Membrane Toilet. Complex disruptive technologies like this entail an extensive product development process, including various types of prototype tests. While there is an abundance of literature discussing how to build prototypes, and the optimal number of tests, there has been little focus on how to plan and conduct tests, especially in a development endeavour of this complexity. Four approaches to testing are reviewed, and their strengths and weaknesses compared. A visualised testing strategy is proposed that encompasses the entire product development process and can be used to plan and communicate prototype tests for the Nano Membrane Toilet to ultimately achieve compliance with international standards.

Keywords: prototyping, reinvent the toilet, testing, waterless sanitation

Abbreviations

ALT – Accelerated Life Testing; BMGF – Bill and Melinda Gates Foundation; CAE – Computer Assisted Engineering; DOE – Design Of Experiments; HALT – Highly Accelerated Life Testing; NMT – Nano Membrane Toilet; PD - Product Development; RTTC – Reinvent The Toilet Challenge; TRL – Technology Readiness Level; UCD - User Centred Design; UDDT – Urine Diversion Dry Toilet

Introduction

Sanitation, the containment, transport, and treatment of human excrements, is a topic of high significance for human development ( Jahan, 2016): UNICEF (2017) stress the importance of safe sanitation for children’s health and that improving (access to) sanitation could reduce child mortality. Lack of sanitation has been linked to reduced cognitive development in children ( Sclar et al., 2017) as well as stunting, caused by environmental enteric dysfunction ( Budge et al., 2019), and to a risk of assault, particularly for women and girls practicing open defecation ( Jadhav et al., 2016; Miiro et al., 2018).

Urban sanitation poses particular difficulties, due to the lack of piped water and prohibitively high cost of sewer systems ( Cobbinah & Poku-Boansi, 2018; Parnell et al., 2007). The most commonly promoted sanitation systems in cities of the Global South involve toilets that use little to no water, i.e. dry toilets, and store the faecal material onsite. Examples of this are pit latrines, pour-flush toilets, urine-diversion dry toilets (UDDT), and septic tanks ( Semiyaga et al., 2015). When full, these toilets are emptied, and the faecal sludge is transported and either treated and reclaimed or discharged, or discharged without treatment. However, there are problems with these sewer-less sanitation services, such as high fees for emptying services, collection and transport trucks not being able to access the houses, high transport costs to treatment facilities or the altogether lack of such facilities ( Strande, 2014). Another obstacle for the success of these technologies is public acceptance: Users can consider the pedestals of dry toilets uncomfortable, dirty, or malodorous, and they may worry their children could fall into the pit ( Roma et al., 2013; Mkhize et al., 2017).

To find a solution to these problems, the Bill & Melinda Gates Foundation (BMGF) initiated the Reinvent The Toilet Challenge (RTTC) to “create a toilet that:

  • -

    Removes germs from human waste and recovers valuable resources such as energy, clean water, and nutrients,

  • -

    Operates “off the grid” without connections to water, sewer, or electrical lines,

  • -

    Costs less than US$0.05 per user per day,

  • -

    Promotes sustainable and financially profitable sanitation services and businesses that operate in poor, urban settings, [and]

  • -

    Is a truly aspirational next-generation product that everyone will want to use – in developed as well as developing nations.”

As result, research institutions and companies worldwide are now developing waterless, non-sewered sanitation technologies ( Bill & Melinda Gates Foundation, 2013) which have been praised as a form of disruptive innovation in the field of environmental research ( Sedlak, 2018). The reinvention of the toilet requires unconventional thinking. Niemeier et al. (2014) discuss the challenges of building technologies for the development context: “If we are to resolve global inequities in access to innovations that improve health, we must adopt new approaches to engineering design that reflect the unique needs and constraints of low-resource settings”. They further mention how “efforts like the [RTTC] reflect the kind of integrative thinking that must occur at the beginning of a design initiative […]”. One example of a reinvented toilet is the Nano Membrane Toilet (NMT), conceived by researchers at Cranfield University ( Parker, 2014). It uses combustion and membrane processes to treat the mechanically separated solid and liquid waste streams ( Figure 1). With all its components, the NMT would not just replace the currently existing dry toilet technologies, but also the associated faecal sludge management services, thus offering a form of safely managed sanitation ( WHO & UNICEF, 2017). It is not simply a human waste receptor, but rather a miniature faecal sludge treatment facility.

Figure 1. Conceptual schematic of the NMT and its components.

Figure 1.

The front end comprises the mechanical flush with its rotating bowl and rubber swipe, the collection tank with the grid and weir and the screw conveyor. The back end consists of the dryer, the combustor, and the membrane bundles.

Naturally, there are numerous considerations to be made during the development of such a technology. The NMT combines entirely novel technologies with already existing ones. However, even for the well-established technologies, their application for this specific purpose is novel, and requires further research in order to miniaturise, integrate and optimise for off-grid functionality. At the same time, from a user’s perspective, not much should change when transitioning from using another dry toilet or a porcelain flush toilet to the NMT. To fulfil the RTTC’s demand for an aspirational design ( Bill & Melinda Gates Foundation, 2018), it should be comfortable, appealing, and simple to use. It should take into account the preferences and customs of users from a diverse range of cultural backgrounds. Fejerskov (2017) emphasizes the importance of considering the users of a newly developed technology: “[…] a technology developed in isolation from those who are supposed to benefit from it cannot be expected to wield predictable outcomes.” There is research on the preferences of toilet users in various contexts, from industrial nations like the Republic of Korea ( Lee, 2019) and Canada ( Morales et al., 2017), to a focus on elderly users ( Dekker et al., 2011) to low- and middle income countries ( Nelson et al., 2014; Austin-Breneman & Yang, 2017). Hence, developing the NMT entails developing a user-friendly user interface—in software development projects this would be called “front end” ( Reza & Grant, 2007)—and a “back end” comprising several sub-technologies, and integrating them into the overall system.

The RTTC has thus led to an unusual case of product development (PD) at this scale: It asks for a product that connects existing notions of a toilet’s function and design with never-before-seen technologies. A viable solution to the problems associated with dry sanitation must simultaneously satisfy users’ ideas of aesthetics and comfort, and adhere to high standards of safety and reliability. To achieve this goal, fundamental research and creative design techniques have to be performed in combination, and testing of physical prototypes is a crucial part of this process ( Tahera et al., 2015). For example, Larsen et al. (2016) acknowledge that, for technologies addressing the “water challenges of an urbanizing world”, “technologies should be tested in a broad variety of experimental settings to ensure robustness, cost-effectiveness, social acceptance, and the wide applicability of alternative solutions.”

Ulrich & Eppinger, 2016 define a prototype very broadly as “an approximation of the product along one or more dimensions”. They furthermore identified four purposes of prototypes: learning, communication, integration, and milestones. In the context of prototype testing, the main purpose considered is learning. For example, Tronvoll et al. (2017) write about the use of prototypes: “A prototype experiment often targets generating knowledge about different attributes of a proposed design which is not identified by simple reflection.” These tests, like most activities in PD processes, can be seen as risk-reduction tasks ( Keizer & Halman, 2009; Unger & Eppinger, 2011). Prototypes can also be categorised by how closely they resemble the final product, i.e. their fidelity ( Mccurdy et al., 2006). Another important distinction of different categories of prototypes is between virtual and physical prototypes, and while the use of virtual prototypes, or simulations, has increasingly gained importance in the past decades ( Tahera et al., 2014), this paper is focused on the testing of physical prototypes, as opposed to “the solution of analytical models and numerical approximations” ( Boës et al., 2017).

There is ample literature advising on how to design and build prototypes according to testing needs (e.g. Camburn et al., 2015; Menold et al., 2017), and testing strategies that aim to optimise the time and number of prototype tests (e.g. Al Kindi & Abbas, 2010; Qian et al., 2010; Thomke & Bell, 2001). However, the question of how to test prototypes is seldom answered ( Tahera et al., 2015). Batliner et al. (2018), for instance, complain about the under-representation of general testing methodology in engineering literature impeding it’s integration into an engineering design curriculum. The planning of prototype testing, and communicating these plans, can therefore be difficult in the multi-disciplinary groups working on a PD project like for the NMT. While types of testing like user-centred design (UCD) ( Unger Unruh & Canciglieri Junior, 2018), design of experiments (DOE) ( Ilzarbe et al., 2008), Reliability Testing ( Bhamare et al., 2007; Zhang et al., 2014) and testing for international standard compliance ( Shin et al., 2015; Tyas, 2009) are well understood in their respective fields, a synthesis of these approaches could be used to develop a unified testing strategy for the NMT. This would require a holistic understanding of what each approach aims to learn from its tests, how each approach conducts and designs tests, and how the different approaches can be consolidated to amplify their strengths and reduce their weaknesses.

Keller et al. (2006) discuss the difficulties faced by people developing large and complex products keeping an overview over the entire project and communicating their work to colleagues. They propose an improved way to visualise design processes to overcome this problem. Similarly, a visualised strategy that achieves synergy of testing approaches could be useful in planning and communicating testing efforts for the development of a complex disruptive technology like the NMT. The result could be more effective tests yielding more valid and useful data, as well as an increase in efficiency throughout the PD process.

This paper aims to review four testing approaches to then propose a visualised testing strategy, as a tool to facilitate planning and communication of prototype testing for the development of the NMT.

Methods

Using our own publications and those of our colleagues on the project, the development history of the NMT was established and outlined in the section below. Subsequently, the Scopus and Google Scholar databases were used for an exploratory search of peer reviewed literature, with a focus on literature reviews covering a range of publications, to advance the understanding of the broad field of prototype testing in PD. Search terms included review, prototyping, prototype testing, product development, technology development, testing, disruptive technology, and others. Using these terms in various combinations, promising publications were identified and studied individually. The sections ‘Testing of Prototypes’ and ‘Phases of the product development process’ were composed using the information from this initial search. In the search, four repeatedly occurring approaches to testing were identified and then further investigated in a more targeted search on the same databases. Again, the focus was on reviews of the existing literature rather than original work, as the aim was to obtain a wide understanding of multiple fields of study, rather than an in-depth analysis of a single one. Similar search terms were used, with the addition of the terms ‘user centred design’ OR ‘UCD’, ‘Reliability’, ‘technical standard’ OR ‘international standard’, and ‘design of experiments’ OR ‘DOE’, with the term ‘OR’ being a Boolean operator. The identified literature on the four approaches to testing was then analysed to extract the information relevant to prototype testing activities, particularly for the development of disruptive technologies. This analysis ultimately resulted in the condensed information collected in Table 2. Furthermore, during both stages of literature search, the topics of iteration, distinction into back end and front end, and visualisations of PD processes were identified as recurring themes and summarised in the respective sections.

