A new method of bid evaluation for renovation projects: Based on unascertained measure theory and entropy weight

Wenlong Li 1,*, Qin Li 2, Yijun Liu 1,*, Sunmeng Wang 3, Xingwang Pei 1,4
Editor: Ahmed Mancy Mosa5
PMCID: PMC9302765  PMID: 35862483

Abstract

To determine the winning bidder of renovation projects scientifically and reasonably, this paper constructs a bid evaluation model for renovation projects based on unascertained measure theory and the entropy weight method. According to the classification criteria of each index, a single-index unascertained measure function is constructed, and the unascertained measure of each index is calculated. The index weight is determined by the entropy weight method, the bid evaluation grade is determined by credible degree recognition criteria, superiority ranking is carried out, and the optimal result is obtained. Finally, an actual case study is used to verify the validity and practicability of the model. This case study shows that the model is an organic combination of the entropy weight method and unascertained measure theory and can provide a new idea for bid evaluation of renovation projects.

1. Introduction

1.1. Bid evaluation of engineering projects

Bidding is a transaction method for assigning or undertaking engineering tasks that is widely recognized and adopted at home and abroad. In the procurement of goods, engineering and services, the tenderer attracts many bidders to compete equally according to the same conditions through preannounced requirements and then organizes experts in technical, economic and legal aspects in accordance with the prescribed procedures to conduct a comprehensive evaluation of many bidders and ultimately select the winning bidders for the project [13]. Bidding plays a decisive role in ensuring project quality and improving investment benefits. Bid evaluation is the most critical link in engineering project bidding work. Whether a bid evaluation method is reasonable will directly affect the bid evaluation result and is of great significance to the success or failure of the whole project [4, 5].

At present, three main bid evaluation methods are adopted in China: the lowest price bid evaluation method, the reasonable low price bid evaluation method and the comprehensive bid evaluation method. The essence of the lowest price bid evaluation method is to evaluate the bidding prices in the order from low to high, and its risk mainly comes from low-price bidding [6]. The essence of the reasonable low price bid evaluation method is to calculate a reasonable benchmark price based on all bid quotations and then calculate the corresponding price score for each bidder’s quotation on the basis of the benchmark price. This method has the widest range of applications, and its risks are mainly from together-conspired bidding and contacting bidding [7, 8]. The essence of the comprehensive bid evaluation method is to comprehensively score bids according to the bidding price, financial ability, technical ability, management level and performance reputation of each bidder and then rank the bids according to the scores from high to low. The comprehensive bid evaluation method is widely used in large-scale projects. It can comprehensively consider more factors affecting the winning bid, so its risks mainly come from the difficulty of quantifying the bid evaluation criteria of each index, the lack of a scientific basis for determining the weight of each index, the subjective factors of the experts, etc. [9].

Based on these attributes, many experts and scholars have performed many studies on issues in the field of bidding at home and abroad and have also achieved research results. First, scholars have performed many studies from the perspective of the bidding system and proposed countermeasures, such as increasing the number of bidding methods and constructing a perfect bidding management information system, which had a positive impact on the improvement of the bidding system [1012]. Second, scholars have carried out relevant research from the perspective of the bidding market environment, such as studies on improving relevant regulations, establishing a unified bidding platform and establishing a social credit system. Third, scholars have conducted research from the perspective of bid evaluation methods [13, 14]. At present, the main methods used for bid evaluation are as follows: analytic hierarchy process (AHP) [15], game theory [16, 17], gray relational evaluation method [18], artificial neural networks [19], triangular fuzzy number method [20], fuzzy comprehensive evaluation method [21, 22], data envelopment analysis (DEA) [23], TOPSIS method [24], compromise ranking method [25], evidence theory [26], fuzzy group decision-making [27], and least squares method [28]. After sorting out the above research, there are still some shortcomings. It is found that the current research is mainly aimed at the bid evaluation of general engineering projects, and there are still a lot of blanks in the research on the bid evaluation of renovation projects.

1.2. Bid evaluation of renovation projects

In recent years, with the acceleration of the urban renewal process, renovation projects have attracted more and more attention from the society and the public [29]. Due to the existence of a large number of existing buildings, in order to better save resources, inherit historical culture and protect the ecological environment, the construction methods of large-scale demolition and large-scale construction have been gradually eliminated, and the number and scale of renovation projects are increasing [30].

Compared with general new construction projects, renovation projects are more complicated, as they include more influencing factors and greater uncertainties [31]. In the bid evaluation process of renovation projects, the following difficulties are faced. First, many indexes are involved in bid evaluation. Due to the different natures of renovation projects and different bidding requirements, there will be a large amount of uncertain information in these bid evaluation indexes. Second, the selection of bid evaluation experts is uncertain, and experts’ knowledge, experience and cognition are quite different, so their views on the same issue will also be uncertain. Therefore, the focus and difficulty of bid evaluation for renovation projects lies in seeking scientific and reasonable mathematical methods and models with which to analyze and deal with various types of uncertain information.

