An Improved African Vulture Optimization Algorithm for Dual-Resource Constrained Multi-Objective Flexible Job Shop Scheduling Problems

Zhou He 1,*, Biao Tang 2, Fei Luan 2
Editor: Subhas Mukhopadhyay
PMCID: PMC9824686  PMID: 36616686

Abstract

According to the characteristics of flexible job shop scheduling problems, a dual-resource constrained flexible job shop scheduling problem (DRCFJSP) model with machine and worker constraints is constructed such that the makespan and total delay are minimized. An improved African vulture optimization algorithm (IAVOA) is developed to solve the presented problem. A three-segment representation is proposed to code the problem, including the operation sequence, machine allocation, and worker selection. In addition, the African vulture optimization algorithm (AVOA) is improved in three aspects: First, in order to enhance the quality of the initial population, three types of rules are employed in population initialization. Second, a memory bank is constructed to retain the optimal individuals in each iteration to increase the calculation precision. Finally, a neighborhood search operation is designed for individuals with certain conditions such that the makespan and total delay are further optimized. The simulation results indicate that the qualities of the solutions obtained by the developed approach are superior to those of the existing approaches.

Keywords: improved African vulture algorithm, dual-resource constrained flexible job shop scheduling problem, population initialization, memory bank, neighborhood search operation

1. Introduction

With the intensification of economic globalization, the production cycle of products has been reduced, requiring enterprises to establish and use manufacturing systems in an agile manner. In the current production system, scheduling is essential for increasing labor efficiency and productivity, as well as enhancing an organization’s ability to compete. At present, many studies focused on the analysis of the problem of flexible job shop scheduling (FJSP) can be found. For example, Gao et al. [1] have proposed an improved artificial bee colony algorithm for FJSP with fuzzy processing time. Li et al. [2] have developed a hybrid artificial bee colony algorithm based on Tabu search for emergencies in FJSP and a clustered grouping roulette method to better initialize the population. Caldeira et al. [3] have presented an improved Jaya algorithm, using a local search method, an effective initialization mechanism, and an acceptance criterion to improve the quality of the FJSP solution. Zhang et al. [4] have recently shown that a genetic algorithm (GA) based on a variable neighborhood search can be used to address the NP-hard property of FJSP, providing a strong search capability and diversity. To solve the FJSP, Chen et al. [5] have used a self-learning genetic algorithm that automatically adjusts the vital parameters of the GA through reinforcement learning. An improved GA based on hybrid initialized populations, manual cross-over methods, and adaptive weighting mechanisms has been proposed by Zhang et al. [6], in order to optimize multi-objective FJSP. Ding et al. [7] have investigated FJSP, and obtained a high-quality scheduling scheme by improving the encoding–decoding scheme, the inter-particle communication mechanism, and the substitution rules for the candidate operation machines in a particle swarm optimization algorithm. Li et al. [8] have developed a scheduling solution based on the Monte Carlo tree search algorithm for the dynamic flexible job shop scheduling problem, in order to minimize the makespan. Different Petri-net based heuristic scheduling methods were used to obtain optimal or near-optimal schedules for FJSP [9,10,11,12,13]. The FJSP has been solved by Caldeira et al. [14] using a discrete multi-objective Jaya algorithm, taking the makespan, total machine workload, and workload of essential machines as performance metrics. There have been many studies on FJSP that consider machine constraints, and many excellent results have been achieved. However, FJSP in the actual manufacturing process is not only constrained by machines, but also by workers. Therefore, it is evident that the traditional job shop scheduling problem (JSP) of machine constraints and FJSP of machine constraints do not meet the requirements of actual production. As a result, the dual-resource flexible job shop scheduling problem (DRCFJSP) with machine and worker constraints has been proposed. The gap between theoretical and practical scheduling problems can be reduced by considering the DRCFJSP. However, as the DRCFJSP is an extension of JSP and FJSP, it still faces significant challenges, such as inheriting the NP-hard features of JSP and FJSP.

At present, there are few relevant studies on DRCFJSP. Cao et al. [15] have contraposed the NP-hard nature of DRCFJSP and, based on the information processing mechanism of innate immunity in biological science, a novel immune genetic algorithm combining the immune algorithm and GA was proposed. Li et al. [16] have presented a branching population genetic metaheuristic algorithm, in order to minimize the completion time and cost of DRCFJSP. The algorithm is a GA-based scheduling method that accumulates and transmits the evolutionary experience of parental chromosomes by introducing pheromones into the branching population. Zheng et al. [17] have designed a knowledge-guided fruit fly optimization algorithm based on a novel coding method to solve the DRCFJSP including a processing time minimization criterion. Zhang et al. [18] have studied the DRCFJSP, and designed a hybrid discrete particle swarm optimization algorithm. Zhang et al. [19] have used a quantum genetic algorithm (QGA) for the DRCFJSP, in order to improve the efficiency of the QGA solution through quantum coding, niche techniques to initialize the population, adaptive rotation angles, and quantum mutation strategies. Tan et al. [20] have proposed a fatigue-based DRCFJSP to alleviate worker fatigue and improve productivity through the joint scheduling of machines and workers.

With the dawn of Industry 4.0 [21], DRCFJSP has become a hot topic of study. As mentioned above, many algorithms have been employed to address the DRCFJSP, in order to obtain scheduling solutions with better overall performance. The African vulture optimization algorithm (AVOA) [22] is a novel metaheuristic optimization algorithm that simulates the foraging and navigation behavior of vultures. Its effectiveness and superiority have been demonstrated through its application to various engineering design problems. Nevertheless, there have been few investigations on AVOA in scheduling problems, even though it has potential advantages in solving scheduling problems.

To adapt to the complicated and volatile external environment of enterprises, in this paper, we construct a makespan and total delay target model, and improve the AVOA (IAVOA) through various improvement strategies to shorten the production cycle time of products, thus increasing the competitive advantage of enterprises. In addition, we also compare and analyze IAVOA against a number of widely used multi-objective algorithms, in order to evaluate relevant performance metrics.

The remainder of this paper is structured as follows: Section 2 presents the specific details of the problem model. The algorithm adopted to solve the model is detailed in Section 3. The improvement strategy and the solution process of IAVOA are provided in Section 4. The simulation experiment is introduced in Section 5. Finally, Section 6 concludes the work.

