Skip to main content
Springer Nature - PMC COVID-19 Collection logoLink to Springer Nature - PMC COVID-19 Collection
. 2021 Apr 26;7(3):77. doi: 10.1007/s40819-021-01003-8

Innovative Approach of EOQ Structure for Decaying Items with Time Sensitive Demand, Cash- Discount, Shortages and Permissible Delay in Payments

R P Tripathi 1,
PMCID: PMC8074708  PMID: 33937442

Abstract

Growing business process and rising aggressive conditions are encouraged to use the inventory control scheme and components in an ideal way. Cash discount and permissible delay are beneficial for vendor and buyer both. This study considers an EOQ model through demand rate depends on the time. A lower or higher time leads to lower or higher demand after feedback vice versa. In this paper deterioration, cash- discount, shortages and permissible delay are also considered. Mathematical models are discussed under four different states of affair. Solution method is given for finding the finest answer. The main aim is to maximize total profit. Numerical examples are provided for all four dissimilar situations. Optimal values with strictures are calculated to analyze the sensitivity investigation of optimal strategy concerning the parameters of the system. It is revealed that the total income is concave by means of cycle time.

Keywords: Cash- discount; Inventory; Deterioration, Shortages, Demand, Trade credit

Introduction

The production of commodities is the first stage of manufacture. Three stage system, a manufacturer, seller and market are considered in the process. The retailer’s term represents for part of the system works as a bridge between market and manufacturer. EOQ models begin by taking into account that the demand rate was stable along with cycle time. This assumption was a serious restriction because in real life, demand of a commodity can depend on such multiple issue at the time, stock – level, quantity, selling price, lead time, advertisings, rebate, exponential etc.

Silver and Peterson [1] pointed out that the demand rate of some goods may be influenced by the stock stage. Indeed, huge heaps of supplies exhibited in a superstore sometimes guides buyers to purchase more. There are two common rules for the inventory manager always keep high stock- level to make best use of profit of the inventory administration and depleting the order a new order begins. It might be profitable to raise the order level in each cycle and request a fresh order previous two stock runs out. Baker and Urban [2] designed an EOQ model with a store- linked, where the aim was profit maximization. Tripathi [3] analyzed an EOQ structure of items whose demand is a decreasing association of trade cost. Alfares [4] published the inventory model containing stock- echelon sensitive demand and a storage time- connected, carrying cost taking two times – linked holding cost functions. Tripathi and Mishra [5] described a production inventory model for time – associated demand. Time induced demand EOQ systems are established by Dave [6] and Maiti et al. [7]. Yang [8] described a structure under store- linked demand rate and stock- connected carrying cost under shortages. Several research papers published in this direction by Chang et al. [9], Soni and Shah [10], Tripathi [11],Teng et al. [12], Hsieh and Dye [13], Wee and Wang [14], Zhou et al. [15], Shah et al. [16] etc.

Deterioration of items is a major problem in the universe. Generally almost all items deteriorate with time. Deterioration means freshness decay of commodities. A normal common man declines his activity after passing the time and at last comes to the end. Tripathi and Pandey [17] studied an EOQ model to find the optimal total cost for price sensitive demand with Weibull distribution. Geetha and Kumar [18] addressed a model in which inventory cost will be lowered, if the seller can effectively reduce deterioration by improving the storage facility. Jaggi et al. [19] offered a model, including selling price dependent demand under deterioration. Mishra and Talati [20] proposed a single set- up multiple deliveries for fading stuff with fixed life time.Jani et al. [21] have studied an inventory policy for the item which has expiry date with two levels of trade credit depending on the quantity of order. It is considered that a supplier is ready to give a mutually agreed credit period to retailer only if the order quantity purchased by retailer is more than the predetermined quantity of ordered. Some researches in this in this direction are Chaudhury et al. [22], Duan et al. [23], Pervin et al. [24], Teng and Chang [25], Dye [26], Ghiami and Williams [27], Shah et al. [28] and others.

In the world economics, inflation and time value of capital cannot be unnoticed because of uncertainty of demand, weather, climate change abruptly, storm lock down (for example COVID-19), labor strike, flood etc. Buzacott [29] presented first an EOQ system by assuming inflationary effect on costs. Yang et al.[30] designed a variety of EOQ models with time – unstable demand pattern under inflation. Sarkar and Moon [31] explored a manufacture EOQ model for random demand through cause of inflation.Chaudhari et al. [32] designed a single retailer and single product which deteriorates continuously for time dependent deteriorating item with seasonal demand, quadratic demand is debated here which is suitable for the items whose demand with starting of the season increases initially and after end of the season, it starts decreases. Reduction of deterioration is reduced by preservation technology. Some researchers like Sarkar et al. [33], Yang [34], Dey et al. [35], Tripathi and Chaudhary [36] consequences special type of structures under inflation and time – reduction.

