Skip to main content
Springer Nature - PMC COVID-19 Collection logoLink to Springer Nature - PMC COVID-19 Collection
. 2023 Jan 23;45(2):477–523. doi: 10.1007/s00291-023-00705-3

Two-stage stochastic formulation for relief operations with multiple agencies in simultaneous disasters

Oscar Rodríguez-Espíndola 1,
PMCID: PMC9868518  PMID: 36712587

Abstract

The increasing damage caused by disasters is a major challenge for disaster management authorities, especially in instances where simultaneous disasters affect different geographical areas. The uncertainty and chaotic conditions caused by these situations combined with the inherent complexity of collaboration between multiple stakeholders complicates delivering support for disaster victims. Decisions related to facility location, procurement, stock prepositioning and relief distribution are essential to ensure the provision of relief for these victims. There is a need to provide analytical models that can support integrated decision-making in settings with uncertainty caused by simultaneous disasters. However, there are no formulations tackling these decisions combining multiple suppliers, multiple agencies, and simultaneous disasters. This article introduces a novel bi-objective two-stage stochastic formulation for disaster preparedness and immediate response considering the interaction of multiple stakeholders in uncertain environments caused by the occurrence of simultaneous disasters. At the first stage, decisions related to the selection of suppliers, critical facilities, agencies involved, and pre-disaster procurement are defined. Resource allocation, relief distribution and procurement of extra resources after the events are decided at the second stage. The model was tested on data from the situation caused by simultaneous hurricanes and storms in Mexico during September of 2013. The case is contrasted with instances planning for disasters independently. The results show how planning for multiple disasters can help understand the real boundaries of the disaster response system, the benefits of integrated decision-making, the impact of deploying only the agencies required, and the criticality of considering human resources in disaster planning.

Keywords: Humanitarian logistics, Multi-objective programming, Procurement, Simultaneous disasters, Disaster preparedness

Introduction

The COVID-19 pandemic shed some light on the complexity of handling multiple co-occurring disasters. For instance, while managing the pandemic, authorities in Louisiana faced two hurricanes within 36 h, unprecedented wind speeds, and storms 2020 (Jerolleman et al. 2021). Similarly, Seattle was affected by wildfires and heatwaves (McMahon 2021). In August 2018, authorities in south Asia had to respond to floods and earthquakes at the same time (Chen et al. 2018a). The increasing number of simultaneous disasters is complicating disaster response in different countries (Trias and Cook 2021). Simultaneous disasters are “two or more disasters that temporally overlap, may be geographically distant, yet make demands of the same pool of resources” (Doan and Shaw 2019). Planning for these situations is necessary because of their cascading effects on each other (e.g., infrastructure or supply chain disruption), their varying magnitude, the different levels of vulnerability of the affected areas (FEMA 2012; Rottkemper et al. 2011), and their impact on the responses of all the stakeholders involved (FEMA 2003).

Disaster management operations involve deploying governmental agencies with diverse expertise and resources to help victims (Cozzolino 2012; Gutjahr et al. 2020). Their purpose is the dispatch of commodities to affected areas efficiently, effectively and quickly (Özdamar et al. 2004). Collaboration between local and international participants is key to manage complex environmental problems (Charles and Lauras 2011). The plurality of responders (Trias and Cook 2021), however, complicates activities because of their varying goals and access to resources (Thompson and Duintjer Tebbens 2016). Given concerns about the potential competition for resources among organizations (Altay 2013; Besiou et al. 2011), effective collaboration requires adopting a holistic view with clear coordination mechanisms to support key stakeholders (Jerolleman et al. 2021). That is the role of a central coordinator, often adopted by federal authorities (Alexander 2015), which make decisions and guide the activities of participants. Effective management of stakeholders at different levels allows to dispatch the agencies needed to support victims of simultaneous disasters (Jerolleman et al. 2021; Chen et al. 2018a), which reduces convergence of staff (Rodríguez-Espíndola et al. 2020) and mitigates the challenges with jurisdictions (Ansell et al. 2010).

Currently, the most widely used approach to handle simultaneous disasters involves adapting single-disaster mechanisms to try to make them effective in these settings (Jerolleman et al. 2021; Kappes et al. 2012). Recent experiences, however, underscore the urgency of going beyond current measures prepared for independent disasters (Chen et al. 2018a) to avoid improvising solutions once the demand caused by several disasters increases, as experienced before (Jerolleman et al. 2021). With the expected increase of simultaneous disasters in the future (FEMA 2012), disaster planners need to think about these instances to prepare effective disaster response (McMahon 2021). This research aligns to the call for having multi-hazard rather than single-hazard management systems for disasters (UNISDR 2019). Neglecting the interaction between hazards can lead to unreliable conclusions. Deciding which stakeholders to involve, what to procure and from whom to satisfy requirements at different locations simultaneously are complex issues. These decisions must consider facilities, resource constraints and demand requirements to provide for victims. Poor management in such conditions can cause delays, duplication of efforts, and inefficient use of resources, which are reasons leading governments to plan and prepare for simultaneous disasters (Doan and Shaw 2019).

This article proposes a two-stage bi-objective stochastic model to support procurement, facility location, resource allocation, and relief distribution in situations caused by simultaneous disasters as an integrated approach needed to manage humanitarian operations. The model incorporates decisions about supplier selection, facility location, stock prepositioning and organization selection at the first stage, whereas the second stage looks at resource allocation, additional procurement, and relief distribution. The formulation is tested using data from the disaster of 2013 in Mexico, where Hurricanes Ingrid, Manuel and major storms occurred at the same time and caused significant damage to the country. The results of the analysis show the importance of considering the interaction of multiple stakeholders during simultaneous disasters to prevent selecting sub-optimal solutions obtained from looking at independent disasters. The contribution is twofold: (i) it provides a novel stochastic formulation considering multiple responding agencies and multiple suppliers in humanitarian operations to manage simultaneous disasters, and (ii) it provides evidence about the impact on performance of neglecting simultaneous disasters.