2. The Multi-Objective DRCFJSP Model

2.1. Description of the Problem

In the following, we provide a description of the DRCFJSP. Suppose that there are w workers in a workshop using m machines to process n jobs. The set of jobs is denoted as J={J1,J2,,Jn}, the set of machines as M={1,2,,m}, and the set of workers as W={1,2,,w}. A job Ji has ni operations waiting for processing, and there is a constraint on the sequence between operations. Each operation Oi,j requires m candidate machines, and each machine MP has w candidate workers. Therefore, there are cases where the processing time PTi,j,p,k,kW of the (same or different) machines processing operation Oi,j differs. The objective of scheduling is to arrange the processing of n jobs reasonably. Therefore, the three tasks of operation sequence, machine allocation, and worker selection comprise the DRCFJSP.

In this paper, we construct a DRCFJSP model to optimize the makespan and total delay. To describe the DRCFJSP model, relevant parameters are defined in Table 1.

Table 1.

Definitions of Parameters.

Symbol Description
n Quantity of jobs
m Quantity of machines
w Quantity of workers
ni Total number of the job i operations
Oi,j The j th operation of job i
BTi,j,p,k The processing time of the j th operation of worker k using machine p to process job i
TTi,(j1),p,k,i,j,p,k Transfer time of job i for two adjacent operations on the machines or workers
Ci Completion time of job i
di The delivery date of job i
Ti Delay time of job i
wwi Weight coefficient of job i
L A big real number
Hi,(j1),p,i,j,p If two adjacent operations of job i are processed on the different machines,  Hi,(j1),p,i,j,p=1; otherwise,  Hi,(j1),p,i,j,p=0
Hi,(j1),k,i,j,k If two adjacent operations of job i are processed by the different workers, Hi,(j1),p,i,j,p=1; otherwise,
Hi,(j1),p,i,j,p=0
Xi,j,p,k If the operation Oi,j is processed on machine p by wk , Xi,j,p,k=1; otherwise, Xi,j,p,k=0
Yi,j,p,i,j,p If the sequence of different operations for processing different jobs is processed on machine p , Yi,j,p,i,j,p=1; otherwise, Yi,j,p,i,j,p=0
Zi,j,k,i,j,k If the sequence of different operations for processing different jobs is processed by worker k , Zi,j,k,i,j,k=1; otherwise, Zi,j,k,i,j,k=0

To obtain a better scheduling solution for the DRCFJSP, the following assumptions are made: (1) there is no hierarchy of importance for various jobs; (2) there is a precedence constraint between various operations of the same job, but not between operations of different jobs; (3) each worker is only able to operate one machine at a time to complete one operation; (4) each operation can only be processed on one machine; (5) each operation process cannot be interrupted; (6) the processing time for all jobs can be zero; and (7) the transfer time of workers on different machines is the same as that of jobs on different machines.

2.2. Objective Function

  • 1.

    Makespan

f1=min(Max(Ci),i{0,1,2,n}), (1)
  • 2.

    Total delay

The total delay objective function has been proposed by Jun [23]. The formula to calculate the total delay f2 is as follows:

f2=min(i=1nwwi·Ti), (2)
Ti=Max(0,Cidi), (3)

such that

Ci,jCi,(j1)+BTi,j,p,k+max(Hi,(j1),p,i,j,p·TTi,(j1),p,k,i,j,p,k,Hi,(j1),k,i,j,k·TTi,(j1),p,k,i,j,p,k)i{1,2,,n},j{1,2,,ni},(p,p)M,(k,k)W, (4)
Ci,j+(1Yi,j,p,i,j,p)·LCi,j+k=1wBTi,j,p,k·Xi,j,p,k(i,i){1,2,,n},j{1,2,,ni},j{1,2,,ni},(p,p)M,(k,k)W, (5)
Ci,j+(1Zi,j,k,i,j,k)·LCi,j+p=1mBTi,j,p,k·Xi,j,p,k+Hi,j,k,i,j,k·TTi,j,p,k,i,j,p,k(i,i){1,2,,n},j{1,2,,ni},j{1,2,,ni},(p,p)M,kW, (6)
p=1mk=1wXi,j,p,k=1,i{1,2,,n},j{1,2,,ni}, (7)

As shown in Equation (4), there are restrictions on the order in which the job can be processed. Equation (5) indicates that, with each machine running at the same time, only one operation can be processed. Equation (6) implies that there is only one job that each worker can process at the same time. Finally, Equation (7) means that an operation can only be performed once.

3. African Vulture Optimization Algorithm

The African Vulture Optimization Algorithm (AVOA) [22] is a recently proposed metaheuristic algorithm that is divided into an exploration phase and an exploitation phase, mimicking the foraging and navigation behavior of African vultures. The exploitation phase can be divided further into a co-operative phase and a competitive phase. The AVOA determines the phase of the algorithm mainly based on the hunger level F of the vulture. If F<r1, AVOA enters the exploration phase. If F>r2, AVOA moves into the co-operative phase. If the above two conditions are not satisfied, AVOA enters the competition phase. The formula for calculating a vulture’s hunger level F is as follows:

t=h×sinωπ2×tmaxt+cosπ2×timaxt1, (8)
F=2×rand1+1×z×1timaxt+t, (9)

where ti defines the present number of iterations, maxt defines the total number of iterations, z is a number drawn at random from the range [1,1], h is a number chosen at random from the range [2,2], rand1 is a number selected at random from the range [0,1], and ω is a constant value (ω=1).

  • (1)
    Exploration phase: Vultures are superb foragers and have outstanding vision in the wild, so they can spot dying animals. However, vultures may have great difficulty in finding food, and need to check different random regions to find food. In AVOA, random regions are represented by two distinct position update formulas, and the parameter P1 is used to select the areas searched by vultures. The random number rand is used to determine the position update formula to obtain new individuals in the exploration phase. If randP1, the position update formula Equation (10) is used; otherwise, the position update Equation (13) is used:
    Pi+1=RiDi×F, (10)
    Di=X×RiPi, (11)
    X=2×rand1, (12)
    Pi+1=RiF+rand2×ublb×rand3+lb, (13)
    where Pi is the position vector of the vultures to be updated; Pi+1 is the new vulture position vector; Ri indicates either an optimal or sub-optimal vulture; rand1, rand2, and rand3 are random numbers between [0,1]; lb and ub represent the upper and lower bounds of the variables; and X defines how vultures move at random to defend their prey from other vultures.
  • (2)
    Co-operative phase: When the vultures are hungry, they will move collectively in search of food. The food source can be represented by two different position update formulas. The random number rand is used to determine the position update formula for the new individual in this phase. If randP2, Equation (14) is applied. Otherwise, Equation (17) is applied.
    Pi+1=Di×F+rand4dt, (14)
    dt=RiPi, (15)
    S1=Ri×rand5×Pi2π×cosPiS2=Ri×rand6×Pi2π×sinPi, (16)
    Pi+1=RiS1+S2, (17)
    where rand4, rand5, and rand6 are a random numbers between [0,1].
  • (3)
    Competitive phase: Serious disputes over food availability can arise when a large group of vultures gather at a single food source. Food sources can be represented by two different position update formulas. The random number rand is used to determine the position update formula followed by the new individual in the competitive phase. If randP3, Equation (19) is applied; otherwise, Equation (20) is applied.
    A1=BV1tBV1t×PiBV1tPi2×FA2=BV2tBV2×PiBV2Pi2×F, (18)
    Pi+1=A1+A22, (19)
    Pi+1=Ridt×F×LFd, (20)
    LFx=0.01×u×σv1β,σ=Γ1+β×sinπβ2Γ1+β2×β×2β121β, (21)
    where BV1t is the optimal vulture in the current iteration, BV2t is the sub-optimal vulture in the current iteration, dt is the distance between BV1t and BV2t, LF refers to Levy flight, d refers to the dimension of the problem, u and v are both arbitrary numbers between [0,1], and the default value for β is fixed at 1.5.