Table 1. Technology readiness levels.

Table adapted from NASA (2016).

TRL 9 TRL 8 TRL 7 TRL 6 TRL 5 TRL 4 TRL 3 TRL 2 TRL 1
Actual system “flight proven” through successful mission operations Actual system completed and “flight qualified ”through test and demonstration (ground or flight) System prototype demonstration in a target/space environment System/subsystem model or prototype demonstration in a relevant environment (ground or space) Component and/or breadboard validation in relevant environment Component and/or breadboard validation in laboratory environment Analytical and experimental critical function and/or characteristic proof-of-concept Technology concept and/or application formulated Basic principles observed and reported
System/subsystem development Technology development Basic technology research
System test, launch, and operations Technology demonstration Research to prove feasibility

Table 2. Summary of the four presented testing approaches applicable in product development (PD).

Approach Aims Test procedure Strengths Weaknesses
DOE Design test protocols to maximise statistical validity of information obtained from a minimal amount of tests conducted. Using the basic principles of DOE, and modern variations thereof, an experimental plan is developed and its results are analysed. High statistical validity and efficiency, applicable across disciplines. Focus on preparation and analysis of tests, rather than what is tested, and why. Statistical validity can give false credibility to methodology.
Reliability Testing Determine a product’s time to/ likelihood for failure to give estimates/ guarantees of its functionality space with regard to load and time Loads/ stresses are simulated on the product – or its components – often accelerated or with increased intensity, and often on several units. The failure points, -times and –frequencies are determined and a reliability metric is calculated. Allows highly reliable guarantees for performance, can be used to identify weak points of the design, material, etc. Does not consider the user experience.
Complex failure modes may not be detected easily.
Standard compliance testing Ensure safety and (inter-)national usability of a product. Ensure a minimum level of performance for a class of products. Detailed descriptions are given of how to conduct the tests and sets requirements for the performance levels in the tests. Highly specified procedures,
Set out requirements for design-brief can be used as go/no-go criterion for decision between competing designs
Doesn’t necessarily account for statistical variation,
May restrict innovative solutions to problems
Testing for UCD Ensure the product is designed for the user, accounts for their preferences and practices, and appeals to their sense of aesthetics The product’s prototypes of increasing fidelity are tested on users, throughout the development process, their responses are recorded and considered in the next iteration step. Adaptable to the realities of the PD process, identifies developers’ misconceptions and blind spots; iterative nature of approach ensures continuous improvement of prototypes while allowing for changes of previous design choices Rarely statistically relevant sample sizes, user preferences and technical possibilities may be incompatible

DOE, design of experiments; UCD, user-centred design.

A visualisation of the prototype testing processes for the PD of the NMT was then conceived, with the aim to consolidate the collected information. A simple linear PD process model was chosen, divided into three phases, with parallel strands of testing for the front end and back end, and possible iteration loops between different stages of the process. The four approaches to testing were matched to the stages, depending on their identified strengths and weaknesses.

The NMT: a case of complex product development

The NMT is a household-level, onsite sanitation system that looks similar to a porcelain water flush toilet ( Figure 1 and Figure 2). It is a highly complex technology, which is, in fact, a combination of subsystems that have to be developed individually and then integrated into the overall system.

Figure 2. Nano Membrane Toilet front-end prototype.

Figure 2.

The original design brief for the NMT was the RTTC, which included important user-centred objectives of aspirational design and affordability, as well as objectives aiming at sustainability and at solving the problems of urban non-sewered sanitation ( Bill & Melinda Gates Foundation, 2013). From this, initial design ideas were conceived involving membrane treatment of liquids and water recovery through condensing beads, as well as the drying and coating of solids ( Parker, 2014). Later design stages discarded the condensing beads and a combustion process was devised to replace the coating of solids. Considering that the user of the toilet would usually not interact with the treatment processes, these were not subjected to user testing. The pedestal, the toilet’s part with which the user interacts, mainly differs from a porcelain water flush toilet in its mechanical flush. It was developed as the result of studies among potential users in Ghana and subsequent agile innovation processes ( Tierney, 2017). Several iterations of prototypes were produced to develop a mechanical flush, until it could be tested in real-use scenarios.

This mechanical flush – a rotating bowl and rubber swipe activated by moving the toilet lid – separates the user from a tank underneath the toilet pan ( Tierney, 2014; Tierney, 2017). Solids are separated through settling and displacement, transported by an screw conveyor ( Mercer et al., 2016) and subsequently dried and combusted ( Fidalgo et al., 2019; Onabanjo et al., 2016), while the liquid fraction is extracted through a weir and purified through membrane processes ( Kamranvand et al., 2018; Wang et al., 2017), driven by the heat of the combustion, which is transferred via a heat exchanger ( Hanak et al., 2016). The toilet pedestal, including the mechanical flush, the screw conveyor, and the liquid weir are considered the NMT’s front end. The dryer, combustor, and membrane components are considered its back end. The NMT is envisioned to be independent of water- or sewer connections and energy neutral, or even have a positive net power output ( Kolios et al., 2018). However, the back-end components have not yet been integrated and combined with the front end to produce a fully functioning prototype of the NMT. Such tasks are envisioned to be conducted in the near future.

At the moment, all subsystems of the NMT are in an iterative phase of building and testing prototypes. The front end has been re-designed as result of field tests involving target users of the NMT ( Hennigs et al., 2019). Prototypes of the dryer (Kentrotis et al., in preparation) and combustor ( Jurado et al., 2018) have been tested in the lab in several iterations. In addition, the recovery of electrical energy by reverse electro-dialysis is under investigation (Hulme et al., in preparation).

This means that the individual components and subsystems of the NMT are developed enough to plan for integration of all subsystems to a complete system-prototype. Such a prototype would then be tested in laboratory tests, and once its safe operation was sufficiently proven, it could be deployed for user-centred field tests. The aim of such tests, and concurrent further subsystem improvements, would be to optimise the operational settings of the entire system. The recently published ISO 30500 standard ( ISO, 2018) could provide the benchmark performance values the prototype has to achieve. Once the prototype meets these values, its design can be polished for usability and manufacture. Final reliability and user tests of this polished design would ensure the NMTs usability and reliable functionality throughout its lifetime, and when passed, allow this design to confidently be tested for ISO 30500 standard-compliance, making it a market-ready product.

Consequently, there are still numerous prototype tests which need to be planned and conducted. The development and testing of prototypes of the NMT’s various components to date have not been guided by a formalised testing strategy. Instead, prototypes of components were developed and tested by the teams working on these components. In the case of the front end, a prototype was developed by one team and then tested by another ( Hennigs et al., 2019). It could therefore be argued that the prototype tests to date could have been conducted more effectively had they been planned in a more coordinated manner. Similarly, the communication within and between the various teams working on the NMT could benefit from a more consolidated terminology and shared understanding of the development process and the associated testing activities. A visualised testing strategy could thus facilitate and improve the planning and communication of testing activities in the future.

Testing of prototypes

Boës et al. (2017) define testing in the context of PD as “exposing a physical system to a condition or situation in order to observe the system’s response.” They then clarify the physical system as a representation of the product or one of its components, the condition or situation as a “use case as a whole or its effect on a subsystem”, and the system’s response as “the performance of a desired function [or] an undesired failure mode.” Using this definition, they propose four categories of testing activities according to the type of knowledge that is generated. First, trial and error tests can be used to gain a basic understanding of the development project and to explore the design space. Secondly, experiment tests resemble experimental work in fundamental scientific research in their structured approach in order to identify influencing factors and develop “necessary system knowledge”. Thirdly, verification tests are usually pass/fail tests to determine if the system- or component prototype fulfils the requirements set at the beginning of the PD process. Lastly, validation tests determine whether the product addresses the underlying user needs, rather than the requirements set by the product developer. They are commonly conducted with a fully functional prototype.

This implies that there are different types of tests being conducted throughout the PD process that differ in their level of formality, in their approach, and in the knowledge they are designed to produce. A similar observation can be made about the prototyping tests for the NMT. Just for one generation of a front-end prototype, Hennigs et al. (2019) conducted user surveys and interviews (which would fall into the category of validation tests), photography and image analysis (experiment tests), and field tests on the material choice of a rubber swipe (trial and error tests).

As the product maturity increases, the types of tests conducted on its prototypes will change according to the knowledge that is sought. The testing of physical prototypes throughout the PD process can therefore also be modelled along technology readiness levels (TRL). These are based on a scale to measure a technology’s maturity, developed and first externally published by NASA as a seven-point scale ( Sadin et al., 1989), and still used in current NASA (2016) documents ( Table 1). The TRL-scale has found general acceptance in PD efforts ( Olechowski et al., 2015).

Phases of the product development process

In the case of User Testing, Rubin & Chisnell (2008) distinguish between exploratory/formative tests, assessment/summative tests, and validation/verification tests along the PD process as the vague initial design develops towards the final product. Exploratory tests are conducted in the early stages of PD, to test its basic design, i.e. whether users find it intuitively appealing. Assessment tests, conducted about halfway through the development process, expand the knowledge on the product’s usability, i.e. whether users can perform the intended tasks on the product. The validation/verification tests at the end of the cycle tend not to inform further iteration, but rather confirm that all previously identified problems have been resolved, and that the entire product can be used as intended. In these phases, the basic design, early to well-developed prototypes and the final product are tested on potential users to identify their likes and problems. Similarly, such phases can be imagined for all types of tests as the product’s TRL increases. The exploration phase would encompass TRL’s one and two, the assessment phase TRL’s three through seven, and the validation/verification phase the remaining two phases, eight and nine.

