1 |
Delay in honoring payment progressively |
0.846 |
1 |
Very high |
2 |
Delay in the provision or delivery of project site |
0.742 |
4 |
High |
3 |
Slow decision-making process |
0.658 |
9 |
High |
4 |
Errors in design and specifications |
0.696 |
7 |
High |
5 |
Lateness in the revision and approval of design documents |
0.729 |
5 |
High |
6 |
Poor communication and coordination with contracting parties |
0.767 |
3 |
High |
7 |
Difficulties in accessing credit facilities (E.g. Loan) |
0.683 |
8 |
High |
8 |
Change orders during construction by owner |
0.792 |
2 |
High |
9 |
Conflicts between project joint-owners |
0.708 |
6 |
High |
10 |
Indefinite suspension of work by owner |
0.696 |
7 |
High |
11 |
Lack of complete documentation before commencement of project |
0.642 |
10 |
High |
12 |
Delay in the approval of sample materials |
0.625 |
11 |
High |