4. Improved African Vulture Optimization Algorithm (IAVOA)

4.1. Initialization of the Population

According to previous studies, a high-quality initial population is helpful in increasing the accuracy of such an algorithm, as well as balancing its exploration and development capacities. Therefore, we designed three rules to generate initial population individuals, as follows:

  1. The shortest processing time principle: Determine the sequence of operations and the selection of machines in a random manner. For the allocation of workers, select the workers with the shortest processing time;

  2. The machine–worker integration principle: Determine the sequence of operations in a random manner, fix the workers assigned to each machine at random, randomly determine the selection allocation of machines, and determine the selection of workers according to the selection of machines;

  3. The randomization principle: Determine the sequence of operations, the selection of machines, and the distribution of workers in a random manner.

The overall processing time of the jobs can be decreased by using the shortest processing time principle. On the contrast, the machine–worker integration principle can reduce the transfer time caused by worker transfer. These two methods have a greater probability of producing better individuals than random methods; however, to maintain population diversity and prevent the algorithm from converging too early, the proportion of individuals generated by the shortest processing time principle and machine–worker integration principle should be low. Thus, 20% of the individuals are generated by the shortest processing time principle, 10% of the individuals are generated by the machine–worker integration principle, and finally, 70% of the individuals are generated by the randomization principle.

4.2. Solution Representation

The DRCFJSP studied in this paper can be divided into three sub-problems: sequencing of operations, allocation of machines, and selection of workers. Therefore, we designed a three-segment encoding scheme—specifically, including a sequence code for operations OC, an allocation code for machines MC, and a selection code for workers WC. The size of each segment is the sum of the operations included in the scheduling problem. The size of the chromosome is i=1nni, where ni reflects the number of operations in job i. Each gene on a bit in OC corresponds to a job number, and different occurrences of the same job number correspond to different operations of the task. In MC, each gene represents that a qualified machine Mk is selected from the machine set M for processing operation Oij. For WC, each gene represents a worker who uses the machine. The three-segment encoding method is conducive to optimizing the processing time and other information in the decoding process, and reducing the complexity of algorithm calculation.

Figure 1 shows an example of the three-segment coding. This example includes three jobs {J1,J2,J3}, three machines {m1,m2,m3}, and five workers {w1,w2,w3,w4,w5}. The workers {w2,w4} can utilize machine m1, workers {w1,w2,w5} can utilize machine m2, and workers {w1,w3,w4} can utilize machine m3. From left to right, the OC is scanned. The first "3" illustrates the first operation O31 of job J3, the first "1" illustrates the first operation O11 of job J1, and the second "3" illustrates the second operation O32 of job J3. Therefore, the processing sequence of the corresponding operation in Figure 1 is O31O11O12O21O22O32O33O23O24. In MC, the first “2” represents machine m2 processing operation O11, the first “1” represents machine m1 processing operation O12, and the second “1” represents machine m1 processing operation O21. In WC, the number “5” indicates that worker w5 uses machine m2 to process operation O11 (i.e., {w5,m2,O11}), and the number “1” indicates that worker w1 uses machine m3 to process operation O12. Based on the above, the specific processing information of this example can be expressed as follows:

{w2,m2,O31},{w5,m2,O11},{w1,m3,O12},{w2,m1,O21},{w2,m1,O22},{w4,m3,O32},{w2,m1,O33},{w1,m2,O23}{w4,m1,O24}

Figure 1.

Figure 1

Three-segment encoding scheme.

4.3. Individual Position Vector

The initial position vector is determined by the OC. The position vector is composed of random numbers in the range [n,n], with length of i=1nni. Figure 2 shows an example of generating a position vector. In Figure 2, there are three jobs {J1,J2,J3} to be processed, where each job includes two operations. It can be seen in Figure 2 that the OC of individual P1 is 312231. Obtaining the sequence number according to the relation between the sequence number and the job number gives 521634. Obtaining the position vector using the relation between the random number and the sequence number gives 2.80.70.23.01.42.1.

Figure 2.

Figure 2

Individual position vector.

4.4. Fitness

When solving DRCFJSP by IAVOA, each individual has different degrees of fitness. Therefore, it is crucial that we develop a way to assess an individual’s fitness value. In evaluating individual fitness, the single objective optimization problem only requires comparing the value of the objective function. However, for problems regarding multi-objective optimization, due to the mutual constraints between objectives, it is necessary to measure the target value of each individual comprehensively. Common methods for evaluating comprehensive individual performance are SPEA2’s k-nearest neighbors method, NSGA-Ⅱ’s Pareto frontier method, and the weight method, among others. To better assess the fitness of individuals and obtain the optimal global solution, we designed a new formula to calculate the individual fitness value, as follows:

F=l=1srl·fl2, (22)

where s is the dimension of the objective function, l is the index of the objective function, f is the objective function, and rl is a number drawn at random from the range [0,1]. In this paper, to prevent the algorithm from entering local optima and maintain high population diversity, the parameter rl is used to control the search direction of the population.

4.5. Memory Bank

The memory bank is a simple storage unit, which is used to store the better individuals in the population. The memory bank has a full file value NA, which controls the population size. The memory bank judges the fitness of individuals according to certain rules. To improve the overall quality of the next generation of individuals, we designed two rules to select better individuals:

  1. Boundary rule: The boundary value αl of the population is calculated by Equation (23), and individuals smaller than the boundary value are stored in the memory bank. The boundary rule can eliminate individuals with large target values, reduce the number of invalid searches in the solution space, and enhance the algorithm’s computational effectiveness.

  2. Distance rule: The distance between each individual and the optimal individual is calculated, and individuals with a large distance are deleted from the memory bank. The distance rule can control the algorithm’s search direction, focusing it toward the optimal solution.