Four approaches to testing of physical prototypes

While the route to technological maturity as exemplified by the TRL’s may seem straight-forward, each step can involve extensive preparations and cooperation among multiple teams. In the example of the NMT, prototype integration (TRL 6) not only requires a sufficient level of maturity of all components, but also operational process control to adjust the components’ outputs to their connected components’ input requirements. As the input of a subsystem affects its output, which, in turn, can be another subsystem’s input, the process of adjusting all parameters is highly complex and requires extensive knowledge of all subsystems’ operational conditions. This knowledge may be acquired in tests that Boës et al. (2017) would classify as experiment tests, using statistical DOE ( Ilzarbe et al., 2008).

Reliability estimation methods are needed to ensure the system’s reliability throughout its lifecycle ( Bhamare et al., 2007), and often national or international standards exist to ensure the technology is safe to use ( Feo-Arenis et al., 2016). Additionally, as mentioned in the introduction, prototype and system tests need to be centred on the target users of the technology. If they do not want to use a novel toilet, it will fail to have a positive impact on the sanitation crisis. Methods of UCD can be used to avoid such failures ( Unger Unruh & Canciglieri Junior, 2018). Therefore, analogous to the taxonomy of Boës et al. (2017), it appears sensible to consider the testing approaches DOE, reliability testing, testing for standard compliance, and testing for UCD in the PD process for the NMT. In this section, the principles of these four approaches to testing a new technology, or prototypes thereof, are presented.

DOE

Laboratory-based experiments commonly involve the observation of a (sub-) system’s condition and/or outputs in relation to its inputs. As mentioned above, a comprehensive understanding of the systems’ outputs respective to their inputs and process variables is required. Often, there are several inputs and/or outputs for one component, and inputs can interact with each other to create second- or higher-order effects on the outputs ( Montgomery, 2009). For example, potential factors that can affect the processes in a combustion chamber are the amount of fuel, its flux, its moisture content and calorific value, the process temperature as well as the flux, pressure, temperature, humidity, and oxygen content of the inflowing air ( Jurado et al., 2018).

To test every effect of each input, and each interaction of inputs, across every input’s potential range, is either very difficult or impossible. It would take hundreds of tests to assess every factor’s influence on the combustion process. Some factors cannot be controlled; some cannot be changed without affecting another.

Based on the work of statistician R.A. Fisher ( Fisher Box, 1980; Yates, 1964), the DOE uses statistical approaches to address such problems, to minimise the time and effort required for a set of experiments while maximising the validity, reliability, and replicability of information gathered from them. The basic principles of DOE, initially developed for agricultural research, are ( Cortes et al., 2018; Fisher, 1935):

  • -

    Factorisation: the variation of several experimental factors at once in order to reduce the number of experiments to run.

  • -

    Replication: the repetition of an experiment with the same settings for experimental factors (treatments) in order to estimate the experimental error.

  • -

    Randomisation: the random application of treatments and order in which experiments are run, to validate the assumption that the observations and errors are independently distributed variables.

  • -

    Local control of error, or blocking: the subdivision of experimental runs into homogenous blocks in the attempt to lessen the impact of errors introduced by controllable nuisance factors, e.g. male and female patients in medical drug trials.

It may occur that these principles have to be compromised to some extent for practical reasons, or that complex processes are to be investigated. Within the DOE-toolbox are methods such as split-plot design ( Kulahci & Tyssedal, 2017; Lee Ho et al., 2016), fractional factorial design, response surface methodology, and random effects models ( Montgomery, 2009) for such cases. It is thusly possible to achieve a high level of understanding from comparably few experimental runs. For example, Ilzarbe et al. (2008) found in their bibliographical review of 77 DOE applications in the field of engineering, that with an average of 5.06 factors to be investigated, 77% of the studies achieved this goal with 30 or fewer experiments, and 50% with 20 or fewer.

DOE finds application in PD efforts of various kinds: Pineau et al. (2019) used a fractional factorial design to assess which design factors of coffee vending machines impacted the sensory experience of the product the most. Gumma & Durgam (2019) improved the structural performance of a car’s body using a multi-model DOE sensitivity study, including simulations and experimental model testing. Sano et al. (2019) studied Bayesian optimisation techniques to reduce the number of experiments necessary to obtain the information with which they could improve production parameters for orally disintegrating tablets.

Thus, DOE encompasses a wide range of statistical tools for planning how to conduct tests, and how to analyse the results later on, to maximise the statistical validity of the lessons learnt. It does, however, not give any advice on what to test, or why. Other problems with DOE can be that statistical models developed through its use do not accurately reflect the observed processes ( Deaconu & Coleman, 2002), or that it gives false credibility to results that stem from badly conducted experiments or the incorrect application of DOE principles. For example, modern technical processes and systems can and must be tested differently to fields of crops ( Collins et al., 2011).

Reliability testing

Reliability estimation, a part of reliability engineering, comprises reliability tests and the analysis of the data gathered in those tests. Kapur & Pecht (2014) define reliability as “the ability of a product to function properly within specified performance limits for a specified period of time, under the life-cycle application conditions”. This means that the tests are carried out to assess the likelihood of the product—or its components—failing over time. They can be conducted on prototypes, on randomly selected products fresh off the assembly line, or even products that have been in use for a certain time. Similar to DOE, statistical approaches are used to calculate a level of confidence with which a failure will occur in a given time ( Kapur & Pecht, 2014).

Challenges lie in accelerating the product’s lifetime: It is not feasible to test a statistically significant number of product units over a number of years in order to assess their reliability for this timespan. Therefore, a reliability engineer attempts the realistic emulation of real use scenarios and environmental conditions in a shortened period of time by applying potential stresses, like shock, vibration, or climatic conditions in rapid succession, periodically, or simultaneously ( Cheon et al., 2015; Donovan & Murphy, 2005; Zanoff & Ekwaro-Osire, 2010). For this aim, accelerated life testing (ALT) is used to determine a product’s time until failure by compressing its lifetime in a short period, usually weeks or months. Highly Accelerated Life Testing (HALT), in contrast, is a technique to determine the most likely failure points of a product but compressing its lifetime into a very short period, usually hours or days ( Silverman, 2006).

Reliability testing is conducted with a broad spectrum of technical products, ranging from computer keyboards ( Duan et al., 2017) over household appliances ( Borgia et al., 2013) to heat exchangers ( Pulido, 2017).

Difficulties with these approaches lie in the complexity of combined stresses and failure modes, particularly on complex physical products. It is difficult or impossible to “model multiple (or competing) failure mechanism[s] to support reliability testing methods” ( Bhamare et al., 2007). Furthermore, reliability engineering does not consider the user’s experience, but rather focuses solely on the product’s reliable functionality. Thus, reliability tests may miss important inputs, as (mis-)use is an important factor in the lifetime of a product, and important outputs, as the user experience may be a more important factor in design changes than increased reliability. For example, a sturdier handheld device may be more reliable, but too heavy or impractical to use.

Testing for technical standard compliance

International “technical standards are established norms or requirements applied to technical systems. They are a crucial aspect of almost all industries […]” ( Shin et al., 2015). They play an important role in technology development ( Østebø et al., 2018), by providing “a benchmark for quality and acceptability in the market place” and guidance on the “safety, reliability, efficiency and interchangeability” of products ( Tyas, 2009). The testing procedures and performance requirements outlined in technology standards form the basis for the process of ensuring a product is compliant with the standard before being released to market. This does, however, not mean that the first time the standard should be consulted is at the end of the PD process. Instead, the performance, safety and other requirements provide the benchmark to which even early prototypes can be compared, and the testing procedures and-protocols can be adapted or used directly to test prototypes of sufficient technological maturity.

Examples of standards being used as benchmarks during product testing are for a wireless fire alarm ( Feo-Arenis et al., 2016), packaging of products ( Nolan, 2004), or sensor interface circuits for the automotive industry ( Ohletz & Schulze, 2009). Another example is the ‘syngina test’, the standardised test for tampon absorbency. The standard was developed by the American Society for Testing and Materials, when a link between tampon size and toxic shock syndrome was discovered, but customers could not reliably buy tampons of similar absorbency from different brands ( Vostral, 2017).

While international standards provide this much-needed guidance, it is important to remember that they are not infallible and may overlook important aspects especially of innovative technologies. For example, Mjör (2002) noted that, for dentistry equipment, “parameters measured in the standards are often not predictors of clinical performance”, and often lacked clinical backing. For the case of the ‘syngina test’, Vostral (2017) discusses the issue that the test is merely a very coarse approximation of a menstruating human body. Narayanan & Chen (2012) discuss the fact that in the early stages of competing, similar technologies, the setting of a standard can result in a “winner-take-all outcome”, as seen in the competition between Betamax and VHS video systems. Moreover, Hu (2010) lists potential threats that international standards could pose to innovation, such as exclusion of innovative start-ups from the market and lack of incentive for leading companies to innovate beyond a minimum-standard level of quality, but also mentions that the benefits of standards toward innovation outweigh the limitations.

The ISO 30500 Standard

The attempt to assist innovation through standards can be applied to the development of sanitation technologies as well: the ‘International Organization for Standardization’ (ISO) recently published the standard ISO 30500:2018 Non-sewered sanitation systems. It “specifies general safety and performance requirements for design and testing as well as sustainability considerations for non-sewered sanitation systems”, and thus aims “to support the development of stand-alone sanitation systems […] and promote economic, social, and environmental sustainability […] ” ( ISO, 2018). In the document, requirements for performance, materials, safety, maintenance, and sustainability are listed and testing procedures are described in great detail. The ‘Annex A – Test methods and additional testing requirements’ comprises 33 pages, and the main document 34. The range of tests covers a comprehensive list of aspects concerning the safety, quality, and usability of non-sewered sanitation systems, but does not necessarily account for the statistical variation in measurements, as would be considered in DOE. For example, only one unit of a new sanitation system is to be tested for the ISO 30500 standard. Similarly, the standard does not fully support a UCD approach. While the ease and safety of use are described as requirements, and consideration is given for variations in cultural requirements like the distinction between users preferring the squatting or seating positions, the standard cannot account for the broad variety of user preferences according to their physical, cultural, and social needs. Such considerations are given in UCD.