The article is structured as follows. Section 2 looks at contributions combining procurement, facility location, stock prepositioning, resource allocation, and relief distribution to present the context and place the contribution in the literature. Section 3 introduces the details of the formulation, and Sect. 4 presents details of the case study. Section 5 includes the analysis of results, and Sect. 6 discusses their relevance. Finally, Sect. 7 presents the conclusions of this work and future research areas.

Literature review

This article is looking at the combination of procurement with other logistics activities in a multi-agency environment during situations caused by simultaneous disasters. Recently, there has been a surge of articles looking at procurement to account for the impact of supply chain actors in relief operations. To understand the contribution of this article in the current state of knowledge, the literature review will look at articles focused on procurement, the evolution toward the integration of multiple participants, and at the inclusion of simultaneous disasters. Finally, it will elaborate on the research gap.

Disaster procurement

Disaster procurement models include decisions about the suppliers required, pre-disaster products to acquire (often prepositioned), and/or post-disaster products bought and delivered. Falasca and Zobel (2011) develop a model with recourse to support procurement in disaster operations. The formulation determines how much to order right after a disaster occurs in the first stage. Once more accurate information about the impact of the disaster is received, additional quantities are requested at the second stage. The model minimizes procurement and shortage costs across all possible scenarios. Considering a risk-averse decision maker, Lu et al. (2016) provide an estimation component and a relief distribution model minimizing total travel time using a rolling horizon approach. Proposing a combination of partial prepositioning and procurement to reduce shortages of relief items, Pradhananga et al. (2016) introduce a scenario-based model minimizing a nonlinear function of social cost for supply facility selection, based on the combination of logistics and deprivation costs. Hu et al. (2017) use a scenario-based approach in a two-stage stochastic programming model to determine the number of suppliers, pre-disaster inventory levels, and locations in the first stage, while post-disaster procurement quantities and the distribution plan are determined in the second stage. The formulation minimizes cost including shortage cost and salvage value. Gonçalves and Castañeda (2018) argue that relief prepositioning decisions resemble newsvendor decisions. They use a newsvendor model and provide variants with the aim of minimizing cost. Using behavioral experiments on 20 relief managers, they show how criticality moderates demand chasing. Alem et al. (2016) design a dynamic model to minimize the weighted sum of cost and unmet demand. First-stage variables include prepositioning and vehicle contracting, while the second stage looks at relief distribution and inventory management. Hu and Dong (2019) propose a two-stage formulation minimizing total expected cost, including shortage penalties. First-stage decisions include location and pre-disaster procurement, whereas second-stage decisions involve transportation and post-disaster procurement. Alem et al. (2021) adopt a social vulnerability index to prioritize victims and needs for procurement, facility location, prepositioning, and distribution. The aim of the model is to maximize coverage, and the dynamic nature of disaster management is included using macro-time and micro-time periods. This article highlights the importance of considering the different levels of vulnerability of each community.

Articles in this section show the importance of linking pre-disaster and post-disaster procurement with other logistics activities such as relief distribution and facility location. The connection between these activities is important because of the availability of supply or supply chain constraints affecting the performance of humanitarian operations. Looking at the different formulations, the value of two-stage formulations to tackle these problems becomes evident. Nevertheless, these formulations are often designed to provide support for one organization facing a single disaster. Neglecting the interaction between stakeholders can have a steep effect on the support given to affected communities (Haimes 2012), especially considering the importance of human resources in disaster management (Santos et al. 2014). Limited resource supply, competition for resources among agencies, and poor government support (Chang et al. 2011) are problems that can be tackled considering multiple agencies and multiple suppliers.

Disaster procurement with multiple participants

Considering the preference of governments to avoid a dependence on single suppliers for reasons of cost, image, and supply failure risk (Balcik and Ak 2014), different types of agreements looking at price and quantity for supplier selection have been studied. These studies are looking at vertical coordination, where the importance of benefits for the organization and suppliers are considered. Shokr and Torabi (Shokr and Torabi 2017) propose a coordinating platform for humanitarian organizations with two phases: bid-construction and a bid-evaluation using possibilistic models. The bid-construction model maximizes profit, whereas the bid-evaluation model minimizes cost and maximum delivery times. The use of different types of contracts has been the focus of different contributions, with articles looking at quantity flexibility, option and bonus contracts. Nikkhoo et al. (2018) analyze the use of quantity flexibility contracts to coordinate procurement in a supply chain. Their objective is to minimize cost by signing agreements between one supplier and one relief organization to coordinate the supply chain. Torabi et al. (2018) propose a fuzzy-stochastic programming model for prepositioning and procurement using quantity flexibility contracts as well. The objective of the formulation is to minimize cost, including penalty cost for unmet demand. First-stage decisions are focused on facility location and prepositioning, whereas second-stage decisions provide the post-disaster procurement and distribution plan. The SIR epidemic model is used for analysis of the post-disaster situation considering the delivery of vaccines. Shamsi et al. (2018) propose a game formulation for vaccine procurement exploring option contracts considering a backup supplier. The aim of the buyer is to minimize cost (including social cost) and the objective of the suppliers is to maximize profit. Also using option contracts, Liu et al. (2019) address governmental stock prepositioning with multiple suppliers. They formulate their model as a Stackelberg game with the government as leader and the suppliers as followers. The objective of the former is to minimize negative impact and cost whereas the aim of the latter is to maximize profit. Aghajani et al. (2020) integrate a two-period option contract with supplier selection and inventory prepositioning into a two-stage possibilistic stochastic model. The formulation has two objectives: to minimize cost and maximize coverage. At the first stage, the model determines decisions about stock prepositioning and procurement. Second-stage decisions include exercised amounts based on the contracts. Wang et al. (2019) aim to optimize agreements with suppliers for stock prepositioning. They add bonus contracts to fixed framework agreements to incentivize suppliers to reduce delivery time. They propose a performance measurement model using deprivation cost and their results show the potential of bonus contracts to improve the performance of humanitarian operations. These articles contribute to understanding the interaction between suppliers and buyers in the supply chain, but the horizontal coordination between organizations responding in the field is missing. Game theory considers different players with individual goals, which aim to maximize their own goals (non-cooperative games) or to create strategic alliances to maximize pay-offs (cooperative games) (Muggy and Jessica 2014). Horizontal collaboration has been addressed using game theory to account for competition among humanitarian organizations using non-cooperative games. Toyasaki et al. (2017) develop a newsvendor model with the aim of minimizing cost in the context of horizontal collaboration between organizations for inventory management. The joint participation of distinct NGOs is addressed by Nagurney et al. (2019) through a model capturing the competition among NGOs that determines the quantity of supplies to purchase, supplier selection, and relief distribution using specific freight logistics providers. This stream of research considers competition among players (Seaberg et al. 2017). However, when multiple players are considered, the problem becomes more difficult to solve, the participants need to be known in advance, and it is important to have foresight of information and potential strategies (Jacob and Charles 1999).