The specific steps of the memory bank processing are as follows:

  • Step 1:
    Use Equation (23) to calculate the boundary value αl of the population and calculate the Euclidean distance between the individuals and the optimal individual. Individual distances in the population are sorted in ascending order:
    αl=maxflr·maxfl, (23)
    where l defines the dimension of the objective function, and r refers to a number in the interval [0,1] (e.g., r=0.35);
  • Step 2:

    Individuals less than the boundary value αl of any dimension using the boundary rule are stored in the memory bank;

  • Step 3:

    Determine whether the number of individuals in the memory bank has reached NA. If the number of individuals l in the memory bank is higher than NA, individuals with a large distance, according to the distance rule, are deleted; otherwise, the storage of individuals in the memory bank is completed.

4.6. Updating of Individuals

IAOVA uses position vectors to update individuals in the population. First, we use the location update formula of AVOA to update the individual location vector in the memory bank, and then use the individual update mechanism to update the individuals. For this paper, we designed an operation update mechanism, three machine–worker update mechanisms, and a neighborhood search operation. The specific steps by which IAOVA updates individuals are as follows:

  • Step 1:

    Determine the optimal vulture individual, the sub-optimal vulture individual, and the individual Pi;

  • Step 2:

    Update the position vector of Pi using the position update formula of AVOA;

  • Step 3:

    Use the process update mechanism to update the OC of individuals in the memory bank;

  • Step 4:

    Determine whether the neighborhood search condition is reached. If the condition is fulfilled, the neighborhood search operation is executed; otherwise, proceed to Step 5;

  • Step 5:

    Randomly generate a random number rr in the range [0,1];

  • Step 6:

    SUse rr to determine the machine–worker update mechanism. Update MC and WC of individuals in the memory bank.

Individual Updating Mechanism

  • 1.

    Operation update mechanism

The specific steps for updating individual operation sequences are as follows:

  • Step 1:

    θ is determined randomly, where θ is a position element of the position vector of individual Pi;

  • Step 2:

    Carry out ascending ranking of element values higher than θ in the position vector of individual Pi, and record the changed operation numbers and position vector elements;

  • Step 3:

    Set the operation number of the optimal vulture or the sub-optimal vulture to zero, which is the same as the operation number recorded in Step 2, and record the non-zero numbers and position vector elements;

  • Step 4:

    Record the operation number and position vector in Step 2 as the first half of the sub-generation, and record the operation number and position vector in Step 3 as the second half of the sub-generation.

The operation update mechanism of the individual is depicted in Figure 3.

Figure 3.

Figure 3

Operation update mechanism of the individual.

  • 2.

    Machine–worker update mechanism

Based on the relationship between the AVOA solution and the optimal or sub-optimal vulture, and to maintain the diversity of the algorithm, we designed three machine–worker update mechanisms. The specific mechanisms are as follows.

  • (1)

    Machine–worker self-updating mechanism

  • Step 1:

    Generate two location indices l1 and l2 on MC in a random way;

  • Step 2:

    Determine the processing procedures on the location indices l1 and l2, and randomly select machines from the machine set to replace the machines at these locations;

  • Step 3:

    Randomly select workers to replace workers at these locations.

Figure 4 depicts the machine–worker self-updating process of individuals.

Figure 4.

Figure 4

Self-updating process for individual machine–worker.

  • (2)

    Machine–worker cross-updating mechanism

  • Step 1:
    Calculate the exchange digit l using Equation (24):
    l=round(u·i=1nni), (24)
    where round is the rounding function, and u=0.225.
  • Step 2:

    Randomly generate two location indices l1 and l2, where |l1l2|=l;

  • Step 3:

    The position elements between l1 and l2 in vulture Ri are transferred to the offspring Ci in turn, keeping the original location index unchanged;

  • Step 4:

    The values of individual Pi, except for the location elements between the location indices l1 and l2, are kept unchanged and passed to the child Ci in turn.

Figure 5 depicts the individual machine–worker cross-updating process.

Figure 5.

Figure 5

Cross-updating process for individual machine–worker.

  • (3)

    Worker self-updating mechanism

  • Step 1:

    Step 1: Randomly generate two location indices l1 and l2 on WC;

  • Step 2:

    Set the location elements in the location indices l1 and l2 of the individual Pi to be updated to the child Ci;

  • Step 3:

    In individual Ri, except for the location elements between the location indices l1 and l2, the original location indices are kept unchanged and passed to the child Ci in turn.

The new MC is the MC of vulture Ri. Figure 6 depicts the WC updating process.

Figure 6.

Figure 6

Updating process for individual WC.

4.7. Neighborhood Search Operation

The neighborhood search operation enhances the algorithm’s exploration of the solution space, enhances the quality of the solution for a wide variety of individual groups, and improves the ability of the algorithm to skip local optima. The neighborhood search operation is as follows:

  • Step 1:

    Judge whether an individual’s position vector meets the neighborhood search conditions (more than 60% of the elements on the position vector are the same, or all elements on the position vector are boundary values). If the condition is met, Step 2 is performed. Otherwise, the neighborhood search operation is not performed;

  • Step 2:

    Determine the allele exchange number Ng;

  • Step 3:

    Generate the location indices l1 and l2;

  • Step 4:

    In OC, the alleles on the location indices l1 and l2 are exchanged. For the position vector, the elements located at l1 and l2 are generated randomly;

  • Step 5:

    Judge whether the exchange number Ng has been met. If the condition is met, new individuals will be generated. Otherwise, Step 2 is executed.

The specific operation flow of the neighborhood search operation is shown in Figure 7. Suppose that the allele exchange number Ng is 3. Each exchange of alleles does not affect each other. Therefore, there is a certain probability of generating the same location index. For example, in Figure 7, the location index required for the second exchange is the same as that generated the first time.

Figure 7.

Figure 7

Operation flow of the neighborhood search operation.