Trade credits and shortages both play an important role in any type of business. Tripathi [37] published at an EOQ system for spoilage products with curvilinear time – linked demand, shortages under traffic credits. Pal and Chandra [38] established a sporadic review EOQ model under traffic credits and price discounts. Chern et al. [39] extended an EOQ system to include particulars that (i) advertising cost is considerably superior to unit acquiring cost and (ii) interest rate charged by the trader is not essentially advanced than the seller’s savings return rate under permitted delay. Jiangtao et al. [40] addressed a multi- commodity system for unpreserved substances where demand rates of goods are stored- linked two- echelon traffic credits. Chern and Teng [41] designed an EOQ system for trader for finding his/ her best possible replenishment cycle time, included the fact that (i) failing foodstuffs decline constantly and having utmost life time and (ii) a seller frequently proposes an allowed delay in payments to draw additional purchasers.

The remainder of the work designed as follows. In the subsequent Sect. 2, assumptions and notation are mentioned. Mathematical formulation is argued in Sect. 3. The most beneficial explanation is renowned in part 4. After that, numerical examples are offered of all four cases to display hypothetical fallouts. Sensitivity exploration by means of distinct parameters is conversed in segment 6. We present conclusion and future research in the last.

Notations and Assumptions

Notations

K cost of ordering (in $)

c,p,h and s unit purchasing, selling, carrying and shortage cost/item

Q1 and Q2 highest inventory level and maximum shortage quantity

Q Lot – size

D(t) demand rate

Ip and Ie unit interest paid and earned/$

Q(t) level of inventory at moment ‘t’

ϕ deterioration rate.

r cash reduction rate, ‘r’ lies between zero and one

t1 time to end up inventory

M1 and M2 stage of cash reduction and allowable delay (M2 > M1)

T cycle time.

CH,CD and CS carrying, deterioration and shortages cost

SR sales profits

IP1and IP3 interest payable (in $) (cases 1 and 3)

IEi interest earned (in $), i = 1- 4

Ti* optimal T

Pi(T) total profit /yr (in $)

Assumptions

  1. Demand rate is time- sensitive, i.e. D (t) = α + β.t, α is positive, 0 ≤ β ≤ 1, β is not zero.

  2. Shortages are permitted.

  3. Vendor suggests cash discount, if payment is ready in t1, or as a well full expense is charged. Inside credit period M2.

  4. Replenishment arises immediately at endless pace.

  5. Deterioration rate is steady, 0 ≤ ϕ < 1.

Mathematical Models

Reduction of originality is a shapeless and natural phenomenon for items with passing time. Some preservation technologies can maintain freshness for some time, but they cannot continue for a long time. The level of inventory Q (t) for some moment ‘t’ is ruled by subsequent equations are:

dQ(t)dt=-ϕQ(t)-D(t),0tt1-D(t),t1tT 1

Solution of (1) and (2) with Q(t1) = 0 is:

Q(t)=1ϕαϕ-βeϕ(t1-t)-1ϕ+βt1eι(t1-t)-t-(t-t1)α+βt1+t2 2
Q=Q1+Q2 3

where Q1 and Q2 is obtained by substituting t = 0 and t = T in (4) and (5) respectively?

CH=hϕα-βϕeϕt1-1-ϕt1ϕ+βt1eϕt1-1ϕ-t12 4
CS=st1T-Q(t)dt=s(T-t1)263α+β(T+2t1) 5

Since seller offers permitted delay of cash reduction and payment. As a result, two situations may occur (i) payment is pleased at M1 with reduction and (ii) payment is paid at M1, lacking the cash diminish.

Case 1: M1 ≤ t1 ≤ T

In nearby learning, T ≥ M1. Since supplier presents allowed delay of cash concession, interest paid is nil. Figures of all mentions cases are as follows:

Therefore,

IP1=cIpϕα-βϕeϕ(t1-M1)-1-ϕ(t1-M1)ϕ+βt1eϕ(t1-M1)-1ϕ-t12-M122 6
IE1=pIc0M1(α+βt).t.dt=pIeM12α2+βM13 7

And,

SR=p0T(α+βt)dt=pTα+βT2 8

The trader gets a cash allowance from supplier, due to payment is remunerated at M1. Thus

CD=rp1ϕα-βϕ(eϕt1-1)+βt1eϕt+(T-t1)2α+β(t1+T)2 9

Thus,

P1T=SR-A+CH+CS+IP1-IE1-CD/T 10

Case 2: M1 > T

In this situation, M1 > T, therefore IC2 = 0 and

IE2=pIet1αM1-t12+βt12M1-t13 11

Thus,

P2T=SR-A+CH+CS-IE2-CD/T 12

Payment is Compensated at Credit Phase M2

Case 3: M2 < T

In such case, T > M2, the seller has no cash price cut, thus

IP3=cIpM2t1Q(t)dt 13
IE3=pIe0M2(α+βt)tdt=pIeM22α2+βM23 14

As a result

P3T=SR-(A+CH+CS+IP3-IE3)/T 15

Case 4: M2 ≥ T

In this situation, T ≤ M2, the vendor has no cash price cut & IP4 = 0, thus

IE4=pIet1αM2-t12+βt12M2-t13 16
P4T=SR-(A+CH+CS-IE4)/T 17

For small decline rate, we can presume (Figs. 1, 2, 3 and 4).

eϕT1+ϕT+ϕ2T22etc,ϕT<1 18

Fig.1.