An alternative to game formulations has been to consider an upper-level coordinator directing different agencies. This approach allows to have organizations with aligned objectives, which has been addressed using resource allocation models to manage multiple participants in humanitarian logistics (Lei et al. 2015; Shan and Zhuang 2013). Celik et al. (2016) propose a formulation focused on location-allocation considering pre-disaster procurement decisions on the first stage, and post-disaster procurement and allocation on the second stage. The model aims to minimize cost considering the participation of different governmental and non-governmental organizations. Velasquez et al. (2019) account for the multi-agency collaboration between governmental agencies and other organizations for procurement, allocation, and inventory. The formulation uses robust optimization to minimize the total demand-weighted distance from distribution centers to dispensing locations. Balcik et al. (2019) introduce an insurance-based method to support facility location and stock prepositioning as part of horizontal collaboration. The model includes decisions about location, premiums, and budgets in the first stage, whereas the second stage is focused on transportation and procurement. The aim is to minimize costs and deviation from the premium paid, and the cost expected for the participants. Arif et al. (2020) focus on repairs after disasters, considering uncertainty in demand and repair times, aiming to minimize cost including penalty costs for delays. The first stage of the model determines the facilities used and the initial allocation of crews and equipment, while second-stage decisions are focused on allocating crews to affected areas and ordering new equipment.

The cluster of articles presented in this part is looking at the importance of guiding different participants in the field to improve horizontal coordination and support disaster victims. It is noteworthy that the articles in this section include resource allocation decisions as part of their formulations, given the importance of these decisions to guide activities from different participants. However, these models also neglect the potential characteristics of different disasters and its effect on the availability and allocation of resources.

Multiple disasters and disaster procurement

Governmental authorities struggle to manage the impact and needs caused by more two or more hazards at the same time, i.e., multiple disasters. Several countries are vulnerable to face multiple hazards simultaneously (Julca 2012), and they require models to support decision-making in those conditions. Considering the expectation about the increase of multiple disasters in the future (FEMA 2012), and the reliance on shared resources to satisfy the needs of all the victims (Kappes et al. 2012), this section analyzes contributions in the procurement literature in that context.

Articles in the literature have identified different types of multiple disasters. When different hazards occur in the same community at the same time, these are called compound disasters (Wachira 1997). Klibi et al. (2018) provide a two-stage stochastic formulation to design a relief network for facility location and stock prepositioning considering the inter-arrival time between two hazards. First-stage decisions are focused on location and prepositioning activities, while second-stage decisions support relief distribution. The authors address the complexity of the need for more than one objective using a weighted sum to maximize coverage and minimize cost. Some authors have looked at situations caused by more than one disaster on different communities. Sharifyazdi et al. (2018) analyze the potential of having relief prepositioned onshore and offshore at on-board vessels. The stochastic formulation aims to support inventory and relief distribution decisions to minimize cost. The proposed model recognizes the different communities affected by hazards to determine the dispatch of products. Chen et al. (2018b) use a prepositioning policy to prepare for multiple disasters. They propose an NGO prepositioning model using the multi-product newsvendor approach to tackle multiple disasters. The flexible structure policy allows joint prepositioning among organizations to minimize cost.

Secondary disasters are another type of multiple disasters. The term refers to a series of disasters taking place after the occurrence of a primary disaster (Zhang et al. 2012). For instance, a tsunami taking place after an earthquake. Focused on those situations, Zhang et al. (2012) consider the probability of occurrence of secondary disasters as a result of the primary catastrophe to propose a resource assignment method for disaster relief. The purpose is to respond to potential secondary disasters based on the decisions made for the primary disaster. The model minimizes travel time between areas. Considering the impact of secondary or subsequent disasters in demand and delivery time, Nezhadroshan et al. (2021) design a possibilistic-stochastic model for procurement and facility location with the objective to minimize logistics costs, maximum travel time, and maximize the level of resilience of the facilities selected. Similarly, Foroughi et al. (2022) incorporate the effect of subsequent disasters on demand in a bi-objective formulation minimizing total cost and maximizing the resilience level of facilities. They show a comparison of solution methods using NSGA-II, NRGA and MOPSO.

The case where different disasters affect different areas at the same time is referred in this paper as simultaneous disasters, and it has been addressed by Doan and Shaw (2019). The authors focus on resource allocation using three optimization models: the first looking at the risk of not reaching the desired level of service with resource constraints, the second one suggesting the resources needed to satisfy the emergencies and the third one combining both models. The formulation introduces the needs of the affected areas based on the type of disaster to guide the allocation. The article shows the importance of considering available resources to carry out humanitarian operations in instances caused by simultaneous disasters.