4.8. Framework of the Developed Algorithm

The AVOA is improved by designing the initial population and memory bank, balancing the ability of the AVOA to explore and develop the solution space. The neighborhood search operation is intended to enhance the ability of the algorithm to skip local optima. Figure 8 shows a flow chart indicating how IAVOA is used to solve the DRCFJSP. The specific steps of the solution process are as follows:

  • Step 1:

    Set up the parameters;

  • Step 2:

    Initialize the population Pt by using the strategy for population initialization;

  • Step 3:

    Calculate individual fitness values in the population. Select the optimal vulture and the sub-optimal vulture, and determine the vulture Ri;

  • Step 4:

    Judge whether the termination condition has been met. If the condition is fulfilled, Step 9 is executed. Otherwise, Step 5 is executed;

  • Step 5:

    Compose the population Pt and memory bank At into a new memory bank At, and calculate the Euclidean distance and boundary value αl between the individuals and the optimal vulture in At;

  • Step 6:

    Use the memory bank pruning strategy to prune At to obtain the memory bank At+1;

  • Step 7:

    Update the position vector of At+1 using the position update formula of AVOA, and update the OC of At+1 using the operation update mechanism;

  • Step 8:

    Judge whether the neighborhood search operation is required. If the condition is fulfilled, the neighborhood search operation is used to update the individuals. Otherwise, the machine–worker update mechanism updates the individual machine code and the worker code. New individuals join the new population Pt+1. Then, Step 3 is executed;

  • Step 9:

    Output the optimal solution.

Figure 8.

Figure 8

Flow chart of the IAVOA process.

5. Experimental Simulation and Analysis

We analyze the performance of IAVOA through an experiment. The environment for the experimental analysis was Windows 10, with 4 GB of RAM and an Intel i7 processor, and the programming environment was MATLAB 2021. The experimental analysis included the following.

  • (1)

    Setting the parameters of IAVOA;

  • (2)

    Assessing the optimal performance of IAVOA;

  • (3)

    Examining the performance of IAVOA, compared to that of commonly used multi-objective optimization algorithms.

5.1. Evaluation Metrics

To assess the performance of IAVOA, three evaluation metrics are used in this paper: Generational Distance (GD) [24], Inverse Generational Distance (IGD) [25], and hypervolume (HV) [26]. GD and IGD were used to evaluate the convergence of IAVOA, while HV was employed to estimate the diversity of IAVOA. The formulas for these evaluation metrics are as follows:

  1. GD

GD=i=1|Ω|Di2Ω,   Ω*Ω, (25)

where Ω is the first Pareto front value (PF) obtained by an algorithm, Ω* is the true PF value, |Ω| is the quantity of elements in the Pareto front obtained from the algorithm’s solution, and Di(Ω,Ω*) denotes the minimum Euclidean distance that separates the solution in Ω* from solution i in Ω. A smaller GD value indicates better convergence of the algorithm.

  • 2.

    IGD

IGD=i=1|Ω*|DiΩ*,ΩΩ*, (26)

where |Ω*| is the quantity of elements in the true PF, and Di(Ω*,Ω) denotes the shortest Euclidean distance that separates the solution in Ω from solution i in Ω*. A smaller value of the IGD indicates better convergence of the algorithm.

  • 3.

    HV

HV=δ(i=1|Ω|Vi), (27)

where δ is the Lebesgue measure, and Vi denotes the hypercube formed between the reference point and the solution i in PF. A larger HV value reflects better diversity of the algorithm.

5.2. Test Case

As the DRCFJSP is a relatively new problem, there were no standard cases for testing the algorithm’s performance. Therefore, we applied 24 test cases, DMK01–DMK15 and DDP10–DDP18, based on FMK01–FMK15 and FDP10–FDP18, respectively [20]. The quantity of jobs, operations, machines, and workers; the processing time BTi,j,p,k of the operation; and the transit time TTi,(j1),p,k,i,j,p,k of the two machines in the test case were the same as in FMK01–FMK15 and FDP10–FDP18. The delivery period of jobs is related to the tightness factor of the delivery period [27]. Equation (28) describes the delivery period for job i. The weights for the jobs were generated using the weight averaging method. Table 2 shows the scale used in the test case.

di=ri+c×j=1niBTi,j,p,k*, (28)

where BTi,j,p,k* indicates the mean processing time for operation j of job i, ri denotes the release time of job i (riU[0,j=1niBTi,j,p,k*/ni]), and c indicates the tightness factor of the delivery period (c=1.2).

Table 2.

Scale of the test case.

Test Case Job Operation Machine Worker
DMK01 10 55 6 4
DMK02 10 58 6 4
DMK03 15 150 8 6
DMK04 15 90 8 5
DMK05 15 160 2 3
DMK06 10 150 15 10
DMK07 20 100 5 4
DMK08 20 225 10 8
DMK09 20 240 10 8
DMK10 20 240 15 10
DMK11 30 179 5 4
DMK12 30 193 10 8
DMK13 30 231 10 8
DMK14 30 277 15 12
DMK15 15 293 8 6
DDP10 15 293 8 6
DDP11 15 293 8 6
DDP12 15 293 8 6
DDP13 20 387 10 8
DDP14 20 387 10 8
DDP15 20 387 10 8
DDP16 20 387 10 8
DDP17 20 387 10 8
DDP18 20 387 10 8

5.3. Setting of Parameters

The performance of IAVOA is significantly impacted by the parameter settings. The key parameters affecting the performance of the IAVOA are r1(i.e., r1[1,1.3]), r2(i.e., r2[0.5,0.8]), P1(i.e., P1[0.4,0.7]), P2(i.e., P2[0.4,0.7]), and P3(i.e., P3[0.3,0.6]), where r1 and r2 determine the phase of the IAVOA (i.e., exploration, co-operative, or competition), and P1, P2, and P3 primarily determine the location update formula employed by IAVOA at each phase. In this paper, the DMK08 was considered a test case, and the Taguchi method [28] for setting up an orthogonal experiment was applied to determine the best parameter combination strategy. Several reasonable levels for the parameters are given in Table 3, and each group of parameters was run 10 times, where the average value for each IGD group was regarded as the response value. Table 4 displays the average response values and the rank of parameters. As shown in Table 4, the parameters with the highest impact rank were r2 and P3. Figure 9 depicts the factor level trend of the parameters. The optimal combination of parameters for IAVOA was found to be r1=1.3, r2=0.5, P1=0.7, P2=0.7, and P3=0.3, through experimental analysis.

Table 3.

Level of parameters.

Parameter Level
1 2 3 4
r1 1 1.1 1.2 1.3
r2 0.5 0.6 0.7 0.8
P1 0.4 0.5 0.6 0.7
P2 0.4 0.5 0.6 0.7
P3 0.3 0.4 0.5 0.6

Table 4.

Response values and rank of parameters.

Level r1 r2 P1 P2 P3
1 0.2015 0.1872 0.1984 0.1956 0.1686
2 0.2033 0.1910 0.1915 0.2084 0.1990
3 0.1919 0.2111 0.2092 0.1905 0.2180
4 0.1807 0.1881 0.1783 0.1830 0.1807
Delta 0.0208 0.0239 0.0309 0.0254 0.0373
Rank 5 4 2 3 1

Figure 9.

Figure 9

Factor level trend of the parameters.