Testing for UCD

The term ‘User Centred Design’ (UCD), first coined and publicised by Norman & Draper (1986) in the context of software design, encompasses a collection of processes and methodologies that follow the basic principles of a human-centred approach, which are now described in the international standard ISO 9241-210:2010 ( ISO, 2010):

  • -

    The design is based upon an explicit understanding of users, tasks and environments.

    • Identify all relevant stakeholders, their needs, and the context of use, i.e. the characteristics of users, tasks, and environment.

  • -

    Users are involved throughout design and development.

    • Users are an important source of information about context of use. The participants should reflect the target users’ (range of) characteristics. The type and magnitude of participation will likely change throughout the development process.

  • -

    The design is driven and refined by user-centred evaluation.

    • Gather user feedback on designs, e.g. prototypes, to detect unknown challenges or requirements. The final product can similarly be tested to ensure the UCD was a success. Long-term issues can be uncovered through user feedback after market-release.

  • -

    The process is iterative.

    • As described above, repeating certain steps of the design process while building on the learnings of the previous repetition is widely accepted as a successful method of progressively improving the design ( Wynn & Eckert, 2017).

  • -

    The design addresses the whole user experience.

    • The user experience is influenced by the technology’s functionality, performance, and user interface, as well as the user’s individual characteristics, skills, and previous knowledge. To improve it, all these factors need to be considered, and the user-technology interaction should be adjusted accordingly.

  • -

    The design team includes multidisciplinary skills and perspectives.

    • While the interdisciplinary, and often international, nature of teams collaborating on PD projects can be the cause of conflict initially ( Yim et al., 2014), it is widely accepted that the combined knowledge and skillset of multidisciplinary teams are beneficial to their success ( Edmondson & Nembhard, 2009).

Usability evaluation is only one, albeit essential, part of the entire UCD process ( Bastien, 2010), and comprises in itself a range of possible tests: from complex experimental designs as produced with DOE methods and involving large numbers of participants to rather informal tests with a single potential user as participant. Considering the aim of such testing is often to obtain qualitative information for the design process, rather than obtaining statistically relevant design parameter values, less formalised, qualitative methods are the focus of Rubin & Chisnell’s (2008) ‘Handbook of Usability Testing’. While there are cases of user tests designed using DOE principles (e.g. Jensen et al., 2018), these remain the exception, as the more common approach for user tests seems to be a qualitative one ( Bastien, 2010).

UCD approaches appear to be particularly important for products that have a high degree of complexity but are used by a broad spectrum of users, with varying degrees of expertise, for example a tubeless insulin pump ( Pillalamarri et al., 2018). Another application would be for products specialised for a certain user group, like a motorcycle tool for one-handed users ( Sudin, 2013). However, a large portion of usability tests is still conducted in software development, for example for a drill rig control system ( Koli et al., 2014).

Summary

Table 2 summarises the basic aspects of the four presented approaches. A comprehensive testing strategy for the development of a novel sanitation system should comprise elements of all approaches to combine their strengths and offset their shortcomings. We believe that a combination of established approaches – not only in testing – is a common occurrence in PD. An example is Lean Six Sigma, a now established concept itself, which combines the two management methodologies ‘Lean’ – a methodology to “remove non-value activities from the [PD] process” and ‘Six Sigma’ – a methodology to reduce variability and thus defects and errors in the process of concern ( Alexander et al., 2019). Furthermore, since the dawn of computer-assisted engineering, a combination of virtual and physical testing has been ( Van Der Auweraer & Leuridan, 2005) and continues to be promoted by experts ( Tahera et al., 2014). Likewise, the testing practice in private enterprises is likely to be more experience-based and will often combine various approaches to varying degrees. However, a visualised combination of different approaches appears to be a novel conclusion.

To incorporate all four approaches, testing of prototypes in PD should thus:

  • -

    Follow UCD-principles

  • -

    Use standard compliance tests and standard requirements as benchmark for performance and safety

  • -

    Use ALT and HALT methodology to identify weak points and estimate the product’s reliability

  • -

    Use DOE-principles where possible to ensure statistical validity and efficient use of time and resources

Distinction between front end and back end – lessons from software development

For the case of the NMT, a distinction between the toilet seat, bowl, and flush, i.e. the “user interface” or front end, and the treatment system, or back end, can be made. This is analogous to software products like web sites ( Chen & Iyengar, 2003). The front end and back end of a system require different testing in the PD process. ( Bertolino, 2007; Sánchez Guinea et al., 2016; Sneed, 2004) For example, while the front end is the part of the product with which the users will interact, the back end is usually only of indirect concern for them, as long as everything operates as expected. Hence, the front end should undergo user testing early on ( Chuang et al., 2011), while the back end might only require limited user testing at later stages, to ensure maintainability by trained personnel. On the other hand, the back end of the NMT will likely require more extensive laboratory testing than the front end, as the treatment processes are more complex than the user interface.

It might therefore be sensible to consider testing for the front end and back end independently, and in a separate step actualise integration testing of the individual components.

Iteration

Iteration occurs throughout the PD process and can have different causes and outcomes ( Wynn, 2007). With its earliest forms dating back to the 1930s ( Larman & Basili, 2003), the cyclical repetition of testing and (re-)designing can be welcomed as a driver of positive design change, or as a wasteful, costly delay in a PD project ( Ballard, 2000; Le et al., 2010; Wynn & Eckert, 2017), but it is undeniable that iteration occurs in nearly every PD process, particularly for complex products ( Wynn & Eckert, 2017).

It is common to develop software user interfaces iteratively ( Nielsen, 1993). For complex physical products, however, every iteration-step of building and testing a prototype can be associated with high costs ( Tahera et al., 2019). It is therefore important to consider when and how many iteration-steps should be undertaken. There is a multitude of publications discussing iteration in PD, and ( Wynn & Eckert, 2017) offer a comprehensive overview and unified terminology of this field of research.

For the development of an NMT testing strategy it is mainly important to know that iterative loops can occur within a stage of the PD process as well as between stages ( Wynn & Eckert, 2017), and to consider which test results should trigger or prevent an iterative loop. With the main goal of the PD process being a marketable product, any proof that a prototype does not represent such a marketable product should be a trigger of iteration. Failed tests, like the shortfall against benchmark values, can be seen as such a proof. International or internal standards can provide such benchmark values.

Visualisations of PD processes

As mentioned in the introduction, visualisations can be beneficial for product developers to plan and communicate their work ( Keller et al., 2006). Wynn & Clarkson (2018) give a very comprehensive overview of a large body of work on process models in PD, including visualisations thereof. They categorise models focusing “on the large-scale organisation and management of design and development” as macro-level models. Examples of these are well-known models such as the Stage-Gate model ( Cooper, 1990), the V-model ( Forsberg et al., 2005), the Waterfall model ( Royce, 1970), and the Spiral model ( Boehm, 1988). While all these models differ in their philosophy, reflected in the shape of their visualisations, they have some common characteristics: They all describe a continuously progressing process towards the final product, and while they all mention testing at some point in this process, they do not consider testing throughout its entirety. Generally, testing does not play a significant role in the various models reviewed by Wynn & Clarkson (2018). This further emphasizes the importance of developing a visualisation of testing activities in PD, not just for the NMT.

As the NMT project does not follow a specific PD process model, a visual description of the testing activities could conceivably be shaped in a number of ways. However, for the sake of simplicity, it seems sensible to base it on the progression of the project to date. Recently, two teams worked on designing and testing the NMT’s front end, and two teams were allocated to researching, developing, and testing the back end membrane and combustion processes respectively. As described in the previous section, a separation into parallel testing activities for front end and back end seems sensible. Furthermore, the entire process has progressed steadily, and even though iteration occurred, a linear model describes the overall development most aptly.

The end point of many models is the launch, or deployment, of the product, although some consider also the operation and maintenance of the product ( Wynn & Clarkson, 2018). For the case of the NMT, the envisioned final test of a prototype, one which is practically identical to the final product, is envisioned to be the testing for compliance with the ISO 30500 standard, conducted by a licensed laboratory. Therefore, this test would signify the endpoint of a visualisation of the NMT testing strategy.

Visual synthesis of testing approaches

Derived from the considerations described above, a unified testing strategy for the NMT could look as shown in Figure 3. The flowchart incorporates the four presented testing approaches and its result is a product that can be tested to achieve standard compliance.

Figure 3. Unified testing strategy flow chart.

Figure 3.

Starting from the problem description, and potentially using input from already existing international standards, a design brief is the first step of the PD process. This will prompt first concept ideas, thus beginning the Exploration Phase. Designers will then develop potential solutions to the problem, which will be realised in the first prototypes, both for the front end and back end. The front-end prototypes will often have low functionality and are mainly used to communicate the designers’ vision. They can then be tested with potential users, to assess whether the designers are ‘on the right track’, and their proposed solutions could be accepted by users. The back-end prototypes will likely be first ‘breadboard’ prototypes of single components, to prove the viability of the concept ideas. Several competing designs might be tested simultaneously, and iteratively, to refine the initial designs.

In the following Assessment Phase, further developed prototypes can be constructed. These might be prototypes of components or the whole system, and they are likely to already have a certain degree of functionality. It is on these prototypes, and increasingly developed iterations thereof, that a variety of tests will be conducted to learn about the technical, functional, and aesthetic aspects of the NMT. Using DOE and UCD methods, and tests from international standards as benchmarks, components and (sub)systems are tested in laboratories and field tests towards functionality and usability. HALT methods can be used to identify and mitigate likely failure points. While first tests will still be conducted on separate prototypes for the front and back end, user tests and functionality tests can be conducted simultaneously at later stages of (sub-) system maturity, when an integrated prototype is constructed. Several iterations are likely until satisfactory component and system maturity is reached, and competing designs can be developed and tested simultaneously. It can be a difficult decision to define a cut-off point for further iterations. The developer has to have confidence that the entire system will safely function as intended. The minimum performance values of an international standard can provide helpful guidance to ensure this confidence.