In general, the articles in this part acknowledge the occurrence of more than one disaster in the same community and different communities. It is possible to note the importance of the difference between the areas affected and the varying nature/magnitude of the disasters. However, only Doan and Shaw (2019) consider the possibility of having independent hazards affecting different regions, which can have an effect on different logistics decisions, and it is focused on resource allocation more than on other key logistics decisions.

Research gap

Tables 1 and 2 provide a summary of the articles reviewed. There are several key takeaways from the literature review. The possibility of congestion because of convergence of supply (Wachtendorf and Kendra 2004) has started the discussion about the value of looking at the participants and their resources. Rodríguez-Espíndola et al. (2018a) argue that selecting and sending the required human and material resources to the field can provide advantages over deploying all available resources. Abualkhair et al. (2020) provide evidence suggesting that having more resources does not necessarily improve the level of service. Nevertheless, most of the formulations in supplier selection and procurement found in the literature neglect to consider the interaction of multiple agencies. Game theoretical formulations make an attempt by incorporating competition between players with selfish objectives, but the introduction of stochastic parameters and the need for a set number of players complicates looking into congestion in supply. On the other hand, formulations looking at collaboration between organizations do not consider the potential impact of having an excess of participants. Hence, new formulations that can manage the resources from different participants to optimize the number of organizations involved in humanitarian operations are needed.

Table 1.

Summary of the decisions tackled by the models

Article Pre-disaster procurement Post-disaster procurement Supplier selection Distribution Resource allocation Location Type of facilities
Falasca and Zobel (2011)
Zhang et al. (2012)
Lu et al. (2016)
Pradhananga et al. (2016) Supply points
Alem et al. (2016)
Hu et al. (2017) Distribution centers
Celik et al. (2016) Distribution centers
Toyasaki et al. (2017)
Shokr and Torabi (2017)
Nikkhoo et al. (2018)
Torabi et al. (2018) Central warehouses and local warehouses
Sharifyazdi et al. (2018)
Klibi et al. (2018) Distribution centers
Gonçalves and Castañeda (2018)
Chen et al. (2018)
Shamsi et al. (2018)
Nagurney et al. (2019)
Wang et al. (2019)
Balcik et al. (2019) Warehouses
Velasquez et al. (2019) Distribution centers
Liu et al. (2019)
Hu and Dong (2019) Distribution centers
Doan and Shaw (2019)
Arif et al. (2020) Depots
Aghajani et al. (2020)
Nezhadroshan et al. (2021) Central warehouses and local distribution centers
Alem et al. (2021) Warehouses and relief centers
Foroughi et al. (2022) Central warehouses and local distribution centers
This article Distribution centers

Table 2.

Summary of the characteristics of the models

Article Characteristics of the models Objectives
Vertical coordination Horizontal coordination Multiple disasters Multiple suppliers Multiple products Human Resources Stochastic demand Multiple objectives Objective function
Falasca and Zobel (2011) Minimize cost
Zhang et al. (2012) Minimize cost
Lu et al. (2016) Minimize total distribution time
Pradhananga et al. (2016) Minimize cost
Alem et al. (2016) Minimize cost
Hu et al. (2017) Minimize cost
Celik et al. (2016) Minimize cost
Toyasaki et al. (2017) Minimize cost
Shokr and Torabi (2017) Maximize supplier profit, minimize cost efficiency and delivery time for the organization
Nikkhoo et al. (2018) Maximize supplier profit, minimize cost
Torabi et al. (2018) Minimize cost
Sharifyazdi et al. (2018) Minimize cost
Klibi et al. (2018) Weighted sum of maximizing coverage and minimizing cost
Gonçalves and Castañeda (2018) Minimize cost
Chen et al. (2018) Minimize cost
Shamsi et al. (2018) Minimize buyer logistics and social cost, maximize supplier’s profit
Nagurney et al. (2019) Maximize utility
Wang et al. (2019) Minimize deprivation
Balcik et al. (2019) Minimize costs and deviation from the premium paid
Velasquez et al. (2019) Minimize demand-weighted distance
Liu et al. (2019) Minimize negative impact and cost for the government and maximize supplier profit
Hu and Dong (2019) Minimize cost
Doan and Shaw (2019) Minimize the risk of not satisfying all resource requirements, minimize cost of additional resources
Arif et al. (2020) Minimize cost
Aghajani et al. (2020) Minimize cost and maximize coverage
Nezhadroshan et al. (2021) Minimize cost, maximum travel time, and resilience of the facilities
Alem et al. (2021) Maximize coverage
Foroughi et al. (2022) Minimize cost and maximize resilience of the facilities
This article Minimize cost and minimize shortage of relief

Although some models have addressed collaboration in logistics activities for single disasters, when multiple or simultaneous disasters are considered, there is an absence of articles accounting for multiple participants as well. The literature has focused heavily on compound and secondary disasters. Following the impact of climate change, the large number of natural disasters is expected to increase globally (EM-DAT 2019), which in turn will also increase the occurrence of independent hazards affecting different communities (FEMA 2012). These disasters have the added complexity of having different regions affected and lacking sequential occurrence, as opposed to compound and secondary disasters, respectively. Only Doan and Shaw (2019) have looked at simultaneous disasters in humanitarian operations, but they are focused on resource allocation alone. Their work opens the door to developing comprehensive logistics plans to support victims affected by situations caused by simultaneous disasters.

Humanitarian logistics require balancing efficiency and effectiveness (Beamon and Balcik 2008), but only Klibi et al. (2018) introduce multiple objectives in a formulation handling instances caused by multiple disasters. It is important to combine the perspective of the decision-makers and the victims to develop suitable and implementable logistics plans. Although their article does not include human resources, congestion in supply or multiple stakeholders, it shows the importance of including more than one performance measure in decision-making, which is currently understudied in the area.