Fig.1

M1 < T

Fig. 2.

Fig. 2

M1 ≥ T

Fig.3.

Fig.3

M2 < T

Fig. 4.

Fig. 4

M2 ≥ T

Hence, the entirety income of case 1–4 is falling too:

P1=(1+r)p2α+βT2-KT-ht12α3+ϕt1+t12+θT1β6T-s(T-t1)23α+β(2t1+T)6T-cIp(t1-M1)26Tα3+t1-M1ϕ+βM1+2t1+ϕt1-M1t1+pIeM126T3α+2βM1+rpϕt12(α+βt1)2T 19
P2=p(1+r)α+βT2-KT-ht12a3+ϕt1+t12+ϕt1β6T-s(T-t1)23α+(T+2t1)β6T+pIet16T3α2M1-t1+βt13M1-t1+rp2α+βT2+rpt12(α+βt1)ϕ2T 20
P3=pα+βT2-KT-ht12α3+ϕt1+β2+ϕt1t16T-s(T-t1)23α+β(2t1+T)6T-cIp(t1-M2)2α3+ϕt1-M2+βM2+2t1+ϕt1-M2t16T+pIeM22Tα2+βM23 21
P4=pα+βT2-KT-ht126Tα3+ϕt1+2+ϕt1βt1-s(T-t1)23α+β(T+2t1)6T+pIet16T3α2M2-t1+β3M2-t1t1 22

Since t1 < T, taking, t1 = γT, γ is stable ( 0 < γ < 1). Equations (19) – (22) become:

P1(T)=p(1+r)2α+βT2-KT-hγ2α3+γϕT+β2+ϕγTγTT6-s(1-γ)23α+(1+2γ)βTT6-cIpTγ-M12α3+ϕ(γT-M1)+βM1+2Tγ+γϕ(Tγ-M1)T3T+pIe3α+2βM1M126T+rpγ2(α+βγT)T2 23
P2(T)=(1+r)p2α+βT2-KT-hγ2α3+ϕγT+βγ2+γϕTTT6-s(1-γ)23α+βT(1+2γ)T6+pIeγ3α2M1-γT+βγT3M1-γT6+rϕγ2(a+βγT)pT2 24
P3(T)=pα+βT2-KT-hγ2a3+ϕγT+β2+γϕTγTT6-s(1-γ)23α+β(1+2γ)TT6-cIpγT-M226Tα3+(γT-M2)ϕ+βM2+2γT+γϕ(γT-M2)T+pIe3α+2βM2M226T 25
P4(T)=p2α+βT2-KT-hγ2Tα3+ϕγT+βγ2+ϕγTT6-s(1-γ)23α+β(2γ+1)TT6+pIeγ3α2M2-γT+βγT3M2-γT6 26

Optimal Solution

Necessary and sufficient circumstances for maximization are: dPidT=0,andd2PidT2<0. Pi,for i = 1–4.

Putting first derivative of (23) – (26) w.r.t. T, to zero, we find

3β(1+r)pT2+6K-hγ2T2α3+2γϕT+β4+3γϕTγT-s(1-γ)23α+21+2γβTT2-cIpγT2-M12α3+ϕ(Tγ-M1)+M1+2Tγ+ϕγ(γT-M1)Tβ-cIpγγT-M12Tαϕ+β2+(2Tγ-M1)ϕ-pIe3α+2βM1M12+rpγ2ϕ(α+2βγT)T2=0 27
6β(1+r)pT2+6K-hγ2T2α3+2γϕT+γβ4+3ϕγTT-s(1-γ)23α+2β1+2γTT2_pIeγ23α-β3M1-2γTT2+rpϕ(γT)2(α+2γβT)=0 28
3βpT2-hγ2T2α3+2γϕT+βγT4+3γϕT-s(1-γ)23α+2β1+2γTT2-cIpT2γ2-M22α3+ϕ(γT-M2)+βM2+2γT+ϕγ(γT-M2)T-cIpγTγT-M22αϕ+β2+ϕ(2γT-M2)-pIeM223α+2βM2-3cIp(t1-M2)2(α+βt1)-pIeM22(3α+2βM2)+6K=0 29