In the final phase of validation and verification, a finalised design, maybe already produced on the product’s assembly line, is tested for reliability using ALT methods. DOE methods can be applied to improve statistical validity of tests. Final user tests ensure all user-related problems have been mitigated. If no serious problems arise, the product can be sent to be tested towards compliance with an international standard.

There is always a possibility that tests reveal problems which necessitate a return to much earlier stages of the PD process. However, this should be avoided by completing an appropriate number of test iterations during the assessment phase.

Discussion

The testing strategy flow chart presented in Figure 3 gives an overview of the testing efforts and approaches that can be employed during the development process of the NMT. It combines the more creative tests involved in UCD processes as well as rigorous reliability tests and DOE-based statistically relevant test designs and uses international standards as benchmarks. At the same time, the combination of approaches compensates for their individual weaknesses: The lack of statistical validity of UCD approaches and some standard-based tests is counteracted by using DOE methods, while the focus on the user allows for important additional input to reliability tests. The lack of information on what tests should be conducted and which values should be tested, a deficiency common in DOE approaches, is filled by using international standards as benchmark.

Tahera et al., 2015, stress the importance of testing in the PD process, and there is abundant research on the ideal number and timing of tests within PD (for example Al Kindi & Abbas, 2010; Thomke & Bell, 2001). Therefore, factors such as cost and timing are not considered in the presented strategy. However, there is a lack of publications focusing on how to approach and plan testing throughout the PD process, which is attempted here.

The strategy aims to combine several testing approaches that, in their own field, are well-developed concepts with numerous publications and ongoing research on refining and advancing methods. It would be far beyond the scope of this paper to attempt to outline detailed methods from all approaches, and we therefore refer to the referenced literature for such information.

The testing strategy flow chart can be applied to visualise and plan testing efforts for the NMT components and the overall system. It can also be used to communicate these testing efforts among and between teams and people new to the project. Combining approaches to develop tests may result in more statistically valid or more useful data. Also, using the flow chart to visually communicate the various testing efforts amongst teams could aid in coordinating testing to further enhance the value of obtained results.

At this stage, the proposed strategy flow chart has not been applied to plan or communicate testing efforts. Future work will aim to test its application in the development of the NMT, which will serve as case study for advancing the strategy. Additionally, the generalisation of the flow chart into a framework, to be used in a number of PD projects, could be attempted. Much like testing prototypes of physical products, the strategy flow chart itself will likely undergo several iterations of various types of tests to further improve its utility.

Conclusion

In this paper, the sanitation crisis was described as the need for developing new non-sewered sanitation technologies, which led to the Reinvent The Toilet Challenge, and in turn to the development of the NMT and other technologies of this type. Through a review of various aspects of prototype testing in general and four testing approaches in particular, a visualised prototype testing strategy for the development of the NMT is presented and proposed to be used for future development efforts in the project. Prospective work towards generalisation could result in a more widely applicable tool.

Data availability

All data underlying the results are available as part of the article and no additional source data are required.

Funding Statement

This publication is based on research funded by the Bill & Melinda Gates Foundation (grant number OPP1149204). The findings and conclusions contained within are those of the authors and do not necessarily reflect positions or policies of the Bill & Melinda Gates Foundation.

The funders had no role in study design, data collection and analysis, decision to publish, or preparation of the manuscript.

[version 1; peer review: 3 approved with reservations]