Overall, the literature review has shown the lack of articles optimizing the number of participants for integrated humanitarian operations including procurement, facility location, and relief distribution, especially in instances caused by simultaneous disasters. The occurrence of simultaneous disasters and their impact on logistics activities is currently understudied. Finally, most of the formulations analyzed consider single performance measures, even though humanitarian operations need to incorporate different dimensions. This article is filling those gaps. It is the first article integrating multiple suppliers, multiple agencies, and simultaneous disasters in the same formulation. Each one of these aspects has been studied independently, but their interaction remains understudied. This article proposes a bi-objective formulation to manage logistics activities involving human resources in settings with stochastic demand and optimizing the number of agencies involved to reduce supply congestion, an approach never undertaken before in the literature.

Methodology

Context of the situation

The interaction of different stakeholders can have a major impact in humanitarian operations, as there is potential for duplication of efforts and competition for scarce resources (Balcik et al. 2010). Coordination plays a crucial role to facilitate the participation of multiple stakeholders and mitigate those problems. Research has shown that clear roles are essential to facilitate coordination and collaboration (Jensen and Hertz 2016). Following arguments about the value of having a coordinator overseeing and guiding operations (Akhtar et al. 2012; Takeda and Helms 2006) mention the existence of “umbrella” organizations responsible for coordinating relief activities of participants in the field. This idea is aligned with civil protection systems in different countries (Alexander 2015), where one coordinator facilitates the interaction between participants and orchestrates the response. Hence, the formulation proposed is built considering a centralized decision-making structure with an upper-level decision-maker guiding different agencies. The coordinator interacts with suppliers, manages the flow of information, deploys organizations, and allocates resources from participants to different disasters and activities.

The two-stage formulation has a clear line between pre-disaster and post-disaster activities. Prior to the disasters, it is important to set-up the relief network. That includes selecting key suppliers, which organizations to deploy, the facilities to use and pre-disaster procurement. After the disasters take place, the allocation of employees, post-disaster procurement, and relief distribution decisions are carried out. A planning horizon of 3 days before and after the disasters is considered for design, although pre-disaster activities can be implemented at any point before the expected occurrence of the disasters and the number of days for response can be tailored to the characteristics of the response system. The focus on the first 3 days after the disasters is linked to the importance of the first 72 h to provide immediate support to save lives and reduce suffering. After this period, there is a shift in needs, priorities, and resources resulting from funding becoming less available (Gustavsson 2003), aiming to provide efficient support in the medium to long term (Wassenhove 2006). As the resources from the civil protection system will be under pressure at this point, the model supports decisions to facilitate the use of resources and respond swiftly and effectively. For simultaneous disasters, once the critical first 72 h pass, the decisions from the model can be the basis for long-term dynamic formulations, whereas in cases with subsequent disasters, the information can be updated with the new information to use the model to provide support for these instances as well.

Suppliers ship relief aid to regional distribution centers, which in turn send it to the affected areas, as used by previous papers (Pradhananga et al. 2016; Hu et al. 2017). Governmental authorities often have a list of approved suppliers which provide commodities in certain amounts and with already agreed prices. Procurement of relief items can be undertaken prior to the disaster (i.e., for stock prepositioning) (Elçi and Noyan 2018; Noyan and Kahvecioğlu 2018) and after the disaster to manage the initial stages of the response based on the circumstances of the disaster.

Activities in distribution centers, such as sorting, classifying, processing and preparing for delivery (Holguín-Veras et al. 2012), are undertaken by personnel from the agencies involved. They also manage the delivery of relief using available vehicles. Similar to the case of human resources, the number of vehicles is limited and it affects the cost of operations (Briskorn et al. 2020).

The decisions described need to be made for every region affected by a disaster, and traditionally this process has been treated as independent planning in the literature. In disaster-prone countries, however, it is possible to have more than one disaster affecting different regions of a country at the same time (Doan and Shaw 2019). Therefore, this paper is proposing a stochastic bi-objective model to provide support for procurement, facility location, resource allocation, and relief distribution for multiple agencies working on situations caused by two or more disasters occurring at different regions during a similar period of time. The model can be used for planning to analyze highly vulnerable areas, or for instances in which forecasts (e.g., for hurricanes) show potential impact in different regions.

Model assumptions

The optimization model proposed is underpinned by the following set of main assumptions:

  • There is an umbrella organization coordinating disaster management participants. Having a central coordinator can help reduce duplication of efforts and competition for resources (Takeda and Helms 2006) and it has been used in previous formulations (Rodríguez-Espíndola et al. 2018b) because it aligns to the characteristics of civil protection systems in different countries (Alexander 2015).

  • Shipments from the supplier to the distribution centers are arranged and managed by the supplier. This can be arranged with the supplier based on the agreements that can be established prior to the occurrence of disasters (Balcik and Ak 2014; Torabi et al. 2018).

  • The agencies managing the disasters have the authority to participate in the different regions. This is an important consideration to reduce the impact of jurisdictional barriers that could affect the response to disasters occurring at different locations, which can be considered for national level emergencies (Boin and Lagadec 2000).

  • Public donations are collected and managed for post-disaster distribution. Hence, these are beyond the planning horizon of the model. As the model is focused on immediate response, it is assumed that immediate response is handled with resources from official participants (Torabi et al. 2018).

  • Information and resources from every participating agency and suppliers are shared with the disaster management coordinator. This assumption enables the coordinator to define the best use of all the resources available and guide effectively the response (Lu et al. 2016; Rodríguez-Espíndola et al. 2018b).

  • Contracts and conditions of supply with potential suppliers are pre-arranged. This assumption is based on the type of agreement with suppliers to give more realism to the requirements for the commitment and participation of them (Balcik and Ak 2014; Torabi et al. 2018).

  • Each supplier and agency involved have ready-to-ship resources and they are ready to fully contribute their resources immediately. This assumption is based on the planning horizon. The three days before the disasters strike are assumed to be enough to prepare and deploy resources based on agreements with suppliers and the interaction with the organizations involved (Balcik and Ak 2014).