and

3βpT2+6K-hγ2α3+2γϕT+βγ4+3γϕTTT2-s(1-γ)23α+21+2γβTT2+pIeγ2T23α-3M2-2γTβ=0 30

Also

d2P1dT2=-2KT3-hγ3αϕ+β(2+3ϕγT3-sβ(1-γ)2(2γ+1)3-cIpγ2T2-M12αϕ+β2+ϕ(2γT-M1)3
cIpM12T3α1+ϕ(γT-M1)3+M1+2γT+ϕγ(γT-M1)T+cIpλ2βϕT3+rβpϕγ3 31
d2P2dT2=-2KT3+hγ3αϕ+β(2+3ϕγT3+sβ(1-γ)2(1+2γ)3+βpIeγ33-rβpϕγ3<0 32
d2P3dT2=-2KT3-hγ3αϕ+β(2+3ϕγT3-sβ(1-γ)2(1+2γ)3-cIpγ2T2-M22αϕ+β2+ϕ(2γT-M2)3-cIpM22T3α1+(γT-M2)ϕ3+M2+2γT+γϕT(γT-M2)-cIpγ2βϕ3T+2pIeM22T3α2+βM23<0 33
d2P4dT2=-2KT2+hγ3αϕ+β2+3γϕT3-s(1-γ)21+2γ3+βpIeγ33<0 34

Since d2PidT2<0, i = 1 - 4. Pi is maximum at Ti*. We have also shown by graphs in numerical examples.

Algorithm

In this section, we provide a solution procedure and flow diagram for finding an optimal resolution.

Step 1 locate Ti* by resolve (27)–(30), i = 1–4.

Step 2 if T1* ≥ M1, come across P1* by (23).

Step 3 if T2* < M1, discover P2* by (24).

Step 4 if T3* ≥ M2, find P3* by (25).

Step 5 if T4* < M2, locate P4* by (26).

Step 6 Obtain most favorable income Pi = max Pi.

Step 7 end.

Numerical Examples

Examples are supplied to make obvious conclusions of structure discussed in each case:

Example 1

(M1 ≤ T).

Bearing in mind subsequent constrains in proper component:

α = 1.5 × 103, β = 150, ϕ = 1/100, s = 100, K = 1.0 × 103, p = 250, h = 10, Ie = 13/100, Ip = 3/20, M1 = 1/5 yr, c = 100, r = 1/50 & γ = 3/5. Putting these in (27), and resolving for T, we find, T1* = 0.65989 yr, that validate case 1, cprresponding Q* = 1023.7 and P1* = $ 2973.7.

Example 2

(M1 > T).

Considering following strictures in their suitable units:

α = 1.5 × 103, β = 150, ϕ = 1/100, s = 500, h = 10, K = 100, p = 300, Ie = 13/100, Ip = 3/20, M1 = 1/5 yr, c = 50, r = 1/50 & γ = 3./5. Replacement of those in (28) and solving for T, we gain, T2* = 0.1157 yr, which proves case 2, accordingly Q* = 174.57 & P2* = $ 794.37.

Example 3

(M2 < T).

Let us choose following constraints in proper entities:

α = 1.1 × 103, β = 150, ϕ = 1/100, s = 100, K = 1.0 × 103, p = 250, h = 10, Ie = 13/100, Ip = 3/20, M1 = 1/4 yr, c = 100, r = 1.50, and M2 = 140 days. On putting these (29) and solving for T, we find, T3* = 0.42588 yr, which confirms case 3, related Q* = 652.92 & P3* = $3082.5.

Example 4

(M2 ≥ T).

Following constraints are taken in suitable units:

α = 1.5 × 103, β = 150, ϕ = 1/100, s = 100, K = 1.0 × 103, p = 500, h = 10, Ie = 13/100, Ip = 3/20, c = 50, r = 1/100, and M2 = 1/4 yr. On substituting those in (30), and solving for T, we obtain, T4* = 0.19933 years, that verifies case 4, resultant Q* = 338.0 & P4* = $2328.2.

Using above algorithm Case 3 gives the optimal (maximum) solution (Figs. 5, 6, 7 and 8).

Fig. 5.

Fig. 5

Figure between T & P1

Fig. 6.

Fig. 6

Illustrative depiction connecting T & P2

Fig. 7.

Fig. 7

Pictographic demonstration connecting T and P3

Fig. 8.

Fig. 8

Graphical depiction T vs. P4

Sensitivity Analysis

Case 1

Considering identical data as in Ex. 1, sensitivity study is conversed. Fallouts are reviewed in Table 1.

Table 1.