1.3. Uncertain information processing

Unascertained information and its mathematical processing theory were first put forward by Wang Guangyuan in 1990 as a new theory of uncertain information [32]. Unlike fuzzy information, random information and gray information, unascertained information indicates that the evidence that people have mastered is not enough to grasp the real quantity relationship or the real state of things, which causes subjective and cognitive uncertainty in the minds of decision makers or evaluators. It can be said that all systems containing behavioral factors are unascertained. To determine how to quantitatively describe the unascertained state or the unascertained size of something, Liu Kaidi et al. [33] established the unascertained mathematical theory and proposed an evaluation model based on unascertained measure theory to describe a thing in an unascertained state or with some unascertained nature using a real number between [0, 1]. Afterwards, unascertained measure theory has been rapidly developed and widely applied in many fields, such as mining risk assessment [34, 35], geotechnical risk evaluation [36, 37], geological risk assessment [38], ecological risk assessment [39], and chemical safety evaluation [40], scheme decision-making [41, 42] and it has achieved good results.

Based on the above results, unascertained measure theory can effectively and quantitatively analyze various uncertain factors. On one hand, it can avoid the incompleteness of bid evaluation indexes due to the uncertainty of the influencing factors. On the other hand, it can avoid the shortcomings of the subjectivity of bid evaluation results caused by expert scoring. Based on the various uncertainties in bid evaluation and the characteristics of the unascertained measurement theory, this paper proposes a new method of bid evaluation for renovation projects, applying the unascertained measurement theory to the bid evaluation of renovation projects and hoping to provide new ideas for bid evaluation of renovation projects in the future.

2. Model development

2.1. Unascertained measure theory

2.1.1. Definition of unascertained measure

Suppose that the bidder set X = {X1,X2,⋯,Xn} and the bid evaluation index set I = {I1,I2,⋯,Im}. If xij denotes the measured value of the i-th bidder Xi with respect to the j-th bid evaluation index Ij, then Xi can be expressed as an m-dimensional vector {xi1,xi2,⋯,xim}. Suppose that the bid evaluation grade space G = {G1,G2,⋯,Gp}, where Gk (k = 1,2,⋯,p) is the k-th bid evaluation grade, and suppose that the k-th grade is higher than the k+1-th grade in the bid evaluation process, that is, Gk>Gk+1. If G1>G2>⋯>Gp or G1<G2<⋯<Gp is satisfied, {G1,G2,⋯,Gp} is called an ordered segmentation class of the bid evaluation grade space G [43].

If μijk = μ(xijGk) denotes the degree to which the measured value xij belongs to the k-th bid evaluation grade Gk,

0μ(xijGk)1(i=1,2,,n;j=1,2,,m;k=1,2,,p) (1)
μ(xijG)=1(i=1,2,,n;j=1,2,,m) (2)
μ|xijl=1kGl|=l=1kμ(xijGl)(k=1,2,,p) (3)

Eq (1) is called nonnegative boundedness, Eq (2) is called normalization, and Eq (3) is called additivity. If μ satisfies Eqs (1)–(3), then μ is called the unascertained measure.

2.1.2. Single-index unascertained measure

For every bidder Xi(i = 1,2,⋯,n), the matrix of (μijk)m×p is called the single-index unascertained measure matrix of Xi, as shown in Eq (4).

(μijk)m×p=[μi11μi12μi1pμi21μi22μi2pμim1μim2μimp] (4)

To obtain the unascertained measure, it is necessary to establish a single-index unascertained measure function. At present, the construction methods used for a single-index unascertained measure function mainly include the linear type, exponential type, parabolic type and sinusoidal type. Regardless of the type of simulation function used, it must satisfy the limiting conditions of Eqs (1)–(3). For simplicity, this paper adopts a linear unascertained measure function, and the corresponding expression is as follows:

μij1={0xija2a2xija2a1a2<xija11xij>a2 (5)
μijk={0xijak+1orxij>ak1xijak+1ak+1ak1ak+1<xijakak1xijak+1ak1ak<xijak1 (6)
μijp={1xijapaP1xijaP1apap<xijap10xij>ap1 (7)

where a1,a2,,ak1,ak,ak+1,,ap1,ap generally takes the average of the value range of each bid evaluation grade.

2.1.3. Multi-index comprehensive unascertained measure

Given that μik = μ(XiGk) denotes the degree to which bidder Xi belongs to the k-th bid evaluation grade Gk, as shown in Eq (8), 0≤μik≤1 and k=1pμik=1 are satisfied. Then, the vector {μi1,μi2,⋯,μip} is called the multi-index comprehensive unascertained measure vector of Xi.

μik=j=1mwj·μijk(i=1,2,,n;k=1,2,,p) (8)

2.1.4. Credible degree recognition

To obtain the final bid evaluation result, credible degree recognition criteria are introduced. Suppose that λ (λ≥0.5, usually taking λ = 0.6 or 0.7) is the credible degree if G1>G2>⋯>Gp is satisfied and p0 is satisfied by Eq (9). Then, bidder Xi belongs to bid evaluation grade Gp0.

p0=min|p:k=1pμik>λ,i=1,2,,n| (9)

2.1.5. Superiority sorting

In some cases, we need to select a single winning bidder, but many bidders have the same bid evaluation grade. Therefore, it is necessary to rank all kinds of bid evaluation results and determine the winning bidder.