5.4. Performance Analysis of IAVOA

In this subsection, the methods developed in [24,29] are employed as comparison algorithms to assess the performance of IAVOA (i.e., SPEA2 and NSGA-II). Both algorithms have been widely used and their excellent performance in solving engineering problems has been proven. Therefore, they were considered highly reliable for comparison. The differences of the two multi-objective optimization algorithms are as follows: SPEA2 evaluates individual fitness mainly by the k-nearest neighbor method, whereas NSGA-II evaluates individual fitness by the non-dominated sorting technique and crowding distance calculation approach. Table 5 shows the parameter setting values for the different algorithms. Zitzler [24] has identified that SPEA2 produces superior solutions around Pc=0.8 and Pm=0.1. Therefore, the probability of crossing and mutation for SPEA2 in Table 5 was set as 0.8 and 0.15, respectively. To avoid errors arising from the parameters, the NSGA-II probability of crossing and mutation was also set as 0.8 and 0.15. The range of each parameter was shown in parentheses. For each case, we run the tested algorithm 10 times.

Table 5.

Parameter setting values of the different algorithm.

Parameter IAVOA SPEA2 NSGA-Ⅱ
Population size 100 (100~300) 100 (100~300) 100 (100~300)
Iterations 500 (400~700) 500 (400~700) 500 (400~700)
The probability of crossing Pc - 0.8 (0.75~0.85) 0.8 (0.75~0.85)
The probability of mutation Pm - 0.15 (0.5~0.2) 0.15 (0.5~0.15)
Memory bank NA 100 (100~500) - -
Archive - 100 (100~500) -
r1 1.3(1~1.3) - -
r2 0.5(0.5~0.8) - -
P1 0.7(0.4~0.7) - -
P2 0.7(0.4~0.7) - -
P3 0.3(0.3~0.6)

The performance metrics of the three algorithms are displayed in Table 6 where the data in bold indicate the optimal values of the performance metrics for each test case. Multiple test cases are detailed in Table 6, where IAVOA’s GD and IGD values were better than those of SPEA2 and NSGA-II, demonstrating that IAVOA has better convergence. The data in Table 6 indicated that IAVOA also had better HV values than SPEA2 and NSGA-II, except for the cases DMK01, DMK04, and DMK07, which demonstrates that the diversity of IAVOA is generally better than the other two algorithms. Figure 10 shows the box plots for the three evaluation metrics.

Table 6.

Performance metric values of the three algorithms.

Test Case GD IGD HV
IAVOA SPEA2 NSGA-Ⅱ IAVOA SPEA2 NSGA-Ⅱ IAVOA SPEA2 NSGA-Ⅱ
DMK01 0.0168 0.0164 0.0353 0.029 0.0283 0.0611 1.0087 1.0221 0.9701
DMK02 0.0280 0.0564 0.0764 0.0483 0.0976 0.1322 1.0250 0.9612 0.9152
DMK03 0.0943 0.1287 0.1428 0.1334 0.1815 0.2019 0.9861 0.9183 0.8945
DMK04 0.0546 0.0529 0.0477 0.1443 0.1397 0.1258 0.9169 0.9264 0.9513
DMK05 0.0496 0.0703 0.0874 0.0859 0.1218 0.1513 1.0622 1.0187 0.9823
DMK06 0.0901 0.1401 0.1720 0.0901 0.1401 0.172 0.9600 0.8863 0.8365
DMK07 0.0527 0.0483 0.0609 0.1178 0.1079 0.1361 0.9464 0.9656 0.9336
DMK08 0.0911 0.1052 0.1376 0.1289 0.1487 0.1946 0.9689 0.9424 0.8796
DMK09 0.1014 0.1214 0.1235 0.1755 0.2103 0.2139 0.9363 0.8930 0.8901
DMK10 0.0935 0.1369 0.1342 0.1322 0.1936 0.1898 0.9989 0.9143 0.9191
DMK11 0.1065 0.1234 0.1300 0.1506 0.1745 0.1838 1.0003 0.9691 0.9626
DMK12 0.0695 0.1784 0.1120 0.1204 0.1784 0.1939 0.9661 0.8915 0.8663
DMK13 0.1333 0.1867 0.2366 0.1333 0.1867 0.2366 0.9922 0.9195 0.8551
DMK14 0.0600 0.0692 0.0948 0.1586 0.183 0.2507 1.0457 1.0118 0.9167
DMK15 0.0982 0.1558 0.1752 0.1387 0.2188 0.2477 1.0358 0.9197 0.8849
DDP10 0.1420 0.1654 0.2007 0.1942 0.2326 0.2839 0.9642 0.9218 0.8652
DDP11 0.0893 0.1386 0.1502 0.1785 0.2771 0.3003 1.0692 0.9334 0.8996
DDP12 0.0887 0.1256 0.1561 0.1984 0.2809 0.349 0.9352 0.8268 0.7436
DDP13 0.0721 0.1123 0.1265 0.2164 0.2751 0.3098 1.0290 0.8935 0.8470
DDP14 0.1423 0.2449 0.2750 0.2013 0.3464 0.3889 1.0549 0.8540 0.7999
DDP15 0.1182 0.1637 0.2169 0.2046 0.2836 0.3757 1.0887 0.9718 0.8503
DDP16 0.0749 0.0840 0.0977 0.1675 0.1879 0.2184 0.9396 0.9128 0.8722
DDP17 0.0540 0.1584 0.1759 0.0935 0.2744 0.3046 1.0970 0.8454 0.8072
DDP18 0.0930 0.1793 0.1879 0.1611 0.3106 0.3254 1.0563 0.8503 0.8334

Figure 10.

Figure 10

Box plot for the three evaluation metrics: (a) GD; (b) IGD; (c) HV.

Table 7 shows the optimization values for the test cases resolved using IAVOA, SPEA2, and NSGA-II. The data in bold indicate the optimal results for the corresponding cases solved by the algorithms, and the corresponding line chart is shown in Figure 11, which demonstrate that higher quality scheduling solutions were obtained when solving DRCFJSP with IAVOA, compared to the other two algorithms. Figure 11 illustrates the various advantages of IAVOA in solving the large-scale DRCFJSP. Thus, our experiment showed that IAVOA is better suited to the practical FJSP solution than SPEA2 and NSGA-II.

Table 7.

Objective function values for the test cases solved with the three algorithms.