References

  1. Alexander P, Antony J, Rodgers B: Lean Six Sigma for small- and medium-sized manufacturing enterprises: a systematic review. Int J Qual Reliab Manag. 2019;36(3):378–397. 10.1108/IJQRM-03-2018-0074 [DOI] [Google Scholar]
  2. Al Kindi M, Abbas A: Sequential testing decisions in product development. 2010 IEEE International Systems Conference2010;490–494. 10.1109/SYSTEMS.2010.5482486 [DOI] [Google Scholar]
  3. Austin-Breneman J, Yang M: Design for Micro-Enterprise: a Field Study of User Preference Behavior. In Proceedings of the International Conference on Engineering Design, ICED2017;219–228. Reference Source [Google Scholar]
  4. Ballard G: Positive vs Negative Iteration in Design, Proceedings Eighth Annual Conference of the International Group for Lean Construction. In Proceedings Eighth Annual Conference of the International Group for Lean Construction2000. Reference Source [Google Scholar]
  5. Bastien JM: Usability testing: a review of some methodological and technical aspects of the method. Int J Med Inform.Elsevier Ireland Ltd,2010;79(4):e18–e23. 10.1016/j.ijmedinf.2008.12.004 [DOI] [PubMed] [Google Scholar]
  6. Batliner M, Boës S, Heinis T, et al. : Testing methodology for engineering design education. In Proceedings of the 20th International Conference on Engineering and Product Design Education, E and PDE 20182018. Reference Source [Google Scholar]
  7. Bertolino A: Software testing research: Achievements, challenges, dreams. In FoSE 2007: Future of Software Engineering2007;85–103. 10.1109/FOSE.2007.25 [DOI] [Google Scholar]
  8. Bhamare SS, Yadav OP, Rathore A: Evolution of reliability engineering discipline over the last six decades: a comprehensive review. Int J Reliability and Safety. 2007;1(4):377–410. 10.1504/ijrs.2007.016256 [DOI] [Google Scholar]
  9. Bill & Melinda Gates Foundation: Fact Sheet - Water, Sanitation & Hygiene: Reinvent the Toilet Challenge. Bill & Melinda Gates Foundation2013;1–2. Reference Source [Google Scholar]
  10. Bill & Melinda Gates Foundation: Bill and Melinda Gates Foundation - Fact Sheet.2018; (Accessed: 4 October 2018). Reference Source [Google Scholar]
  11. Boehm BW: Spiral Model of Software Development. In Thayer RH, Dorfman M, (eds) Tutorial Software Project Management IEEE Press.1988. [Google Scholar]
  12. Boës S, Batliner M, Stücheli M, et al. : A Taxonomy of Testing Activities in Product Development. ETHZ Research Collection. 2017. 10.3929/ethz-b-000214845 [DOI] [Google Scholar]
  13. Borgia O, De Carlo F, Fanciullacci N, et al. : Accelerated life tests for new product qualification: A case study in the household appliance. IFAC Proceedings Volumes. 2013;46(7):269–274. 10.3182/20130522-3-BR-4036.00080 [DOI] [Google Scholar]
  14. Budge S, Parker AH, Hutchings PT, et al. : Environmental enteric dysfunction and child stunting. Nutr Rev. 2019;77(4):240–253. 10.1093/nutrit/nuy068 [DOI] [PMC free article] [PubMed] [Google Scholar]
  15. Camburn B, Dunlap B, Gurjar T, et al. : A Systematic Method for Design Prototyping. J Mech Des. 2015;137(8): 081102. 10.1115/1.4030331 [DOI] [Google Scholar]
  16. Chen H, Iyengar A: A tiered system for serving differentiated content. World Wide Web. 2003;6(4):331–352. 10.1023/A:1025609904398 [DOI] [Google Scholar]
  17. Cheon S, Jeong H, Hwang SY, et al. : Accelerated Life Testing to Predict Service Life and Reliability for an Appliance Door Hinge. In 43rd Proceedings of the North American Manufacturing Research Institution of SME Elsevier B.V.,2015;1:169–180. 10.1016/j.promfg.2015.09.082 [DOI] [Google Scholar]
  18. Chuang KC, Shih CS, Hung SH: User Behavior Augmented Software Testing for User-Centered GUI. In Proceedings of the 2011 ACM Research in Applied Computation Symposium, RACS 20112011;200–208. 10.1145/2103380.2103421 [DOI] [Google Scholar]
  19. Cobbinah PB, Poku-Boansi M: Towards resilient cities in Ghana: Insights and strategies. Futures.Elsevier Ltd,2018;101:55–66. 10.1016/j.futures.2018.06.005 [DOI] [Google Scholar]
  20. Collins B, Hurst T, Ard J: Designed Simulation Experiments, Part 1: Roots, Myths, and Limitations of Conventional DOE. In AIAA Modeling and Simulation Technologies Conference Portland, OR United States,2011;972–978. 10.2514/6.2011-6624 [DOI] [Google Scholar]
  21. Cooper RG: Stage-gate systems: A new tool for managing new products. Bus Horiz. 1990;33(3):44–54. 10.1016/0007-6813(90)90040-I [DOI] [Google Scholar]
  22. Cortes LA, Simpson JR, Parker PA: Response surface split-plot designs: A literature review. Qual Reliab Eng Int. 2018;34(7):1374–1389. 10.1002/qre.2350 [DOI] [Google Scholar]
  23. Deaconu S, Coleman HW: Limitations of Statistical Design of Experiments Approaches in Engineering Testing. J Fluids Eng. 2002;122(2):254–259. 10.1115/1.483252 [DOI] [Google Scholar]
  24. Dekker D, Buzink SN, Molenbroek JFM: User preferences regarding body support and personal hygiene in the toilet environment. Assist technol Res Ser. 2011;27:194–206. 10.3233/978-1-60750-752-9-194 [DOI] [Google Scholar]
  25. Donovan J, Murphy E: Total system reliability: Integrated model for growth and test termination. Qual Reliab Eng Int. 2005;21(4):329–344. 10.1002/qre.646 [DOI] [Google Scholar]
  26. Duan H, Chen Z, Li S, et al. : A highly accelerated life test method for computer keyboards. In Proceedings of 2016 11th International Conference on Reliability, Maintainability and Safety: Integrating Big Data, Improving Reliability and Serving Personalization, ICRMS 20162017; Article Number 8050112. IEEE 10.1109/ICRMS.2016.8050112 [DOI] [Google Scholar]
  27. Edmondson AC, Nembhard IM: Product development and learning in project teams: The challenges are the benefits. J Prod Innov Manage. 2009;26(2):123–138. 10.1111/j.1540-5885.2009.00341.x [DOI] [Google Scholar]
  28. Fejerskov AM: The New Technopolitics of Development and the Global South as a Laboratory of Technological Experimentation. Science Technology and Human Values. 2017;42(5):947–968. 10.1177/0162243917709934 [DOI] [Google Scholar]
  29. Feo-Arenis S, Westphal B, Dietsch D, et al. : Ready for testing: ensuring conformance to industrial standards through formal verification. Form Asp Comput. 2016;28(3):499–527. 10.1007/s00165-016-0365-3 [DOI] [Google Scholar]
  30. Fidalgo B, Chilmeran M, Somorin T, et al. : Non-isothermal thermogravimetric kinetic analysis of the thermochemical conversion of human faeces. Renew Energy. 2019;132:1177–1184. 10.1016/j.renene.2018.08.090 [DOI] [PMC free article] [PubMed] [Google Scholar]
  31. Fisher Box J: R. A. Fisher and the Design of Experiments, 1922-1926. Am Stat. 1980;34(1):1–7. 10.1080/00031305.1980.10482701 [DOI] [Google Scholar]
  32. Fisher RA: The Design of Experiments. 1st edn. Edinburgh: Oliver and Boyd. 1935. Reference Source [Google Scholar]
  33. Forsberg K, Mooz H, Cotterman H: Visualizing project management: models and frameworks for mastering complex systems. 3rd edn. Hoboken, NJ, USA: Wiley Publishing, Inc.2005. Reference Source [Google Scholar]
  34. Gumma M, Durgam P: Optimization Driven Methodology to Improve the Body-in-White Structural Performance. SAE Technical Paper Series. 2019;1:1–7. 10.4271/2019-26-0205 [DOI] [Google Scholar]
  35. Hanak DP, Kolios AJ, Onabanjo T, et al. : Conceptual energy and water recovery system for self-sustained nano membrane toilet. Energy Convers Manag.The Authors,2016;126:352–361. 10.1016/j.enconman.2016.07.083 [DOI] [PMC free article] [PubMed] [Google Scholar]
  36. Hennigs J, Ravndal KT, Blose T, et al. : Field testing of a prototype mechanical dry toilet flush. Sci Total Environ.The Authors,2019;668:419–431. 10.1016/j.scitotenv.2019.02.220 [DOI] [PMC free article] [PubMed] [Google Scholar]
  37. Hu C: A selective review of the impact of standard on technology innovation. In ICIME 2010 - 2010 2nd IEEE International Conference on Information Management and Engineering IEEE,2010;201–203. 10.1109/ICIME.2010.5477471 [DOI] [Google Scholar]
  38. Ilzarbe L, Alvarez MJ, Viles E, et al. : Practical applications of design of experiments in the field of engineering: a bibliographical review. Quality and Reliability Engineering International. 2008;24(4):417–428. 10.1002/qre.909 [DOI] [Google Scholar]
  39. International Organization for Standardization (ISO): BS EN ISO 9241-210: 2010 Ergonomics of human-system interaction Part 210: Human-centred design for interactive systems. BSI Standards Publication.British Standards Institution (BSI).2010. Reference Source [Google Scholar]
  40. International Organization for Standardization (ISO): ISO 30500:2018. International Organization for Standardization.2018. Reference Source [Google Scholar]
  41. Jadhav A, Weitzman A, Smith-Greenaway E: Household sanitation facilities and women’s risk of non-partner sexual violence in India. BMC Public Health. 2016;16(1):1139. 10.1186/s12889-016-3797-z [DOI] [PMC free article] [PubMed] [Google Scholar]
  42. Jahan S: Human Development Report 2016. New York City.2016. Reference Source [Google Scholar]
  43. Jensen LS, Vorting D, Villadsen A, et al. : Prototyping for desirability by design of experiments: A case study of a hardware startup. In Proceedings of the ASME Design Engineering Technical Conference. 2018. 10.1115/DETC2018-86293 [DOI] [Google Scholar]
  44. Jurado N, Somorin T, Kolios AJ, et al. : Design and commissioning of a multi-mode prototype for thermochemical conversion of human faeces. Energy Convers Manag.Elsevier,2018;163:507–524. 10.1016/j.enconman.2018.02.065 [DOI] [PMC free article] [PubMed] [Google Scholar]
  45. Kamranvand F, Davey CJ, Sakar H, et al. : Impact of fouling, cleaning and faecal contamination on the separation of water from urine using thermally driven membrane separation. Separation Science and Technology (Philadelphia).Taylor & Francis,2018;53(9):1372–1382. 10.1080/01496395.2018.1433688 [DOI] [PMC free article] [PubMed] [Google Scholar]
  46. Kapur KC, Pecht M: Reliability Engineering. Hoboken, NJ, USA: John Wiley & Sons, Inc.2014. Reference Source [Google Scholar]
  47. Keizer JA, Halman JIM: Risks in major innovation projects , a multiple case study within a world ’ s leading company in the fast moving consumer goods. Int J Technol Manage. 2009;48(4):499–517. 10.1504/IJTM.2009.026691 [DOI] [Google Scholar]
  48. Keller R, Flanagan TL, Eckert CM, et al. : Two sides of the story: Visualising products and processes in engineering design. In Proceedings of the International Conference on Information Visualisation2006;362–367. 10.1109/IV.2006.114 [DOI] [Google Scholar]
  49. Koli K, Kärkkäinen T, Lehikoinen J, et al. : User-centered design for more efficient drill rig control system. In Conference on Human Factors in Computing Systems - Proceedings 20142014;873–876. 10.1145/2559206.2559972 [DOI] [Google Scholar]
  50. Kolios A, Jiang Y, Somorin T, et al. : Probabilistic performance assessment of complex energy process systems – The case of a self-sustained sanitation system. Energy Conversion and Management.Elsevier,2018;163:74–85. 10.1016/j.enconman.2018.02.046 [DOI] [PMC free article] [PubMed] [Google Scholar]
  51. Kulahci M, Tyssedal J: Split-plot designs for multistage experimentation. Journal of Applied Statistics. 2017;44(3):493–510. 10.1080/02664763.2016.1177497 [DOI] [Google Scholar]
  52. Larman C, Basili VC: Iterative and Incremental Development – A brief History. IEEE Computer. 2003;36(6):47–56. 10.1109/MC.2003.1204375 [DOI] [Google Scholar]
  53. Larsen TA, Hoffmann S, Lüthi C, et al. : Emerging solutions to the water challenges of an urbanizing world. Science. 2016;352(6288):928–933. 10.1126/science.aad8641 [DOI] [PubMed] [Google Scholar]
  54. Le HN, Wynn DC, Clarkson PJ: Evaluating the Positive and Negative Impact of Iteration in Engineering Processes. In Heisig P, Clarkson PJ and Vajna S. (eds) Modelling and Management of Engineering Processes.London: Springer London.2010. 10.1007/978-1-84996-199-8_8 [DOI] [Google Scholar]
  55. Lee HK: Designing a Waterless Toilet Prototype for Reusable Energy Using a User-Centered Approach and Interviews. Applied Sciences. 2019;9(5):919 10.3390/app9050919 [DOI] [Google Scholar]
  56. Lee Ho L, Vivacqua CA, Santos De Pinho AL: Minimum Setup Minimum Aberration Two-level Split-plot Type Designs for Physical Prototype Testing. Quality and Reliability Engineering International. 2016;32(3):1007–1020. 10.1002/qre.1810 [DOI] [Google Scholar]
  57. Mccurdy M, Connors C, Pyrzak G, et al. : Breaking the Fidelity Barrier: An Examination of our Current Characterization of Prototypes and an Example of a Mixed-Fidelity Success. In roceedings of the SIGCHI Conference on Human Factors in Computing Systems.New York City: ACM,2006;1233–1242. 10.1145/1124772.1124959 [DOI] [Google Scholar]
  58. Menold J, Jablokow K, Simpson T: Prototype for X (PFX): A holistic framework for structuring prototyping methods to support engineering design. Design Studies.Elsevier Ltd,2017;50:70–112. 10.1016/j.destud.2017.03.001 [DOI] [Google Scholar]