If G1>G2>⋯>Gp is satisfied, let the value of Gk be equal to Zk and Zk>Zk+1. The unascertained importance can be obtained from Eq (10):

QXi=k=1pZkμik (10)

where QXi is the unascertained importance of bidder Xi. Q={QX1,QX2,,QXn} is the unascertained importance vector, which is sorted according to the size of QXi. The larger is the unascertained importance, the better is the bidder.

2.2. Entropy weight method

The determination of the index weight is a very important link, which will seriously affect the subsequent calculation results. Of course, there are many methods for determining the index weight, each method has its own advantages and disadvantages, and has been applied in different fields [44, 45]. In this paper, the entropy weight method is used to determine the weight of each index [46, 47]. This method can make full use of the values of the single-index unascertained measure matrix, avoid the influence of many subjective factors on the results, overcome the subjectivity and limitations of traditional methods for determining the weight, and make the bid evaluation result more scientific and reasonable.

Suppose that wj denotes the relative degree of importance of an index compared with other indexes. If wj satisfies 0≤wj≤1 and j=1mwj=1, then wj is called the index weight of Ij, and w = (w1,w2,⋯,wn) is called the vector of the index weights. The index weight can be determined by the following expressions. According to the matrix (μijk)m×p, the index weight wj can be obtained from Eqs (11) and (12):

Hj=tk=1pqijklnqijk (11)
wj=djj=1mdj=1Hjmj=1mHj (12)

where Hj>0; qijk=μijk/k=1pμijk; t is a coefficient, with t = 1/ln p; and when μijk = 0, then μijk ln μijk = 0 (i = 1,2,⋯,n).

2.3. Implementation steps

Based on unascertained measure theory and entropy weight method, this paper constructs a bid evaluation model for renovation projects. The specific steps are shown in Fig 1.

Fig 1. Specific steps of bid evaluation model for renovation projects.

Fig 1

  • Step 1: Determine the bid evaluation object and potential bidders, and collect the bidding documents and related data.

  • Step 2: According to the characteristics of the bidder, construct a bid evaluation index system, and determine the grading standard for each index.

  • Step 3: Determine the score of each bid evaluation index for each bidder.

  • Step 4: According to the above definitions of the unascertained measure function and the index grading standard, construct the single-index unascertained measure function.

  • Step 5: Determine the single-index unascertained measure matrix of each bidder.

  • Step 6: Determine the index weight by the entropy weight method.

  • Step 7: Determine the multi-index comprehensive unascertained measure matrix.

  • Step 8: According to the credible degree recognition criteria, determine the bid evaluation grade and superiority sorting of each bidder, and finalize the winning bidder.

3. Model application

The above derivation indicates that the model established in this paper can deal with various uncertainties. Therefore, this paper takes the bid evaluation of a renovation project architectural design as an example for an empirical analysis to verify the feasibility and superiority of the model.

The project is located in Xi’an city, China. It was originally a student dormitory building, and it is planned to be transformed into hotel-style apartments. To select the winning bidder, bidding work is carried out. Five bidders with different strengths apply to bid, one of which fails the prequalification, while the other four pass the prequalification. Based on this, this paper uses the above-mentioned model to conduct an empirical analysis, invites seven experts to evaluate the four bidders and finally determines the winning bidder.

(1) Construct a bid evaluation index system

According to the relevant research on bid evaluation in the literature review, referring to the enterprise situation, technical factor and economic factor that are mainly considered in the bid evaluation process of general engineering projects, considering the particularity and complexity of the renovation projects, and combining the bidding requirements and characteristics of each specific renovation project, this paper constructs the bid evaluation index system for renovation project architectural design, as shown in Fig 2. The final bid evaluation index system mainly includes four aspects: enterprise situation, technical factor, economic factor and supporting service.

Fig 2. Bid evaluation index system for renovation project architectural design.

Fig 2

(2) Determine the grading standard for each index

Each index is divided into four grades by the grading standardization method, and the bid evaluation grade space is G = {G1, G2, G3, G4}, i.e., Grade I (excellent), Grade II (good), Grade III (medium), and Grade IV (poor).

For the above bid evaluation indexes, enterprise qualification (I11), enterprise performance (I12), corporate reputation (I13), financial situation (I14), completeness of scheme information (I21), rationality of design scheme (I22), innovation of design scheme (I23), degree of difficulty in implementing the scheme (I24), coordination with surrounding areas (I27), rationality of quotation composition (I32), preferential conditions (I33), on-site work coordination of late-stage projects (I41), and construction cost consultation (I42) are qualitative indexes. Enterprise qualification (I11) is assigned a value of “4, 3, 2, or 1” according to the qualifications, which are “Qualification Class-A, Qualification Class-B, Qualification Class-C, and Qualification Class-D”. Other qualitative indexes are assigned values by a semi-quantitative method, and their grading standards and assignments are shown in Table 2. Similar project experience (I15), utilization of existing resources (I25), utilization of environmental protection materials (I26), tender price (I31), and completion time of construction drawing design (I34) are quantitative indexes. Their values are extracted and obtained from the bidding documents, and their grading standards are shown in Table 1.