  • Supply capacity and costs are assumed to be known in advance. Based on the experience in previous disasters, the planning horizon of 72 h, and the use of available stock, supplier agreements are assumed to have accurate information about capacities and costs.

These assumptions shape the characteristics of the formulation. The use of a central coordinator with a clear role and attributions is essential for the formulation proposed. Centralized decision-making for disaster response is used in civil protection systems on several countries currently (Alexander 2015), which facilitates fitting the model in these cases. That coordinator enables the participation of organizations to prevent jurisdictional restrictions because they have the attributions to authorize the participation of the stakeholders. It is an approach that can be adapted to current systems and reduce cost (Arif et al. 2020). That also relies on accurate information sharing between participants and the coordinator. In the case of the central coordinator and the organizations involved being from the government, that can facilitate the exchange of information, but for external organizations this aspect needs to be carefully considered because it can affect the solutions. The interaction with suppliers can be governed by agreements. Pre-determined agreements with suppliers are set to define the requirements of supply, including the responsibilities for shipping relief, commitment fees, and order sizes (Balcik and Ak 2014). The planning horizon restricts the inclusion of donations, which can also be unpredictable, to provide a plan for civil protection authorities with their resources at hand. Overall, the assumptions presented in this section are aligned to current practice and can be achieved defining the attributions of the central coordinator, clear agreements with suppliers, and accurate knowledge about available resources at the pre-disaster stage.

Model formulation

This article employs optimization to develop a plan for humanitarian logistics balancing the shortage of relief items with the operational cost of the logistics operations. Although authors in the literature have introduced objective functions specifically focused on humanitarian operations See Sheu (2014), Duhamel et al. (2016), the complexity of these operations can be better served using more than one objective. Thus, the use of multiple objectives has been deemed as an appropriate approach to consider the conflicting goals encountered in humanitarian operations (Beamon and Balcik 2008; Doerner et al. 2009). The model determines the optimal location of regional supply facilities (e.g., warehouses or distribution centers) based on their capacity, distance to the affected areas, and operational cost. The facilities are used to preposition stock and prepare the relief items for dispatch. These facilities are operated by staff from the organizations deployed to receive and manage items from a set of suppliers selected at the first stage of the model. Along with supplier selection, the model introduces pre-disaster and post-disaster procurement constrained by the capacity of supply from suppliers and the minimum order size set in the agreements with them. Pre-disaster procurement decisions are made at the first stage to facilitate immediate response, whereas post-disaster procurement allows decision-makers to define the quantity if relief to get immediately after the disaster to adjust to the conditions of the scenario.

Staff from the selected organizations is allocated to relief management or distribution. The purpose is to balance the needs to operate the system and avoid having an excess of human resources. On the other hand, relief distribution decisions are oriented toward the delivery of relief items from regional supply facilities to the affected areas. Relief distribution decisions include the service from supply to demand facilities, the quantity of items shipped, and the trips required for delivery.

The model is designed to provide support for disaster preparedness and immediate response, which are crucial for survival and to reduce suffering. Simultaneous disasters affecting multiple areas can be very demanding at that stage because resources must be shared quickly without a clear sequence of events. Hence, the model proposed is looking at that period, to enable decision-makers to modify once there is more information about the different damages.

Table 3 presents the model notation and definitions. The data description can be found in Appendix.

Table 3.

Model notation and definitions

Indices
i Index of regional supply facilities
j Index of demand areas
o Index of available relief agencies
k Index of potential suppliers
n Index of relief items
l Index of regions affected by disasters
s Index of scenarios
Scenario-independent parameters
αk,n Cost of relief item n from supplier k at stage the second stage
βk,n Supply capacity of relief item n from supplier k
γi Cost of opening supply facility i
ζi,j,l Cost of each trip from supply facility i to demand point j at region l
η Number of potential trips per day per vehicle
θ Procurement budget
ιo Number of vehicles available per agency o
κk Cost of the partnership with supplier k
μo Cost of involving agency o
νk,n Minimum order size of relief item n allowed by supplier k
ξi,k Coverage from supplier k to facility i
o Facility space covered per employee
σ Weight capacity of each vehicle
τi Volumetric capacity of the distribution center i
υo Number of employees per agency o
φn Volume of relief item n
χ Number transportation staff required per trip per vehicle
ψn Weight of relief item n
Ωk,n Cost of buying relief item type n from supplier k at stage 1
Scenario-dependent parameters
δj,n,l,s Demand of relief item n in area j at region l under scenario s
πs Probability of scenario s
ρl,s Priority of disaster area l under scenario s
First-stage decision variables
Ak Selection of supplier k; 1 if the supplier is chosen, 0 otherwise
Xi Activation of distribution center i; 1 if the facility is opened, 0 otherwise
Yi,k,n Number of relief items type n procured from supplier k for distribution center i at stage 1
Wo Involvement of agency o; 1 if the agency is deployed, 0 otherwise
Second-stage decision variables
Ci,n,s Number of relief items n allocated to facility i at scenario s
Di,o,s Employees from agency o allocated to relief management in DC i at scenario s
Ei,o,s Employees from agency o allocated for distribution in DC i at scenario s
Gi,j,o,l,s Trips from facility i to zone j at region l at scenario s of vehicles from agency o
Pj,n,l,s Demand not satisfied of relief item n at area j in region l at scenario s
Qi,j,n,l,s Relief item type n sent from supply facility i to demand point j in region l at scenario s
Ti,k,n,s Relief item type n bought from supplier k for distribution center i at stage 2 at scenario s

The model supports the selection and management of the most suitable stakeholders (i.e., suppliers and relief agencies) to engage in simultaneous disasters, because of the importance of incorporating to introduce multiple stakeholders in the optimization of humanitarian operations (Anaya-Arenas et al. 2014). Having an umbrella organization coordinating the efforts of different agencies introduces the possibility of deploying only the necessary stakeholders to avoid supply congestion (Wenger et al. 1986; Abounacer et al. 2014) and supports the collaboration and swift response required to minimize death and suffering. This becomes even more relevant in situations caused by multiple disasters, to avoid competition for resources among jurisdictions (Altay 2013), to allow the holistic analysis of the use of resources, and to consider the characteristics of resource providers. The formulation represents the involvement of agencies and suppliers as decision variables to ensure only required participants with the most suitable resources are involved to handle the situation, while different regions are included as a set to account for multiple simultaneous disasters. This perspective aligns with the escalation processes for civil protection systems used in several countries (Takeda and Helms 2006).