Deviation of T, Q and Pi by s, K, c, p, h, ϕ, α and β

s T* Q* P1* K T* Q* P1*
105 0.55973 863.97 2448.7 1100 0.69855 1085.8 2882.8
110 0.48786 750.29 2020.7 1200 0.73295 1141.2 2793.4
115 0.43481 666.92 1717.6 1300 0.76408 1191.6 2705.4
120 0.39437 603.65 1347.1 1400 0.79263 1237.8 2619.0
125 0.36259 554.11 1069.4 1500 0.81908 1280.8 2533.9
c T* Q* P1* p T* Q* P1*
105 0.63346 981.41 2903.7 260 0.80909 1264.6 3860.7
110 0.61039 944.57 2842.4 270 1.01837 1608.3 4993.1
115 0.59018 912.36 2788.4 280 1.27802 2044.3 6417.3
120 0.57241 884.10 2740.8 290 1.56867 2544.8 8148.3
125 0.55671 859.18 2698.5 300 1.87570 3088.0 9976.4
h T* Q* P1* ϕ T* Q* P1*
12 0.57088 881.67 2505.4 0.02 0.65874 1023.2 2969.2
14 0.50394 775.66 2113.6 0.03 0.65771 1022.7 2964.8
16 0.45278 695.11 1777.9 0.04 0.65664 1022.1 2960.4
18 0.41281 632.46 1483.8 0.05 0.65559 1021.6 2956.0
20 0.38084 582.53 1221.2 0.06 0.65454 1021.2 2951.7
1250 1.8827 2533.8 8242.99 200 2.24652 3890.5 13,933.5
α T* Q* P1* β T* Q* P1*
1000 2.9219 3581.6 14,854.0 160 0.92394 1456.7 4323.9
1050 2.6585 3337.9 12,968.5 170 1.26014 2029.8 6151.1
1100 2.3968 3080.9 11,238.0 180 1.60881 2654.0 8405.0
1200 2.1378 2812.2 9662.94 190 1.94021 3279.6 11,017.0
1250 1.8827 2533.8 8242.99 200 2.24652 3890.5 13,933.5

Case 2

Using the same figures as in Ex. 2, sensitivity scrutiny is conversed in Table 2.

Table 2.

Disparity of T, Q and Pi with s, K, p, h, α, and β

s T* Q* P2* K T* Q* P2*
510 0.10770 162.46 995.48 105 0.11837 178.65 639.13
520 0.10111 152.47 1146.3 110 0.12098 182.60 467.84
530 0.09557 144.07 1260.5 115 0.12352 186.46 340.12
540 0.09083 136.89 1347.3 120 0.12599 190.22 195.83
p T* Q* P2* h T* Q* P2*
280 0.09515 143.43 1044.4 12 0.11192 168.85 891.37
285 0.09929 149.71 1025.6 14 0.10848 163.62 976.45
290 0.10440 156.84 982.16 16 0.10532 158.84 1032.2
295 0.10941 165.04 907.87 18 0.10241 154.43 1117.2
310 0.15204 199.42 397.41 20 0.09972 150.36 1175.4
α T* Q* P2* β T* Q* P2*
1600 0.20466 330.71 2508.0 120 0.07868 118.40 1933.9
1700 0.19034 326.41 2584.1 125 0.08253 124.24 1874.5
1800 0.17865 324.06 2865.0 130 0.08699 130.99 1771.0
1900 0.16886 323.07 3171.3 135 0.09222 138.93 1663.0
2000 0.16051 323.05 3501.8 140 0.09848 148.42 1524.6

Case 3

With parallel information as in Ex 3, sensitivity inquiry id discussed below:

Case 4

By means of alike data as design in Ex. 4, sensitivity inspection is as follows:

Following judgment can be finished from Table 1:

  1. Enlarge of s, K, c and it will cause a drop of P1.

  2. Elevate of ‘p’ and ϕ will lead augment in P1.

Following submission can be equipped from Table 2.

  1. Lift of s, K and h will cause weakening in P2.

  2. Raise of p consequences enhances P2.

Following proposition can be finished from Table 3.

  1. Boost of s, K, and h will direct diminish P3.

  2. Augment of will direct decline in P3.

  3. Amplification of p causes moves up in P3.

Table 3.

Dissimilarity of T, Q and Pi by s, K, c, p, h, α. β and ϕ

s T* Q* P3* K T* Q* P3*
75 1.67627 2733.5 6987.5 1100 0.49783 766.03 2866.4
80 1.31673 2110.2 5093.2 1200 0.55300 853.29 2676.3
85 1.00272 1582.4 4340.7 1300 0.59869 925.92 2502.7
90 0.74353 1158.3 3786.5 1400 0.63815 988.91 2341.1
95 0.55171 857.21 3383.2 1500 0.67315 1045.0 2186.6
c T* Q* P3* p T* Q* P3*
105 0.42468 651.04 3082.9 260 0.52326 806.18 3576.3
110 0.42375 649.59 3082.4 270 0.60849 941.53 3847.7
115 0.42302 648.50 3082.4 280 0.72163 1123.0 4148.2
120 0.42342 647.51 3082.4 290 0.85594 1340.9 4487.9
125 0.42193 646.74 3082.4 300 1.00290 1582.7 4874.5
h T* Q* P3* α T* Q* P3*
4 0.88331 1385.7 4114.6 1050 2.4952 2838.8 9524.6
5 0.77881 1215.4 3882.6 1100 2.2308 2563.1 8170.0
6 0.68476 1063.6 3679.2 1150 1.9681 2407.9 6982.0
7 0.60240 1024.3 3501.0 1200 1.7079 1978.6 5959.8
8 0.53225 820.04 3344.5 1250 1.4518 1675.3 5101.8
β T* Q* P3* ϕ T* Q* P3*
160 0.68667 1019.1 3016.7 0.03 0.42441 651.61 3080.5
170 1.05000 1671.9 4298.9 0.04 0.42368 650.97 3079.4
160 1.41903 2315.8 5859.2 0.05 0.42296 650.33 3078.5
190 1.76202 2947.4 7735.1 0.06 0.42239 649.69 3077.5
200 2.07512 2556.9 9809.1 0.07 0.42153 649.06 3076.5