Table 2. Specific score values and weight values of the bid evaluation indexes.

Index Bidder 1 Bidder 2 Bidder 3 Bidder 4 Weight
Enterprise qualification (I11) 3 4 3 3 0.085
Enterprise performance (I12) 79.86 80.43 75.57 69.04 0.043
Corporate reputation (I13) 82.71 86.71 74.71 75.29 0.062
Financial situation (I14) 78.57 81.43 76.71 73.86 0.050
Similar project experience (I15) 18 26 15 9 0.049
Completeness of scheme information (I21) 83.71 88.14 67.14 80.29 0.048
Rationality of design scheme (I22) 74.43 82.14 77.14 70.86 0.047
Innovation of design scheme (I23) 86.71 63.71 65.43 35.43 0.044
Degree of difficulty in implementing the scheme (I24) 65.14 83.14 85.86 77.43 0.042
Utilization of existing resources (I25) 0.45 0.54 0.55 0.51 0.043
Utilization of environmental protection materials (I26) 0.49 0.35 0.32 0.28 0.050
Coordination with surrounding areas (I27) 71.14 67.43 69.71 73.86 0.043
Tender price (I31) 36 30 32 28 0.047
Rationality of quotation composition (I32) 76.57 80.86 78.00 74.86 0.045
Preferential conditions (I33) 42.57 76.43 46.57 52.86 0.071
Completion time of construction drawing design (I34) 30 28 30 26 0.085
On-site work coordination of late-stage projects (I41) 60.14 63.43 58.43 45.14 0.081
Construction cost consultation (I42) 54.43 56.57 44.71 25.57 0.065

Table 1. Bid evaluation index grading standards for renovation project architectural design.

Index Grading Standard
Grade I (C1) Grade II (C2) Grade III (C3) Grade IV (C4)
Enterprise qualification (I11) Qualification Class-A (4) Qualification Class-B (3) Qualification Class-C (2) Qualification Class-D (1)
Enterprise performance (I12) Excellent [85,100] Good [70,85) Medium [50,70) Poor [0,50)
Corporate reputation (I13) Excellent [85,100] Good [70,85) Medium [50,70) Poor [0,50)
Financial situation (I14) Excellent [85,100] Good [70,85) Medium [50,70) Poor [0,50)
Similar project experience (I15) Based on the amount of participation in similar projects, with the interval of 0–40 times.
[20,40] [10,20) [3,10) [0,3)
Completeness of scheme information (I21) Complete [85,100] Basically complete [70,85) Slightly incomplete [50,70) Incomplete [0,50)
Rationality of design scheme (I22) Extremely reasonable [85,100] Basically reasonable [70,85) Generally reasonable [50,70) Unreasonable [0,50)
Innovation of design scheme (I23) Obvious innovation [85,100] Medium innovation [70,85) Slight innovation [50,70) No innovation [0,50)
Degree of difficulty in implementing the scheme (I24) Easy [85,100] General [70,85) Slightly difficult [50,70) Very difficult [0,50)
Utilization of existing resources (I25) Based on the utilization ratio, with the interval of 0–100%.
[60%,100%] [40%,60%) [20%,40%) [0,20%)
Utilization of environmental protection materials (I26) Based on the utilization ratio, with the interval of 0–100%.
[60%,100%] [40%,60%) [20%,40%) [0,20%)
Coordination with surrounding areas (I27) Very coordinated [85,100] Coordinated [70,85) Uncoordinated [50,70) Very uncoordinated [0,50)
Tender price (I31) Based on the total bid price, with the interval of 20–50 million RMB.
[20,25) [25,30) [30,35) [35,50]
Rationality of quotation composition (I32) Very reasonable and very complete [85,100] Basically reasonable and basically complete [70,85) Unreasonable or incomplete [50,70) Very unreasonable or very incomplete [0,50)
Preferential conditions (I33) Big discount [85,100] General discount [70,85) Small discount [50,70) No discount [0,50)
Completion time of construction drawing design (I34) Based on the completion time of construction drawing design, with the interval of 20–60 days.
[20,30) [30,40) [40,50) [50,60]
On-site work coordination of late-stage projects (I41) Coordination in the whole process [85,100] Coordination in the key process [70,85) Only for answering questions [50,70) No coordination [0,50)
Construction cost consultation (I42) Provide full-process construction cost consultation [85,100] Provide partial construction cost consultation [70,85) Provide local construction cost consultation [50,70) No construction cost consultation [0,50)

(3) Determine the specific score value of each index for each bidder

The score values of the quantitative indexes are extracted and obtained from the bidding documents. For the qualitative indexes, the score value of I11 is taken directly from “4, 3, 2, or 1” according to the enterprise qualification. The score values of the other qualitative indexes are determined by an expert scoring method. Seven experts are invited to score according to the grading standard shown in Table 1. By eliminating the highest and lowest scores and then equalizing them, the qualitative indexes are transformed into semi-quantitative indexes, and the score values of the qualitative indexes are obtained. The specific score values of each index for the four bidders are shown in Table 2.