Test Case Optimal Results of Makespan/min Optimal Results of Total Delay/min
IAVOA SPEA2 NSGA-Ⅱ IAVOA SPEA2 NSGA-Ⅱ
DMK01 75 76 83 11.7687 7.4946 7.9494
DMK02 75 82 91 10.0309 12.1499 17.1734
DMK03 349 379 400 97.4101 121.1134 126.3537
DMK04 150 162 155 61.9927 49.9123 42.0513
DMK05 338 379 390 182.5554 170.4126 174.6927
DMK06 183 205 218 6.4038 23.2212 40.4034
DMK07 280 293 306 118.9131 82.1253 93.6101
DMK08 687 726 769 312.6511 321.0397 386.9322
DMK09 643 690 699 291.3925 301.9603 297.0488
DMK10 485 556 550 158.5083 212.4392 211.066
DMK11 1211 1271 1306 735.8705 744.534 725.7022
DMK12 736 828 842 313.419 351.2002 376.6815
DMK13 858 954 1050 407.6391 465.5957 510.1178
DMK14 947 1001 1091 451.6775 466.4827 545.0523
DMK15 836 938 985 323.9902 387.5786 432.1122
DDP10 4759 4974 5350 2236.6866 2308.146 2324.749
DDP11 4346 4860 4973 1962.1604 2236.056 2406.352
DDP12 4523 5059 5453 2152.6979 2505.917 2805.742
DDP13 4800 5362 5594 2280.077 2748.891 2956.206
DDP14 4220 4986 5238 1735.3055 2434.829 2559.569
DDP15 4610 4944 5456 2064.664 2489.012 2860.294
DDP16 4781 4959 5189 2315.1469 2422.619 2603.635
DDP17 4271 5754 6064 1728.576 2991.734 3168.29
DDP18 4402 5453 5657 1978.0443 2839.279 2834.144

Figure 11.

Figure 11

Line chart of the optimization problem values.

To clearly determine the performance of IAVOA, the medium-scale DMK12 was selected for performance analysis. Figure 12 presents the convergence graph for DMK12, which shows that IAVOA provides a better solution when the iterations increase. The superior results obtained by IAVOA illustrate the feasibility and effectiveness of the improved strategy. Figure 13 shows the Gantt chart of DMK12 for IAVOA.

Figure 12.

Figure 12

Convergence graph of DMK12.

Figure 13.

Figure 13

Gantt chart of DMK12.

6. Conclusions

In this paper, we considered the influence of machine and worker constraints on the FJSP, and established the DRCFJSP with makespan and total delay as objective functions. The AVOA, based on the position update formula and position vector, was proposed to solve DRCFJSP. To sustain population diversity and optimize solution quality, the population was initialized in three ways, following the shortest processing time principle, the machine–worker integration principle, and the randomization principle. The memory bank of AVOA was improved to enhance the solution space exploration and exploitation capabilities of the algorithm. A neighborhood search operation was designed to avoid the algorithm falling into local optima, and the Taguchi method was employed to determine the optimal parameters of the algorithm. The test cases were DMK01-DMK10 and DDP10-DDP18, based on FMK01-FMK10 and FDP10-FDP18, respectively. The experimental results demonstrated that the IAVOA can outperform the state-of-the-art SPEA2 and NSGA-II in solving large-scale flexible job shop scheduling problems. In terms of performance metrics, the experiments verified that IAVOA has good convergence and diversity.

For future work, there exist many dynamic problems attached to FJSP, such as job insertion, machine breakdowns, and other emergencies, which deserve further consideration. In this manuscript, the limitation of overtime for workers was not considered. This problem can be solved in future work by increasing the number of workers. Distributed scheduling and reverse scheduling can also be considered as future research directions. In addition, the algorithm needs further improvement, in order to obtain a scheduling solution with better performance.

Acknowledgments

The authors wish to express our gratitude to every reviewer of this paper.

Abbreviations

The following abbreviations are used in this manuscript:

AVOA African vulture optimization algorithm
IAVOA Improved African vulture optimization algorithm
GA Genetic algorithm
FJSP The problem of flexible job shop scheduling
JSP The traditional job shop scheduling problem
DRCFJSP The dual-resource flexible job shop scheduling problem

Author Contributions

Conceptualization, Z.H. and B.T.; methodology, Z.H.; software, B.T.; validation, B.T. and F.L.; formal analysis, Z.H. and B.T.; investigation, Z.H. and B.T.; resources, Z.H.; data curation, not applicable; writing—original draft preparation, B.T.; writing—review and editing, Z.H. and F.L.; visualization, Z.H. and B.T.; supervision, Z.H; project administration, Z.H.; funding acquisition, Z.H. All authors have read and agreed to the published version of the manuscript.

Institutional Review Board Statement

Not applicable.

Informed Consent Statement

Not applicable.

Data Availability Statement

Not applicable.

Conflicts of Interest

The authors declare no conflict of interest.

Funding Statement

The research was funded by National Natural Science Foundation of China: 61803246; China Postdoctoral Science Foundation: 2019M663608; Scientific Research Foundation of Shaanxi University of Science and Technology: 2021BJ-34; Project of Xi’an Science and Technology Program: 22GXFW0016.

Footnotes

Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content.