Deductions made from Table 4 are as follows:

  1. Boost of s and p will express make bigger in P4.

  2. Improve of A and h lead, turn down in P4.

Table 4.

Discrepancy of T, Q & Pi by s, K, c, p and h

s T Q* P4* K T* Q* P4*
460 0.21621 327.94 2178.7 950 0.21711 329.32 2657.3
470 0.21024 318.80 3026.5 960 0.21824 331.06 2590.9
480 0.20475 310.39 1872.6 970 0.21837 332.80 2524.7
490 0.19968 302.62 1717.4 980 0.22050 334.52 2454.9
500 0.19498 285.42 1561.5 990 0.22162 336.24 2393.4
p T* Q* P4* h T* Q* P4*
450 0.20427 306.45 700.10 12 0.21976 333.39 2261.4
460 0.20758 314.72 1022.0 14 0.21691 329.02 2194.0
470 0.21107 320.06 1361.2 16 0.21417 324.81 2126.1
480 0.21474 325.70 1687.2 18 0.21153 320.80 2052.7
490 0.21862 331.65 2009.7 20 0.20899 316.87 1989.0
α T* Q* P3* β T* Q* P3*
1600 0.20466 330.71 2584.1 100 0.17645 266.32 727.25
1700 0.19034 326.41 2865.0 110 0.18345 277.12 1047.4
1800 0.17865 324.06 3171.4 120 0.19134 289.31 1369.4
1900 0.16886 323.07 3501.8 130 0.20032 303.20 1691.9
2000 0.16051 232.05 3854.8 140 0.21065 319.21 2012.7

Managerial Insights

These above deviations have the following managerial implications.

  • Higher values of s, c, h, ϕ and α implies lower values of cycle time, order quantity and total profit for case I and III.

  • Higher values of p and β implies higher values of cycle time, order quantity and total profit for case I and III.

  • Higher values of K implies higher values of cycle time and order quantity while lower values of total profit.

  • Higher values of s, h, and α implies lower values of cycle time,order quantity and lower values total profit for case II and IV.

  • Higher values of K, p, and β implies higher values of cycle time,order quantity and lower values total profit for case II and IV.

Conclusion

In this study, we have deliberated EOQ models under trade credits permit for four unlike conditions. We have attempted to locate characteristic of cash decline into the conventional model with permitted delay. Numerical examples are completed on credible attempt. Optimal explanation is acquired for finding optimal variables. Solution process is communicated to find most advantageous solution. Sensitivity reading of the clarification for dissimilar constraints has been conferring. This research is obliging for returning products since demand for continuing foodstuffs is usually time allied. It is seen that disparity in shortage, ordering, procure, carrying and selling costs, lead to momentous possessions on finest Pi, i = 1–4). Entire income is around stable with adjust in weakening rate. Outcomes came into view in sensitivity analysis is conflicting, like expand in cost fallouts reject of earnings whereas intensify in selling price argued lift in income.

A variety of likely extensions of the model that can be presented as like: (i) variable decay and Weibull deterioration (ii) to assume a variable carrying cost (iii) to comprise fall in the purchasing cost/ unit (iv) to study the case of inflation and shipment charges and (v) to study stock- sensitive demand.

Footnotes

Publisher's Note

Springer Nature remains neutral with regard to jurisdictional claims in published maps and institutional affiliations.