(4) Construct the single-index unascertained measure function

To operate simply and easily, this paper adopts a linear-type unascertained measure function. According to the above definition of the single-index unascertained measure function and the grading standard shown in Table 1, the single-index unascertained measure function is constructed as shown in Fig 3.

Fig 3. Single-index unascertained measure function.

Fig 3

(5) Determine the single-index unascertained measure matrix of each bidder

According to the constructed single-index unascertained measure function and the specific score values of each bidder shown in Table 2, the single-index unascertained measure matrix of each bidder can be obtained as μ1, μ2, μ3, and μ4, respectively.

μ1=[01.000000.1570.843000.3480.652000.0710.929000.2000.800000.4140.5860000.8240.17600.6140.3860000.2940.706000.7500.250000.9500.050000.6370.3630000.6500.35000.9470.0530000.5020.4980.5000.5000000.0080.9920000.8410.159] (13)
μ2=[1.0000000.1950.805000.6140.386000.2620.738000.7330.267000.7090.291000.3090.6910000.212000.3760.624000.1330.8670000.2500.750000.4250.575000.5000.50000.7760.2240000.9390.06100.7000.3000000.1960.8040000.9020.098] (14)
μ3=[01.0000000.8900.110000.8410.159000.9550.045001.0000000.4080.592000.9800.020000.3100.69000.5570.443000.1670.8330000.1000.900000.5550.445000.1000.90000.0330.96700000.6160.3840.5000.50000000.9550.045000.5630.437] (15)
μ4=[01.0000000.5170.483000.8730.127000.7920.208000.2940.70600.1860.8140000.6200.3800000.2980.70200.9960.00400.0330.96700000.9000.10000.7920.208000.9000.100000.8490.1510000.7960.2040.9000.10000000.5760.424000.0160.984] (16)

(6) Determine the index weight

The index weight is calculated by the entropy weight method. The weight values are shown in Table 2.

(7) Determine the multi-index comprehensive unascertained measure matrix

According to the single-index unascertained measure matrix and the weight of each index, the multi-index comprehensive measure matrix of the four bidders can be obtained as follows:

μ=[0.1310.5360.2710.0620.3450.4000.2490.0060.0750.5250.3410.0590.0870.4900.2740.149] (17)

(8) Determine the bid evaluation grade

According to the credible degree recognition criteria, use the credible degree λ = 0.6. For bidder 1, on one hand, from small to large, the values are 0.131 + 0.536 = 0.667 > 0.6, and on the other hand, from large to small, the values are 0.062 + 0.271 + 0.536 = 0.869 > 0.6. It can be seen that p0 = 2; that is, the bid evaluation result is Grade II. In this paper, the credible degree recognition criteria are used for two calculations, from small to large and from large to small. The bid evaluation result is consistent with the actual situation, the error is within the acceptable range, and the results are reliable. Similarly, the bid evaluation grades of the other three bidders are also Grade II.

(9) Finalize the winning bidder

In this case, the four bidders reached Grade II (good), and the winning bidder can be determined only by superiority sorting. Since G1>G2>G3>G4, let G1 = 4, G2 = 3, G3 = 2, and G4 = 1. The unascertained importance of the four bidders can be calculated according to Eq (10), and the unascertained importance vector is obtained as follows:

Q={QX1,QX2,QX3,QX4}={2.736,3.082,2.615,2.514} (18)

After calculation, the bid evaluation results of the four bidders are shown in Table 3. The sorting of the four bidders is as follows: bidder 2 > bidder 1 > bidder 3 > bidder 4. Therefore, after comprehensive evaluation of the above bidders, bidder 2 is selected as the best bidder, that is, the ultimate winning bidder.

Table 3. The final bid evaluation results.

Bidder number Grade Unascertained importance Superiority sorting
Bidder 1 II 2.736 2
Bidder 2 II 3.082 1
Bidder 3 II 2.615 3
Bidder 4 II 2.514 4

4. Discussions

From Eq (17), we can get the multi-index comprehensive measure matrix of the four bidders. According to the credible degree recognition criteria, the bid evaluation grades of the four bidders are Grade II, it shows that the difference between the four bidders is relatively small. By calculating the unascertained importance, each bidder can be further compared. From Table 3, we can see that the sorting of the four bidders is as follows: bidder 2>bidder 1>bidder 3>bidder 4. It can be seen from the results that the bid evaluation model established in this paper can reasonably determine the winning bidder.