References

  • 1.Gao K.Z., Suganthan P.N., Pan Q.K., Chua T.J., Chong C.S., Cai T.X. An improved artificial bee colony algorithm for flexible job-shop scheduling problem with fuzzy processing time. Expert Syst. Appl. 2016;65:52–67. doi: 10.1016/j.eswa.2016.07.046. [DOI] [Google Scholar]
  • 2.Li X., Peng Z., Du B., Guo J., Xu W., Zhuang K. Hybrid artificial bee colony algorithm with a rescheduling strategy for solving flexible job shop scheduling problems. Comput. Ind. Eng. 2017;113:10–26. doi: 10.1016/j.cie.2017.09.005. [DOI] [Google Scholar]
  • 3.Caldeira R.H., Gnanavelbabu A. Solving the flexible job shop scheduling problem using an improved Jaya algorithm. Comput. Ind. Eng. 2019;137:106064. doi: 10.1016/j.cie.2019.106064. [DOI] [Google Scholar]
  • 4.Zhang G., Zhang L., Song X., Wang Y., Zhou C. A variable neighborhood search based genetic algorithm for flexible job shop scheduling problem. Clust. Comput. 2019;22:11561–11572. doi: 10.1007/s10586-017-1420-4. [DOI] [Google Scholar]
  • 5.Chen R., Yang B., Li S., Wang S. A self-learning genetic algorithm based on reinforcement learning for flexible job-shop scheduling problem. Comput. Ind. Eng. 2020;149:106778. doi: 10.1016/j.cie.2020.106778. [DOI] [Google Scholar]
  • 6.Zhang G., Hu Y., Sun J., Zhang W. An improved genetic algorithm for the flexible job shop scheduling problem with multiple time constraints. Swarm Evol. Comput. 2020;54:100664. doi: 10.1016/j.swevo.2020.100664. [DOI] [Google Scholar]
  • 7.Ding H., Gu X. Improved particle swarm optimization algorithm based novel encoding and decoding schemes for flexible job shop scheduling problem. Comput. Oper. Res. 2020;121:104951. doi: 10.1016/j.cor.2020.104951. [DOI] [Google Scholar]
  • 8.Li K., Deng Q., Zhang L., Fan Q., Gong G., Ding S. An effective MCTS-based algorithm for minimizing makespan in dynamic flexible job shop scheduling problem. Comput. Ind. Eng. 2021;155:107211. doi: 10.1016/j.cie.2021.107211. [DOI] [Google Scholar]
  • 9.Huang B., Zhou M., Lu X.S., Abusorrah A. Scheduling of resource allocation systems with timed Petri nets: A Survey. ACM Comput. Surv. 2022. to be published . [DOI]
  • 10.He Z., Li Z., Giua A. Optimization of deterministic timed weighted marked graphs. IEEE Trans. Autom. Sci. Eng. 2017;14:1084–1095. doi: 10.1109/TASE.2015.2490538. [DOI] [Google Scholar]
  • 11.Hu L., Liu Z., Hu W., Wang Y., Tan J., Wu F. Petri-net-based dynamic scheduling of flexible manufacturing system via deep reinforcement learning with graph convolutional network. J. Manuf. Syst. 2020;55:1–14. doi: 10.1016/j.jmsy.2020.02.004. [DOI] [Google Scholar]
  • 12.Han L., Xing K., Chen X., Xiong F. A Petri net-based particle swarm optimization approach for scheduling deadlock-prone flexible manufacturing systems. J. Intell. Manuf. 2018;29:1083–1096. doi: 10.1007/s10845-015-1161-2. [DOI] [Google Scholar]
  • 13.Huang B., Zhou M.C. Symbolic scheduling of robotic cellular manufacturing systems with timed Petri nets. IEEE Trans. Control Syst. Technol. 2022;30:1876–1887. doi: 10.1109/TCST.2021.3123963. [DOI] [Google Scholar]
  • 14.Caldeira R.H., Gnanavelbabu A. A Pareto based discrete Jaya algorithm for multi-objective flexible job shop scheduling problem. Expert Syst. Appl. 2021;170:114567. doi: 10.1016/j.eswa.2021.114567. [DOI] [Google Scholar]
  • 15.Cao X., Yang Z. An improved genetic algorithm for dual-resource constrained flexible job shop scheduling; Proceedings of the 2011 Fourth International Conference on Intelligent Computation Technology and Automation; Shenzhen, China. 28–29 March 2011; Piscataway, NJ, USA: IEEE; 2011. pp. 42–45. [Google Scholar]
  • 16.Li J., Huang Y., Niu X. A branch population genetic algorithm for dual-resource constrained job shop scheduling problem. Comput. Ind. Eng. 2016;102:113–131. doi: 10.1016/j.cie.2016.10.012. [DOI] [Google Scholar]
  • 17.Zheng X., Wang L. A knowledge-guided fruit fly optimization algorithm for dual resource constrained flexible job-shop scheduling problem. Int. J. Prod. Res. 2016;54:5554–5566. doi: 10.1080/00207543.2016.1170226. [DOI] [Google Scholar]
  • 18.Zhang J., Wang W., Xu X. A hybrid discrete particle swarm optimization for dual-resource constrained job shop scheduling with resource flexibility. J. Intell. Manuf. 2017;28:1961–1972. doi: 10.1007/s10845-015-1082-0. [DOI] [Google Scholar]
  • 19.Zhang S., Du H., Borucki S., Jin S., Hou T., Li Z. Dual resource constrained flexible job shop scheduling based on improved quantum genetic algorithm. Machines. 2021;9:108. doi: 10.3390/machines9060108. [DOI] [Google Scholar]
  • 20.Tan W., Yuan X., Wang J., Zhang X. A fatigue-conscious dual resource constrained flexible job shop scheduling problem by enhanced NSGA-II: An application from casting workshop. Comput. Ind. Eng. 2021;160:107557. doi: 10.1016/j.cie.2021.107557. [DOI] [Google Scholar]
  • 21.Ghobakhloo M. Industry 4.0, digitization, and opportunities for sustainability. J. Clean. Prod. 2020;252:119869. doi: 10.1016/j.jclepro.2019.119869. [DOI] [Google Scholar]
  • 22.Abdollahzadeh B., Gharehchopogh F.S., Mirjalili S. African vultures optimization algorithm: A new nature-inspired metaheuristic algorithm for global optimization problems. Comput. Ind. Eng. 2021;158:107408. doi: 10.1016/j.cie.2021.107408. [DOI] [Google Scholar]
  • 23.Jun S., Lee S., Chun H. Learning dispatching rules using random forest in flexible job shop scheduling problems. Int. J. Prod. Res. 2019;57:3290–3310. doi: 10.1080/00207543.2019.1581954. [DOI] [Google Scholar]
  • 24.Zitzler E., Deb K., Thiele L. Comparison of Multiobjective Evolutionary Algorithms: Empirical Results. Evol. Comput. 2000;8:173–195. doi: 10.1162/106365600568202. [DOI] [PubMed] [Google Scholar]
  • 25.Zitzler E., Thiele L. Multiobjective evolutionary algorithms: A comparative case study and the strength Pareto approach. IEEE Trans. Evol. Comput. 1999;3:257–271. doi: 10.1109/4235.797969. [DOI] [Google Scholar]
  • 26.Van Veldhuizen D.A., Lamont G.B. Multiobjective evolutionary algorithm test suites; Proceedings of the 1999 ACM Symposium on Applied Computing; San Antonio, TX, USA. 28 February–2 March 1999; pp. 351–357. [Google Scholar]
  • 27.Tay J.C., Ho N.B. Evolving dispatching rules using genetic programming for solving multi-objective flexible job-shop problems. Comput. Ind. Eng. 2008;54:453–473. doi: 10.1016/j.cie.2007.08.008. [DOI] [Google Scholar]
  • 28.Montgomery D.C. Montgomery: Design and Analysis of Experiments. John Willy & Sons; Hoboken, NJ, USA: 2017. [Google Scholar]
  • 29.Deb K., Pratap A., Agarwal S., Meyarivan T. A fast and elitist multiobjective genetic algorithm: NSGA-II. IEEE Trans. Evol. Comput. 2002;6:182–197. doi: 10.1109/4235.996017. [DOI] [Google Scholar]

Associated Data

This section collects any data citations, data availability statements, or supplementary materials included in this article.

Data Availability Statement

Not applicable.