References

  • 1.Silver ES, Peterson R. Decision systems for inventory management and production planning. 2. New York: Wiley; 1995. [Google Scholar]
  • 2.Baker RC, Urban TL. A deterministic inventory system with an inventory level- dependent demand. Euro. J. Oper. Res. 1988;39:823–831. [Google Scholar]
  • 3.Tripathi RP. Economic order Quantity models for price dependent demand and different holding cost functions. Jor. J. Math. Stat. 2019;12(1):15–33. [Google Scholar]
  • 4.Alfares HK. Inventory model with stock- level dependent demand rate and variable holding cost. Int. J. Prod. Eco. 2007;108:259–265. doi: 10.1016/j.ijpe.2006.12.013. [DOI] [Google Scholar]
  • 5.Tripathi RP, Mishra S. Innovative study of EPQ model with time – induced demand under decline release. Int. J. Sup. Chain. Oper. Manag. 2019;6(1):264–275. [Google Scholar]
  • 6.Dave U. An order level inventory model for deteriorating items with variable instantaneous and discrete opportunities for replenishment. Opsearch. 1986;23:244–254. [Google Scholar]
  • 7.Maiti AK, Maiti MK, Maiti M. Inventory model with stochastic lead time and price dependent demand incorporating advance payment. App. Math. Mod. 2009;33:2433–2443. doi: 10.1016/j.apm.2008.07.024. [DOI] [Google Scholar]
  • 8.Yang CT. An inventory model with both stock- dependent demand rate and stock- dependent holding cost rate. Int. J. Pro. Eco. 2014;155:214–221. doi: 10.1016/j.ijpe.2014.01.016. [DOI] [Google Scholar]
  • 9.Chang CT, Teng JT, Goyal SK. Optimal replenishment policies for non-instantaneous deteriorating item with stock- dependent demand. Int. J. Pro. Eco. 2010;123:62–68. doi: 10.1016/j.ijpe.2009.06.042. [DOI] [Google Scholar]
  • 10.Soni H, Shah NH. Optimal Ordering policy for stock- dependent demand under progressive payment scheme. Eur. J. Oper. Res. 2008;184:91–100. doi: 10.1016/j.ejor.2006.10.048. [DOI] [Google Scholar]
  • 11.Tripathi RP. Inventory model with time – dependent demand rate under inflation when supplier credit linked to order quantity. Int. J. Bus. Inf. Tech. 2011;1(3):174–18. [Google Scholar]
  • 12.Teng JT, Min J, Pan Q. Economic order quantity model with trade credit financing for non- decreasing demand. Omega. 2012;40:328–335. doi: 10.1016/j.omega.2011.08.001. [DOI] [Google Scholar]
  • 13.Hsieh TP, Dye CY. A production – inventory model incorporating the effect of preservation technology investment when demand is fluctuating with time. J. App. Comp. Math. 2003;239:25–36. doi: 10.1016/j.cam.2012.09.016. [DOI] [Google Scholar]
  • 14.Wee HM, Wang WT. A variable production scheduling policy for deteriorating item with time- varying demand. Com. Oper. Res. 1999;26(3):237–254. doi: 10.1016/S0305-0548(98)00043-4. [DOI] [Google Scholar]
  • 15.Zhau YW, Lau HS, Yang SL. A new variable production scheduling strategy for deteriorating item with time varying demand and partial lost sale. Com. Oper. Res. 2003;30(21):1753–1776. doi: 10.1016/S0305-0548(02)00104-1. [DOI] [Google Scholar]
  • 16.Shah NH, Chaudhari U, Jani MY. An inventory model with an expiration date of items and deterioration under two-level trade credit and preservation technology investment for time and price-sensitive demand: DCF approach. Int. J. Log. Sys. Manag. 2017;27(4):420–437. [Google Scholar]
  • 17.Tripathi RP, Pandey HS. Optimal ordering policies for non- instantaneous Weibull deteriorating items with price linked demand under trade credits. Int. J. Sup. Cha. Inv. Mana. 2020;3(2):77–92. [Google Scholar]
  • 18.Geetha KV, Uttayakumar R. Economic design for an inventory policy for non- instantaneous deteriorating item under permissible delay in payments. J. App. Comp. Math. 2020;233(10):2492–2505. doi: 10.1016/j.cam.2009.10.031. [DOI] [Google Scholar]
  • 19.Jaggi CK, Tiwari S, Goel SK. Credit financing in economic ordering policies for non- instantaneous deteriorating item with price dependent demand and two storage facilities. Ann. Oper. Res. 2017;248(1–2):253–280. doi: 10.1007/s10479-016-2179-3. [DOI] [Google Scholar]
  • 20.Mishra P, Talati I. Quantity discount for integrated supply chain model with back order and controllable deterioration rate. Yugo. J. Oper. Res. 2018;28(5):355–369. doi: 10.2298/YJOR171014012M. [DOI] [Google Scholar]
  • 21.Jani, MY., Shah, NH., and Chaudhari, UB.,: Inventory Control Policies for Time-Dependent Deteriorating Item with Variable Demand and Two Level Order Linked Trade Credit. In: Shah, NH., and Mittal, M., (eds.) Optimization and inventory management, (pp. 55-67). Springer, Singapore (2020)