Selected stakeholders are supported by facility and relief delivery decisions. A set of facilities are chosen to manage the relief procured for all areas before and after the occurrence of the disasters. Relief delivery involves the use of human and material resources from participant agencies. Effective use of resources in simultaneous disasters is very important. Parameter ρl,s has been included in the model to reflect the urgency of an affected area to allow optimal resource allocation (Sarma et al. 2020) based on the nature of the disasters and the vulnerability of the areas affected. This parameter can be set using forecasts about the magnitude and nature of the events or combined with levels of vulnerability of the regions affected to determine the optimal split of resources. Hence, more severe disasters affecting vulnerable areas would have a higher ρl,s, forcing the model to use more resources to reduce shortage in those areas.

Because of the presence of uncertainty in disaster management, authorities require the development of plans to manage resources available with the aim of supporting victims (Chang et al. 2007). Hence, the model is formulated using a two-stage stochastic approach. The pre-disaster phase is addressed at the first-stage, and the second-stage is focused on the post-disaster phase See Behl and Dutta (2019). The first stage includes the activation of different agencies, the selection of suppliers, the opening of distribution facilities and pre-disaster procurement of relief sent to them. Second-stage variables involve scenario-dependent decisions at the response stage including the procurement of further relief items to complement the prepositioned stock, the allocation of human and material resources, and decisions about relief distribution. The deterministic equivalent problem of the model proposed is structured as follows:

minCOST=iXiγi+oWoμo+iknYi,k,nΩk,n+kAkκk+sπsiknTi,k,n,sαk,n+ijolGi,j,o,l,sζi,j,l 1
minSHORTAGE=jnlsρl,sπsPj,n,l,s 2

Objective function (1) minimizes cost whereas objective function (2) minimizes shortage of relief. The COST function involves the cost of activating a facility and preparing it for operation, staff cost incurred for activating an organization, the cost of entering a partnership with a supplier, procurement cost (prior to the disaster and after the occurrence of disaster) and transportation cost. The SHORTAGE function reduces the maximum shortage of relief items based on the priority of the region (decided according to the severity of damage and urgency) and the probability of the scenario. The constraints include:

oDi,o,sonCi,n,sφni,s 3
Akνk,niTi,k,n,s+Yi,k,nAkβk,nk,n,s 4

Constraint (3) ensures enough employees are allocated to operate the supply facilities, whereas expression (4) makes sure that items procured from any supplier (either prior or after the disaster) respect the minimum order size agreed and their maximum supply capacity.

Ci,n,s=kYi,k,nξi,k+kTi,k,n,sξi,ki,n,s 5
nCi,n,sφnXiτii,s 6

Equation (5) combines the relief items available that have been procured at both stages, while constraint (6) ensures the total number of relief items available does not exceed the capacity of the distribution centers opened.

jlQi,j,n,l,sCi,n,si,n,s 7
iknsTi,k,n,sαk,n+iknYi,k,nΩk,n+ijolsGi,j,o,l,sζi,j,lθ 8

Expression (7) makes sure than only available relief items are shipped to the affected regions, whereas constraint (8) ensures the relief distribution budget is not exceeded, combining procurement and distribution cost.

Pj,n,l,s=δj,n,l,s-iQi,j,n,l,sj,n,l,s 9
oGi,j,o,l,sσnQi,j,n,l,sψni,j,l,s 10

Equation (9) calculates the shortage of relief items per demand area and constraint (10) estimates the number of trips required for relief distribution. These trips are determined using capacity of the vehicles based on vehicles with the same weight capacity, which can have different volume capacities.

ijlGi,j,o,l,sWoιoηo,s 11
jlGi,j,o,l,sχEi,o,si,o,s 12
i(Di,o,s+Ei,o,s)Woυoo,s 13

Constraint (11) ensures that vehicle capacity of the agencies involved is not exceeded by the trips required, whereas expression (12) determines the number of employees to be allocated to distribution activities and constraint (13) ensures that the total number of employees allocated is below the capacity of the agencies involved. Declaration of integer and binary variables is presented below. The reason for the use of discrete variables is because of the nature of the decisions involving products, people, and trips, which cannot be divided. However, that influences the solution time.

Ci,n,s,Di,o,s,Ei,o,s,Gi,j,o,l,s,Pj,n,l,s,Qi,j,n,l,s,Ti,k,n,s,Un,l,s,Yi,k,n,Z0;Ak,Wo,Xi0,1

Solution method

A major challenge of the formulation presented is that it has two objectives, which require multi-objective solution techniques. Given the added difficulty to anticipate the post-disaster decisions of each scenario, a scalarization technique is proposed to transform a vector problem into a family of scalar optimization problems (Huong and Yen 2014). The ε-constraint method has been selected because of its simplicity and the evidence in the literature about its value to obtain solutions (Nazemi et al. 2022). To implement the method, the SHORTAGE objective function has been selected as primary objective. Consequently, the COST objective function is turned into a constraint and the model takes the following form:

minSHORTAGE=jnlsρl,sπsPj,n,l,s 14

s.t. (3)–(13).