Through the research of this paper, it can be seen that there are a lot of uncertainties in the bid evaluation process of renovation projects. On the one hand, due to the complexity of renovation projects, there are many factors affecting the bid evaluation of renovation projects, so there will be a lot of uncertain information in the bid evaluation index system of renovation projects. On the other hand, the selection of experts is random and uncertain, the knowledge, experience and cognition of experts are very different, and they also have different views on the same issue, so there will be many uncertainties in the process of scoring indicators by experts. However, the unascertained measure theory is just able to deal with the uncertainty, so the new method proposed in this paper can be used for the bid evaluation of renovation projects.

In order to make the method more widely used in the bid evaluation for renovation projects, it is necessary to further research and optimize the setting of the index and the determination of the index value. In addition, with the rapid development of intelligence today, the use of computer-aided methods for model calculation and bid evaluation is the next research direction.

5. Conclusions

In this paper, by sorting out the problems that exist in current renovation projects bid evaluation, the entropy weight method and unascertained measure theory were used to conduct comprehensive bid evaluation for renovation projects, and this approach can deal with a large amount of uncertain information involved in the bid evaluation process. First, unascertained measure theory was applied to the bid evaluation of renovation projects, and a bid evaluation model for renovation projects based on unascertained measure theory was constructed. Second, the weight of each index was determined by the entropy weight method, and the single-index unascertained measure matrix was fully utilized, which weakened the influence of subjective factors on the bid evaluation results and made the determination of the index weight more reasonable. Finally, an actual case study was used to conduct an empirical analysis, which showed that the bid evaluation model constructed in this paper has certain feasibility and operability.

Bid evaluation is the most critical link in renovation projects bidding work. The bid evaluation model established in this paper can be better used in bidding work to solve various uncertainties. Compared with general bid evaluation methods, this model is more scientific and can provide a new method and idea for renovation projects bid evaluation.

Data Availability

All relevant data are within the paper.

Funding Statement

This research was supported by the Project of Beijing Social Science Foundation (Grant No. 18YTC020), the Project of Beijing Advanced Innovation Center for Future Urban Design of BUCEA (Grant No. udc2018010921), the Project of Beijing Municipal Educational Science “13th Five-Year Plan” (Grant No. CDDB19167), the Project of China Association of Construction Education (Grant No. 2019061), the Special Fund Support for Basic Scientific Research Business Expenses of Municipal Universities of BUCEA (X20055). The funders had no role in study design, data collection and analysis, decision to publish, or preparation of the manuscript.