  59. Mercer E, Cruddas, P, Williams L, et al. : Selection of screw characteristics and operational boundary conditions to facilitate post-flush urine and faeces separation within single household sanitation systems. Environ Sci Water Res Technol. 2016;2(6):953–964. 10.1039/C6EW00170J [DOI] [Google Scholar]
  60. Miiro G, Rutakumwa R, Nakiyingi-Miiro J, et al. : Menstrual health and school absenteeism among adolescent girls in Uganda (MENISCUS): a feasibility study. BMC Womens Health. 2018;18(1):4. 10.1186/s12905-017-0502-z [DOI] [PMC free article] [PubMed] [Google Scholar]
  61. Mjör IA: Product certification (Letter). J Am Dent Assoc.American Dental Association,2002;133(9):1160–1161. 10.14219/jada.archive.2002.0347 [DOI] [PubMed] [Google Scholar]
  62. Mkhize N, Taylor M, Udert KM, et al. : Urine diversion dry toilets in eThekwini Municipality, South Africa: acceptance, use and maintenance through users’ eyes. Journal of Water Sanitation and Hygiene for Development. 2017;7(1):111–120. 10.2166/washdev.2017.079 [DOI] [PMC free article] [PubMed] [Google Scholar]
  63. Montgomery DC: Design and Analysis of Experiments - International Student Version. 7th edn. John Wiley& Sons (asia) Pte Ltd.2009. [Google Scholar]
  64. Morales E, Pilon MA, Doyle O, et al. : Which grab bar do you prefer in the bathroom? J Enabling Technol. 2017;11(4):123–137. 10.1108/JET-03-2017-0012 [DOI] [Google Scholar]
  65. Narayanan VK, Chen T: Research on technology standards: Accomplishment and challenges. Res Policy.Elsevier BV,2012;41(8):1375–1406. 10.1016/j.respol.2012.02.006 [DOI] [Google Scholar]
  66. NASA: NASA System Engineering Handbook Revision 2. Revision 2. Washington, DC: National Aeronautics and Space Administration.2016. Reference Source [Google Scholar]
  67. Nelson KB, Karver J, Kullman C, et al. : User perceptions of shared sanitation among rural households in Indonesia and Bangladesh. PLoS One. 2014;9(8):e103886. 10.1371/journal.pone.0103886 [DOI] [PMC free article] [PubMed] [Google Scholar]
  68. Nielsen J: Iterative User-Interface Design. Computer. 1993;26(11):32–41. 10.1109/2.241424 [DOI] [Google Scholar]
  69. Niemeier D, Gombachika H, Richards-Kortum R: How to transform the practice of engineering to meet global health needs. Science. 2014;345(6202):1287–1290. 10.1126/science.1257085 [DOI] [PubMed] [Google Scholar]
  70. Nolan PJ: Complying with EU packaging regulations using ASTM international standards. Standardization News. 2004;32(12):32–35. Reference Source [Google Scholar]
  71. Norman DA, Draper SW: User-Centered System Design: New Perspectives on Human-Computer Interaction. Hillsdale, New Jersey: Lawrence Erlbaum Associates.1986. Reference Source [Google Scholar]
  72. Ohletz MJ, Schulze F: Design, qualification and production of integrated sensor interface circuits for high-quality automotive applications. Microelectron J.Elsevier,2009;40(9):1350–1357. 10.1016/j.mejo.2008.08.018 [DOI] [Google Scholar]
  73. Olechowski A, Eppinger SD, Joglekar N: Technology Readiness Levels at 40: a Study of State-of-the-Art Use Challenges, and Opportunities. In Proceedings of Portland International Conference on Management of Engineering and Technology 15. Management of the Technology Age Portland: IEEE,2015;2084–2094. 10.1109/PICMET.2015.7273196 [DOI] [Google Scholar]
  74. Onabanjo T, Kolios AJ, Patchigolla K, et al. : An experimental investigation of the combustion performance of human faeces. Fuel (Lond). The Authors, 2016;184:780–791. 10.1016/j.fuel.2016.07.077 [DOI] [PMC free article] [PubMed] [Google Scholar]
  75. Østebø R, Selvik JT, Naegeli G, et al. : ISO Standards to Enable Reliable, Safe and Cost-Effective Technology Development, Project Execution and Operational Excellence. In Proceedings of the Annual Offshore Technology Conference Houston, United States,2018; 4021–4043. 10.4043/28705-MS [DOI] [Google Scholar]
  76. Parker A: Membrane technology plays key role in waterless hygienic toilet. Membrane Technology.Elsevier Ltd,2014;2014(12):8 10.1016/S0958-2118(14)70255-1 [DOI] [Google Scholar]
  77. Parnell S, Simon D, Vogel C: Global Environmental Change: Conceptualising the Growing Challenge for Cities in Poor Countries. Area. 2007;39(3):357–369. 10.1111/j.1475-4762.2007.00760.x [DOI] [Google Scholar]
  78. Pillalamarri SS, Huyett LM, Abdel-Malek A: Novel Bluetooth-Enabled Tubeless Insulin Pump: A User Experience Design Approach for a Connected Digital Diabetes Management Platform. J Diabetes Sci Technol. 2018;12(6):1132–1142. 10.1177/1932296818804802 [DOI] [PMC free article] [PubMed] [Google Scholar]
  79. Pineau N, Moser M, Rawyler F, et al. : Design of experiment with sensory data: A pragmatic data analysis approach. J Sens Stud. 2019;34(2):e12489 10.1111/joss.12489 [DOI] [Google Scholar]
  80. Pulido J: Reliability test design of a membrane air-water heat exchanger. In Proceedings - Annual Reliability and Maintainability Symposium 29 March 2017, Article number 7889735 IEEE,2017;1–6. 10.1109/RAM.2017.7889735 [DOI] [Google Scholar]
  81. Qian Y, Xie M, Goh TN, et al. : Optimal testing strategies in overlapped design process. Eur J Oper Res.Elsevier B.V.,2010;206(1):131–143. 10.1016/j.ejor.2010.02.010 [DOI] [Google Scholar]
  82. Reza H, Grant ES: A method to test concurrent systems using architectural specification. J Supercomput. 2007;39(3):347–357. 10.1007/s11227-006-0017-0 [DOI] [Google Scholar]
  83. Roma E, Philp K, Buckley C, et al. : User perceptions of urine diversion dehydration toilets: Experiences from a cross-sectional study in eThekwini municipality. Water SA. 2013;39(2):305–311. 10.4314/wsa.v39i2.15 [DOI] [Google Scholar]
  84. Royce WW: Managing the development of large software systems. In Proceedings IEEE WESCON1970;1–9. Reference Source [Google Scholar]
  85. Rubin J, Chisnell D: Handbook of usability testing: how to plan, design, and conduct effective tests. 2nd ed. Indianapolis, IN USA: Wiley Publishing, Inc.2008. Reference Source [Google Scholar]
  86. Sadin SR, Povinelli FP, Rosen R: The NASA Technology Push Towards Future Space Mission Systems. Acta Astronautica. 1989;20(C):73–77. 10.1016/0094-5765(89)90054-4 [DOI] [Google Scholar]
  87. Sánchez Guinea A, Nain G, Le Traon Y: A systematic review on the engineering of software for ubiquitous systems. J Syst Software. 2016;118:251–276. 10.1016/j.jss.2016.05.024 [DOI] [Google Scholar]
  88. Sano S, Kadowaki T, Tsuda K, et al. : Application of Bayesian Optimization for Pharmaceutical Product Development. J Pharm Innov. 2019;1–11. 10.1007/s12247-019-09382-8 30923586 [DOI] [Google Scholar]
  89. Sclar GD, Garn JV, Penakalapati G, et al. : Effects of sanitation on cognitive development and school absence: A systematic review. Int J Hyg Environ Health.Elsevier GmbH.,2017;220(6):917–927. 10.1016/j.ijheh.2017.06.010 [DOI] [PubMed] [Google Scholar]
  90. Sedlak DL: Disruptive Environmental Research. Environ Sci Technol.American Chemical Society,2018;52(15):8059–8060. 10.1021/acs.est.8b03839 [DOI] [PubMed] [Google Scholar]
  91. Semiyaga S, Okure MA, Niwagaba CB, et al. : Decentralized options for faecal sludge management in urban slum areas of Sub-Saharan Africa: A review of technologies, practices and end-uses. Resources, Conservation and Recycling. 2015;104,109–119. 10.1016/j.resconrec.2015.09.001 [DOI] [Google Scholar]
  92. Shin DH, Kim H, Hwang J: Standardization revisited: A critical literature review on standards and innovation. Computer Standards and Interfaces.Elsevier B.V.,2015;38:152–157. 10.1016/j.csi.2014.09.002 [DOI] [Google Scholar]
  93. Silverman M: HALT vs. ALT: When to use which technique?In Proceedings - Annual Reliability and Maintainability Symposium IEEE,2006;310–312. 10.1109/RAMS.2006.1677392 [DOI] [Google Scholar]
  94. Sneed HM: Testing a Web Application. In Proceedings - Sixth IEEE International Workshop on Web Site Evolution, WSE 20042004;3–10. 10.1109/wse.2004.10011 [DOI] [Google Scholar]
  95. Strande L: The Global Situation. In Faecal Sludge Management - Systems Approach for Implementation and Operation2014;1–14. Reference Source [Google Scholar]
  96. Sudin MN: User-centred design approach in designing motorcycle tire dismounting tool for one-handed user. International Journal of Engineering and Technology. 2013;5(4):3588–3595. Reference Source [Google Scholar]
  97. Tahera K, Earl C, Eckert C: Integrating virtual and physical testing to accelerate the engineering product development process. International Journal of Information Technology & Management. 2014;13(2/3):154–175. 10.1504/IJITM.2014.060307 [DOI] [Google Scholar]
  98. Tahera K, Eckert C, Earl C: Highlighting the Importance of Testing in the Product Development Process. In Proceedings of the 20th International Conference on Engineering Design (ICED 15)2015;21–30. Reference Source [Google Scholar]
  99. Tahera K, Wynn DC, Earl C, et al. : Testing in the incremental design and development of complex products. Research in Engineering Design.Springer London,2019;30(2):291–316. 10.1007/s00163-018-0295-6 [DOI] [Google Scholar]
  100. Thomke S, Bell DE: Sequential testing in product development. Management Science. 2001;47(2):308–323. 10.1287/mnsc.47.2.308.9838 [DOI] [Google Scholar]
  101. Tierney R: The Development of the User Interface of an Innovative Sanitation Solution Targeted at Developing Countries. Cranfield University.2014. Reference Source [Google Scholar]
  102. Tierney R: The potential of Reverse Innovation within the Sanitation Sector. Cranfield University.2017. [Google Scholar]
  103. Tronvoll SA, Elverum CW, Welo T: Prototype Experiments: Strategies and Trade-offs. In Procedia CIRP2017;554–559. 10.1016/j.procir.2017.01.049 [DOI] [Google Scholar]
  104. Tyas MJ: International standards: why do we need them? Dental Materials Journal. 2009;28(1):57–61. 10.4012/dmj.28.57 [DOI] [PubMed] [Google Scholar]
  105. Ulrich KT, Eppinger SD: Prototyping. In Product Desing and Development 6th edn. New York City: McGraw-Hill Education,2016;291–312. [Google Scholar]
  106. Unger D, Eppinger S: Improving product development process design: A method for managing information flows, risks, and iterations. Journal of Engineering Design. 2011;22(10):689–699. 10.1080/09544828.2010.524886 [DOI] [Google Scholar]
  107. Unger Unruh G, Canciglieri Junior O: Human and user-centered design product development: A literature review and reflections. Advances in Transdisciplinary Engineering. 2018;7:211–220. 10.3233/978-1-61499-898-3-211 [DOI] [Google Scholar]
  108. UNICEF: The State of the World’s Children 2017 - Children in a Digital World. Unicef. New York City.2017; Reference Source [Google Scholar]
  109. Van Der Auweraer H, Leuridan J: A new testing paradigm for today’s product development process - Part 1.2005;39(9):14–18. Reference Source [Google Scholar]
  110. Vostral SL: Toxic Shock Syndrome, Tampon Absorbency, and Feminist Science. Catalyst: Feminism, Theory, Technoscience. 2017;3(1):1–30. Reference Source [Google Scholar]
  111. Wang CY, Mercer E, Kamranvand F, et al. : Tube-side mass transfer for hollow fibre membrane contactors operated in the low Graetz range. J Memb Sci.Elsevier,2017;523:235–246. 10.1016/j.memsci.2016.09.049 [DOI] [PMC free article] [PubMed] [Google Scholar]
  112. WHO, UNICEF: Progress on Drinking Water, Sanitation and Hygiene - 2017 Update and SDG Baselines. Geneva, Switzerland. 2017. Reference Source [Google Scholar]
  113. Wynn DC: Model-Based Approaches to Support Process Improvement in Complex Product Development.Cambridge University.2007. 10.17863/CAM.13990 [DOI] [Google Scholar]
  114. Wynn DC, Clarkson PJ: Process models in design and development. Research in Engineering Design.Springer London,2018;29(2):161–202. 10.1007/s00163-017-0262-7 [DOI] [Google Scholar]
  115. Wynn DC, Eckert CM: Perspectives on iteration in design and development. Research in Engineering Design Springer London.2017. 10.1007/s00163-016-0226-3 [DOI] [Google Scholar]
  116. Yates F: Sir Ronald Fisher and the Design of Experiments. Biometrics. 1964;20(2):307–321. 10.2307/2528399 [DOI] [Google Scholar]
  117. Yim H, Lee K, Brezing A, et al. : A Design-Engineering Interdisciplinary and German-Korean Intercultural Design Project Course. In Proceedings of NordDesign 2014 Conference2014;27–36. Reference Source [Google Scholar]
  118. Zanoff J, Ekwaro-Osire S: An approach that can quickly assess product reliability. Quality and Reliability Engineering International. 2010;26(6):571–578. 10.1002/qre.1080 [DOI] [Google Scholar]
  119. Zhang ZZ, Qin JQ, Di CC, et al. : An Introductory Review of Mechanical Reliability Testing. Applied Mechanics and Materials. 2014; 541–542,1414–1418. 10.4028/www.scientific.net/AMM.541-542.1414 [DOI] [Google Scholar]
Gates Open Res. 2019 Oct 1. doi: 10.21956/gatesopenres.14186.r27764