  • 22.Chaudhury KD, Karmakar B, Das M, Datta TK. An inventory model for deteriorating items with stock- dependent demand, time varying holding cost and shortages. Opsearch. 2015;52(1):55–74. doi: 10.1007/s12597-013-0166-x. [DOI] [Google Scholar]
  • 23.Duan Y, Li G, Tien JM, Huo J. Inventory models for perishable items with inventory level dependent demand rate. Appl. Math. Model. 2017;36:5015–5028. doi: 10.1016/j.apm.2011.12.039. [DOI] [Google Scholar]
  • 24.Pervin M, Roy SK, Weber GW. A two – echelon inventory model with stock- dependent demand and variable holding cost for deteriorating item. Numer. Alg. Con. Opt. 2017;7(1):21–50. [Google Scholar]
  • 25.Teng JT, Chang CT. Economic production quantity models for deteriorating items with price and stock-dependent demand. Comp. Oper. Res. 2005;32:297–308. doi: 10.1016/S0305-0548(03)00237-5. [DOI] [Google Scholar]
  • 26.Dye CY. The effect of preservation technology investment on a non- instantaneous deteriorating inventory model. Omega. 2013;41:872–880. doi: 10.1016/j.omega.2012.11.002. [DOI] [Google Scholar]
  • 27.Ghiani Y, Williams T. A two- level production inventory model for deteriorating items with multiple buyers. Int. J. Prod. Res. 2015;159:233–240. [Google Scholar]
  • 28.Shah NH, Jani MY, Chaudhari U. Optimal replenishment time for a retailer under partial upstream prepayment and partial downstream overdue payment for quadratic demand. Math. Comp. Mod. Dyna. Sys. 2018;24(1):1–11. doi: 10.1080/13873954.2017.1324882. [DOI] [Google Scholar]
  • 29.Buzacott JA. Economic order quantities with inflation. Oper. Res. Quar. 1975;26:553–558. doi: 10.1057/jors.1975.113. [DOI] [Google Scholar]
  • 30.Yang HL, Teng JT, Chern MG. Deterministic inventory lot- size models under inflation with shortages and deterioration for fluctuating demand. Nov. Res. Log. 2001;48:144–158. doi: 10.1002/1520-6750(200103)48:2&#x0003c;144::AID-NAV3&#x0003e;3.0.CO;2-8. [DOI] [Google Scholar]
  • 31.Sarkar B, Moon I. An EPQ model with inflation in an imperfect production system. App. Math. Comp. 2011;217:6159–6167. doi: 10.1016/j.amc.2010.12.098. [DOI] [Google Scholar]
  • 32.Chaudhari UB, Shah NH, Jani MY. Inventory modelling of deteriorating item and preservation technology with advance payment scheme under quadratic demand. Opt. Inv. Mana. 2020;3(2):69–79. [Google Scholar]
  • 33.Sarkar BR, Jamal AMM, Wang J. Supply chain model for perishable products under inflation and permissible delay in payments. Comp. Oper. Res. 2000;27:59–75. doi: 10.1016/S0305-0548(99)00008-8. [DOI] [Google Scholar]
  • 34.Yang HL. Two warehouse inventory models for deteriorating items with shortages under inflation. Eur. J. Oper. Res. 2004;157:344–356. doi: 10.1016/S0377-2217(03)00221-2. [DOI] [Google Scholar]
  • 35.Dey JK, Mondal SK, Maity M. Two storage inventory problem with dynamic demand and interval valued lead time over finite time horizon under inflation and time value of money. Euro. J. Oper. Res. 2008;185:170–194. doi: 10.1016/j.ejor.2006.12.037. [DOI] [Google Scholar]
  • 36.Tripathi RP, Chaudhary SK. Inflationary induced EOQ model for Weibull distribution deterioration and trade credits. Int. J. App. Comp. Math. 2017;3(4):3341–3353. doi: 10.1007/s40819-016-0298-9. [DOI] [Google Scholar]
  • 37.Tripathi RP. Innovation of Economic Order quantity (EOQ) model for deteriorating items with time- linked quadratic demand under non- decreasing shortages. Int. J. App. Comp. Math. 2019;5(5):1–13. [Google Scholar]
  • 38.Pal M, Chandra S. A periodic review inventory model with stock- dependent demand, permissible delay in payments and price discount in backorders. Yugo. J. Oper. Res. 2014;24(1):99–110. doi: 10.2298/YJOR120512017P. [DOI] [Google Scholar]
  • 39.Chern SC, Cardenss- Barron LE, Teng JT. Retailer’s economic order quantity when the supplier offers conditionally permissible delay in payments linked to order quantity. Int. J. Pro. Eco. 2014;155:284–291. doi: 10.1016/j.ijpe.2013.05.032. [DOI] [Google Scholar]
  • 40.Jiangtao M, Guimei C, Ting F, Hong M. Optimal ordering policies for perishable multi- item under stock- dependent demand and two level trade credits. App. Math. Mod. 2014;38(9–10):2422–2532. [Google Scholar]
  • 41.Chen SC, Teng T. Retailer’s optimal ordering policy for deteriorating items with maximum lifetime under supplier’s trade credit financing. App. Math. Mod. 2014;38:4049–4061. doi: 10.1016/j.apm.2013.11.056. [DOI] [Google Scholar]

Articles from International Journal of Applied and Computational Mathematics are provided here courtesy of Nature Publishing Group

RESOURCES