References

  • 1.Fayek A. Competitive bidding strategy model and software system for bid preparation. Journal of Construction Engineering and Management 1998, 124(1), 1–10. doi: 10.1061/(ASCE)0733-9364(1998)124:1(1). [DOI] [Google Scholar]
  • 2.Engelbrechtwiggans R.; Milgrom P.; Weber R. Competitive bidding and proprietary information. Journal of Mathematical Economics 2006, 11(2), 161–169. doi: 10.1016/0304-4068(83)90034-4. [DOI] [Google Scholar]
  • 3.Guan X.; Gu X. Tendering and bidding of Engineering Projects; China Architecture & Building Press: Beijing, China, 2018. [Google Scholar]
  • 4.Lai K.; Liu S.; Wang S. A method used for evaluating bids in the chinese construction industry. International Journal of Project Management 2004, 22(3), 193–201. doi: [DOI] [Google Scholar]
  • 5.Carlos A.; Emerson C.; Jean-Marie D.; Jean-Claude V. Facilitating bid evaluation in public call for tenders: a socio-technical approach. Omega 2002, 30(3), 227–242. doi: [DOI] [Google Scholar]
  • 6.Wei D.; Zheng K. Research on the bid of evaluating method of the lowest price based on the game theory. IEEE International Conference on Software Engineering & Service Science 2012, 6269497. doi: 10.1109/ICSESS.2012.6269497 [DOI] [Google Scholar]
  • 7.Lin C.; Wang W.; Yang J. Evaluating bid item prices to support contractor selection—a case study. Journal of the Chinese Institute of Engineers 2007, 30(4), 765–771. doi: 10.1080/02533839.2007.9671303 [DOI] [Google Scholar]
  • 8.Chen J. Analysis of evaluating bid price of reasonable lowest price in construction project bidding. Advanced Materials Research 2013, 709, 775–779. doi: 10.4028/www.scientific.net/AMR.709.775 [DOI] [Google Scholar]
  • 9.Li H.; Liu X.; Tang S. Green construction bid evaluation system research based on comprehensive evaluation method. IEEE International Conference on Management & Service Science 2011, 5998171. doi: 10.1109/ICMSS.2011.5998171 [DOI] [Google Scholar]
  • 10.Guo P. Comparative study on bidding system of domestic and abroad; Northeast Normal University: Changchun, China, 2014. [Google Scholar]
  • 11.Wei W. Research on the regulation of construction tendering and bidding in China; Central China Noamal University: Wuhan, China, 2018. [Google Scholar]
  • 12.Xi Y. Construction of bidding management information system. China Tendering Weekly 2018, 17, 22–24. [Google Scholar]
  • 13.Hu J. Study on the surround-bidding behaviors of the construction project bidding and its control measure. Xi’an University of Architecture and Technology: Xi’an, China, 2017. [Google Scholar]
  • 14.Xie W. Analysis of the construction of the construction project electronic bidding and tendering transaction management platform. Construction & Design for Engineering 2019, 4, 263–264. doi: 10.13616/j.cnki.gcjsysj.2019.02.324 [DOI] [Google Scholar]
  • 15.Hruška R.; Průša P.; Babić D. The use of ahp method for selection of supplier. Transport 2014, 29(2), 195–203. doi: 10.3846/16484142.2014.930928 [DOI] [Google Scholar]
  • 16.Ho P. Bid compensation decision model for projects with costly bid preparation. Journal of Construction Engineering and Management 2005, 131(2), 151–159. doi: 10.1061/(asce)0733-9364(2005)131:2(151) [DOI] [Google Scholar]
  • 17.Xu N.; Xu Q.; Li Q. Construction project bidding research based on game theory and target cost pre-control management. Proceedings of the 20th International Symposium on Advancement of Construction Management and Real Estate. Springer; Singapore: 2017, 978–981. doi: 10.1007/978-981-10-0855-9_77 [DOI] [Google Scholar]
  • 18.Yan H. The construction project bid evaluation based on gray relational model. Procedia Engineering 2011, 15, 4553–4557. doi: 10.1016/j.proeng.2011.08.855 [DOI] [Google Scholar]
  • 19.Art Chaovalitwongse W.; Wang W.; Williams T.; Chaovalitwongse P. Data mining framework to optimize the bid selection policy for competitively bid highway construction projects. Journal of Construction Engineering and Management 2012, 138(2), 277–286. doi: 10.1061/(asce)co.1943-7862.0000386 [DOI] [Google Scholar]
  • 20.Zhang M.; Zhang D. Construction project bid evaluation of group decision-making model based on triangular fuzzy number. Applied Mechanics and Materials 2013, 405–408, 3451–3454. doi: 10.4028/www.scientific.net/amm.405-408.3451 [DOI] [Google Scholar]
  • 21.Li W.; Shi H. A method used for evaluating bids based on FCE-AHM. IEEE International Conference on Information Management 2009, 579. doi: 10.1109/ICIII.2009.579 [DOI] [Google Scholar]
  • 22.Geng J.; Ren B. Application of fuzzy comprehensive evaluation in the bid evaluation of municipal engineering construction projects. Applied Mechanics and Materials 2014, 584–586, 2159–2164. doi: 10.4028/www.scientific.net/AMM.584-586.2159 [DOI] [Google Scholar]
  • 23.Yang J.; Wang H.; Wang W.; Ma S. Using data envelopment analysis to support best-value contractor selection. Journal of Civil Engineering and Management 2016, 22(2), 199–209. doi: 10.3846/13923730.2014.897984 [DOI] [Google Scholar]
  • 24.Zhao C.; Dong X.; Hong Q. Project bid evaluation model based on the perspective of index multiple attribute. Journal of Civil Engineering and Management 2017, 34(04), 143–147. doi: 10.13579/j.cnki.2095-0985.2017.04.024 [DOI] [Google Scholar]
  • 25.Zhao C.; Dong X.; Hong Q. Project bid evaluation model based on z-number theory and VIKOR method. Journal of Civil Engineering and Management 2017, 34(03), 114–118. doi: 10.13579/j.cnki.2095-0985.2017.03.020 [DOI] [Google Scholar]