Reviewer response for version 1

Christer W Elverum 1, Aksel Elkjaer 1

The paper argues that there is a lack of literature on how to plan and conduct tests, especially for something as complex as the presented case study. The authors then proceed to review four testing approaches and propose a testing strategy that covers the entire product development process.

The context of the problem is thoroughly covered, including the challenge from the Gates Foundation, sanitation problems and state of the art. The paper covers recent research on testing and addresses testing in product development from a holistic point of view which is an area currently lacking in the literature.

However, there are some major issues that need to be addressed.

  1. Testing approaches:
    • The four testing approaches chosen appear to be quite arbitrarily selected. Why were these chosen over other alternatives?
    • Why is "testing for UCD" presented as a testing approach? This is notably understated as a testing approach as it is a part of a much larger framework. Perhaps "usability testing" is more fitting as a testing approach instead?
    • Is DOE in the same “dimension” as the other approaches? The other approaches have a target (e.g. reliability, compliance, usability) whereas DOE is methodological theory that can be applied when performing a test or experiment. The approaches cannot, in our opinion, be directly compared. DOE certainly has an important role in testing approaches but should perhaps be considered more of a foundational underlying framework than simply an approach.
  2. Validity of framework and overall contribution:
    • As the model is untested, even in the context of the NMT, one can question the validity of the model. Most case studies apply an inductive approach where the goal is to create something more generalizable that can be used for other projects as well, this is lacking in this paper. The flowchart simply states which of the four testing methods should be used at each stage, what about focusing on the objectives or outcome as well? In other words, the outcome that is expected/required at each stage to progress the development.
  3. Discussion and conclusion should focus more on the applicability to other contexts. How can researchers and practitioners benefit from this work?

In addition to these issues there are some minor issues that should be resolved.

  • Additional nuances regarding iterations would be beneficial. Iterations may happen at a smaller scale than highlighted in the paper. Iterations in the development of complex systems do not necessarily happen on a system level. It is assumed the authors have already considered iteration characteristics from the notably different magnitudes of iteration arrows communicating an (undefined?) difference in importance. Do the authors have additional justification for the location, importance and dependencies of the presented iterative loops? Adding information addressing development dependencies to the iteration stages would improve the planning and communication of the visualized strategy. This could be achieved by relating the flowcharts perspective of iterations to agile philosophy advocating the benefits short iterations cycles provide to communication.

  • The TRL seems to be forgotten after the introduction. It should perhaps be a part of the visualization as the figure covers most of the development.

  • The authors state on multiple occasions that it was necessary to define the test strategy considering the disruptive nature of the technology, but limited focus is given to what impact this caused on the formulation of the flow chart strategy. Justification of which parts of the strategy were directly defined considering a disruptive product innovation may assist in generalizing the proposed framework.

  • The NTM is highlighted as an “unusual case of product development” due to its combination of highly innovative back-end technology development while maintaining consistent front-end performance. This is comparable to many sustainable product development cases, from electric cars to plastic bags, where the objective is to maintain our current capabilities with new technology. The authors are encouraged to further promote the relevance of the case study in a wider context.

We confirm that we have read this submission and believe that we have an appropriate level of expertise to confirm that it is of an acceptable scientific standard, however we have significant reservations, as outlined above.

Gates Open Res. 2019 Nov 8.
Jan Hennigs 1

We want to thank the reviewers' for their comments, which were greatly appreciated and considered in the updated version! Please refer to the 'note to readers' for details of changes in the updated version.

Gates Open Res. 2019 Sep 24. doi: 10.21956/gatesopenres.14186.r27767

Reviewer response for version 1

Khadija Tahera 1

  • This research is in an interesting topic of prototype testing. This paper has partly addressed the issues of prototype testing and proposed a solution that integrates four approaches/methods/tools however, the rationale of choosing these four approaches is not clearly mentioned.

  • A major concern would be that all four of these approaches are considered as testing approaches, which they are clearly not (as my understanding). It needs to clearly come out as to why these approaches are considered as testing approaches.

  • The proposed solution has high potential but is in a preliminary stage and would need a significant improvement for scientific publication.

  • Please see my detailed comments on the attached document linked here.

I confirm that I have read this submission and believe that I have an appropriate level of expertise to confirm that it is of an acceptable scientific standard, however I have significant reservations, as outlined above.

Gates Open Res. 2019 Nov 8.
Jan Hennigs 1

We want to thank the reviewers' for their comments, which were greatly appreciated and considered in the updated version! Please refer to the 'note to readers' for details of changes in the updated version.

Gates Open Res. 2019 Sep 18. doi: 10.21956/gatesopenres.14186.r27763

Reviewer response for version 1

Eckhard Kirchner 1, Stefan Schork 2

In this paper a unified testing strategy flow chart is presented. The flow chart is introduced to support the prototyping process of a nano membrane toilet (NMT) but should be usable in other design projects as well. The strengths of the flow chart are that its application visualizes the planned testing efforts and supports the communication between teams and people new to the project.

The paper addresses a relevant topic both in engineering and science. It is well structured and the originality of the work is good. There is a high number of relevant and high-quality references and the work of others is acknowledged. The paper is well written and easy to understand but a final proof read to eliminate some minor spelling mistakes is advised.

Thoughts and recommendations:

  1. The paper focuses on the testing of physical prototypes, which is stated in the introduction. However, there is no further explanation of how and why this decision was made. Please elaborate on this decision.

  2. The number and quality of references is quite high. Nevertheless, there is a paper by Camburn et al. (2017 1) which is missing in my opinion and could provide some useful information.

  3. Table 1 shows the technology readiness levels. In this work however, the TRL are only used to explain the current state of development of the NMT (TRL level 6). There is no inclusion of the TRL in the flow chart which raises the question, if the table showing all TRL is needed in this paper. My recommendation is to either use the TRL in the later parts of the paper as well or to delete the table.

  4. The flow chart itself is of good quality. There are many “iteration possible” arrows included which raises some questions. Why are there only two of those arrows on the frontend side but six on the backend side? Is there any intention of visualizing which iterations are possible? For example, would an iteration on the frontend side from the validation phase to the exploration phase be possible? My recommendation therefore is to revise the flow chart in terms of visualizing possible iterations and to elaborate those iterations in the text.

  5. The conclusion is very short and has more of a summarizing character than a concluding one. Please strengthen this section by pointing out the core aspects of your work.

We confirm that we have read this submission and believe that we have an appropriate level of expertise to confirm that it is of an acceptable scientific standard, however we have significant reservations, as outlined above.

References

  • 1. : Design prototyping methods: state of the art in strategies, techniques, and guidelines. Design Science.2017;3: 10.1017/dsj.2017.10 10.1017/dsj.2017.10 [DOI] [Google Scholar]
Gates Open Res. 2019 Nov 8.
Jan Hennigs 1

We want to thank the reviewers' for their comments, which were greatly appreciated and considered in the updated version! Please refer to the 'note to readers' for details of changes in the updated version.

Associated Data

    This section collects any data citations, data availability statements, or supplementary materials included in this article.

    Data Availability Statement

    All data underlying the results are available as part of the article and no additional source data are required.


    Articles from Gates Open Research are provided here courtesy of Bill & Melinda Gates Foundation

    RESOURCES