  • 26.Zhang Y. Decision-making model of engineering project bid evaluation based on D-S evidence theory and TFAHP-TOPSIS. Statistics & Decision 2018, 34(11), 48–51. doi: 10.13546/j.cnki.tjyjc.2018.11.009 [DOI] [Google Scholar]
  • 27.Liu B.; Huo T.; Wang X; Shen G.; Chen Y. The decision model of the intuitionistic fuzzy group bid evaluation for urban infrastructure projects considering social costs. Canadian Journal of Civil Engineering 2013, 40(3), 263–273. doi: 10.1139/cjce-2012-0283 [DOI] [Google Scholar]
  • 28.Liu B.; Huo T.; Liao P.; Yuan J.; Sun J.; Hu X. A special partial least squares (PLS) path decision modeling for bid evaluation of large construction projects. KSCE Journal of Civil Engineering 2017, 21(3), 579–592. doi: 10.1007/s12205-016-0702-3 [DOI] [Google Scholar]
  • 29.Zhang Y.; Zhang G.; Guo P. Regeneration path of abandoned industrial buildings: The moderating role of the goodness of regeneration mode. Journal of Cleaner Production 2021, 297(8): 126668. doi: 10.1016/j.jclepro.2021.126668 [DOI] [Google Scholar]
  • 30.Liu Y.; Li H.; Li W.; Li Q.; Hu X. Value assessment for the restoration of industrial relics based on analytic hierarchy process: a case study of Shaanxi Steel Factory in Xi’an, China. Environmental Science and Pollution Research 2021, 1–20. doi: 10.1007/s11356-021-14897-0 [DOI] [PubMed] [Google Scholar]
  • 31.Li W.; L,i Q.; Liu Y.; Li H.; Pei X. Effect evaluation for the regeneration of old industrial buildings based on multilevel extension method. Journal of Architectural Engineering 2020, 26(3): doi: 10.1061/(ASCE)AE.1943-5568.0000424 [DOI] [Google Scholar]
  • 32.Wang G. Uncertainty Information and its Mathematical Treatment. Journal of Harbin Architecture and Engineering Institute 1990, 23(4), 1–8. [Google Scholar]
  • 33.Liu K.; Pang Y.; Sun G.; Yao L. The Unascertained Measurement Evaluation on a City’s Environmental Quality. Systems Engineering Theory and Practice 1999, 12, 52–58. [Google Scholar]
  • 34.Zeng J.; Huang R.; Guan Y.; Cheng J.; Song G. Research on application of entropy-unascertained measure theory in tailing pond safety standardization. Journal of Safety Science and Technology 2014, 2,160–166. [Google Scholar]
  • 35.Yang F.; Wu C. Risk Assessment on Spontaneous Combustion of Sulfide ore Dump in Stope based on Uncertainty Measurement Theory. Journal of Central South University: Science and Technology 2010, 41(6), 2373–2380. [Google Scholar]
  • 36.Gong F.; Li X.; Dong L.; Liu X. Underground goaf risk evaluation based on uncertainty measurement theory. Chinese Journal of Rock Mechanics & Engineering 2008, 27(2), 323–330. doi: 10.1016/S1872-5791(08)60057-3 [DOI] [Google Scholar]
  • 37.Li S.; Wu J.; Xu Z; Li L. Unascertained measure model of water and mud inrush risk evaluation in karst tunnels and its engineering application. Ksce Journal of Civil Engineering 2017, 21(4), 1170–1182. doi: 10.1007/s12205-016-1569-z [DOI] [Google Scholar]
  • 38.Wu Q.; Zhao D.; Wang Y.; Shen J.; Mu W.; Liu H. Method for assessing coal-floor water-inrush risk based on the variable-weight model and unascertained measure theory. Hydrogeology Journal 2017, 25(10), 1–15. doi: 10.1007/s10040-017-1614-0 [DOI] [Google Scholar]
  • 39.Peng X.; Guo S. Research on ecological risk assessment and prevention mechanism in mining areas based on unascertained measures theory. Forestry Economics 2018, 40(8), 92–97. doi: 10.13843/j.cnki.lyjj.2018.08.017 [DOI] [Google Scholar]
  • 40.Wei D.; Jiang J.; Ni L.; Shen S.; Fu G. Uncertainty measurement theory based evaluation of inherent safety of chemical process. China Safety Science Journal 2018, 28(05), 117–122. doi: 10.16265/j.cnki.issn1003-3033.2018.05.020 [DOI] [Google Scholar]
  • 41.Yang Y.; Deng X.; Feng Y. Optimization of mining method based on uncertainty measurement theory and AHP. Journal of Central South University (Science and Technology) 2014, 45(11), 3936–3942. [Google Scholar]
  • 42.Yuan X.; Wang L.; Liu X.; Peng P. Mining mode optimization based on improved unascertained measurement theory. Gold Science and Technology 2015, 23(05), 72–76. [Google Scholar]
  • 43.Li H.; Qin K.; Li P. Selection of project delivery approach with unascertained model. Kybernetes 2015, 44(2), 238–252. doi: 10.1108/K-01-2014-0012 [DOI] [Google Scholar]
  • 44.Wang Y.; Jin X. Structural risk of diversified project financing of city investment company in China based on the best worst method. Engineering, Construction and Architectural Management 2021, 28(1), 196–215. doi: 10.1108/ECAM-05-2019-0249 [DOI] [Google Scholar]
  • 45.Wang Z.; Zhou Y.; Jin X.; Zhao N.; Sun J. Risk allocation and benefit distribution of PPP projects for construction waste recycling: a case study of China. Engineering, Construction and Architectural Management 2022, ahead-of-print. doi: 10.1108/ECAM-10-2021-0855 [DOI] [Google Scholar]
  • 46.Li Q.; Li W. Availability evaluation for current status of old industrial area in China: From the perspective of sustainable development. Environmental Technology & Innovation 2021, 23(1): 101743. doi: 10.1016/j.eti.2021.101743 [DOI] [Google Scholar]
  • 47.Sahoo M.; Patra K.; Swain J.; Khatua K. Evaluation of water quality with application of bayes’ rule and entropy weight method. European Journal of Environmental and Civil Engineering 2016, 21(6), 1–23. doi: 10.1080/19648189.2016.1150895 [DOI] [Google Scholar]

Associated Data

This section collects any data citations, data availability statements, or supplementary materials included in this article.

Data Availability Statement

All relevant data are within the paper.