With the additional constraint:

iXiγi+oWoμo+iknYi,k,nΩk,n+kAkκk+sπsiknTi,k,n,sαk,n+ijolGi,j,o,l,sζi,j,lεΦ 15

The single-objective problem is solved parametrically for different values of ε. The values of ε are determined using the payoff table of both objectives, in which the minimum and maximum values of the COST objective function are used as reference to minimize (14) for Φ iterations. The results are used to obtain the Pareto front of the problem.

Case study: Mexico

Region of study

Hurricanes and tropical storms are a significant problem in the country, as shown by the 58 disasters caused by storms from 2000 to 2018 (EM-DAT 2019). However, situations are worse when different disasters affect the country simultaneously. Countries near subduction zones, such as Mexico, are more vulnerable to the occurrence of multiple hazards (Ordaz et al. 2019). From 2009 to 2018, nearly 50% of the disasters caused by hydrometeorological phenomena in Mexico occurred at the same time as other disasters (EM-DAT 2019). For instance, in September 2013, Hurricane Ingrid affected the Caribbean region, while Hurricane Manuel approached the Pacific coast, and heavy rainfall was reported in the northwest of the country. These disasters affected around 155,000 people and caused nearly 200 deaths (EM-DAT 2019). The case study analyzed in this article is based on that situation because of the economic and social implications of reacting to a complex situation caused by the three disasters with limited resources.

Disaster management structure

Decision-making in disaster situations in Mexico is centralized, with the National System for Civil Protection (SINAPROC) as the coordinating entity in charge of articulating activities from different participants (Sosa-Rodríguez 2006). Each organization has regulations and directives in disaster situations (SEGOB 2006), often overlapping. The SINAPROC directs other branches of the government and collaborators to deliver the response as per government legislation (Alexander 2015). SINAPROC relies on the organization in charge of food services (DICONSA), responsible for procuring and distributing food for social programs and disaster relief, and to use their pre-arranged agreements with suppliers to source relief.

Data collected

Data were collected from secondary sources through reports and freedom of information (FOI) requests. Freedom of information requests are submitted electronically through the Mexican transparency system including the type of request, the information required and the responsible agency. Information was gathered from eight agencies in health services (IMSS), DICONSA, relief activities (Red Cross), family services (DIF), police (SSM), military (SEDENA and SEMAR) and civil protection (Civil Protection), as well as the Mexican National Institute of Statistics and Geography (INEGI).

Information about suppliers, facilities and costs was collected from DICONSA. SINAPROC provided data about demand, relief distributed and emergency declarations. Geographical information was obtained from INEGI. Regulations from FONDEN were used to gather the characteristics of the different relief items considered. Transparency websites from the Mexican government were used to gather information about budgets and wages, whereas SEDENA provided information about the number of employees required for distribution. Each organization provided information about their employees and vehicles available, including their characteristics. The information can be classified into five categories: demand areas, procurement and relief, relief agencies, distribution network, scenario development.

Demand areas

The regions were obtained from emergency declarations made by the Mexican government including the period from September 16th to September 30th of 2013. The areas were clustered, based on their geographical location, into three regions shown in Table 4.

Table 4.

Regions affected by Hurricanes Ingrid, Manuel and heavy rainfall

States (Southwest/center) Affected people States (East) Affected people States (Northwest) Affected people
Guerrero 238,028 San Luis Potosí 46,926 Colima 15,523
Oaxaca 13,618 Nuevo León 3,663 Jalisco 31,598
Chiapas 15,746 Quintana Roo 14,263 Zacatecas 11,001
Morelos 4014 Tamaulipas 29,958 Chihuahua 60,250
Michoacán 49,368 Veracruz 7,555 Nayarit 9,762
Sinaloa 18,497

Source Compiled by author with information from SEGOB

The summarized demand can be seen in Table 13 in Appendix.

Table 13.

Aggregated demand

Disaster Scenario Demand area
A1 A2 A3 A4 A5 A6
R1 S1 818,224 46,816 54,131 13,805 169,708 0
R1 S2 818,224 46,816 54,131 13,805 169,708 0
R1 S3 818,224 46,816 54,131 13,805 169,708 0
R1 S4 818,224 46,816 54,131 13,805 169,708 0
R1 S5 818,224 46,816 54,131 13,805 169,708 0
R1 S6 818,224 46,816 54,131 13,805 169,708 0
R1 S7 818,224 46,816 54,131 13,805 169,708 0
R1 S8 818,224 46,816 54,131 13,805 169,708 0
R1 S9 654,577 37,455 43,307 11,044 135,762 0
R1 S10 654,577 37,455 43,307 11,044 135,762 0
R1 S11 654,577 37,455 43,307 11,044 135,762 0
R1 S12 654,577 37,455 43,307 11,044 135,762 0
R1 S13 654,577 37,455 43,307 11,044 135,762 0
R1 S14 654,577 37,455 43,307 11,044 135,762 0
R1 S15 654,577 37,455 43,307 11,044 135,762 0
R1 S16 654,577 37,455 43,307 11,044 135,762 0
R1 S17 0 0 0 0 0 0
R1 S18 0 0 0 0 0 0
R1 S19 0 0 0 0 0 0
R1 S20 0 0 0 0 0 0
R2 S1 161,315 12,595 49,038 102,993 25,971 0
R2 S2 161,315 12,595 49,038 102,993 25,971 0
R2 S3 161,315 12,595 49,038 102,993 25,971 0
R2 S4 129,052 10,076 39,226 82,390 20,779 0
R2 S5 129,052 10,076 39,226 82,390 20,779 0
R2 S6 129,052 10,076 39,226 82,390 20,779 0
R2 S7 0 0 0 0 0 0
R2 S8 0 0 0 0 0 0
R2 S9 161,315 12,595 49,038 102,993 25,971 0
R2 S10 161,315 12,595 49,038 102,993 25,971 0
R2 S11 161,315 12,595 49,038 102,993 25,971 0
R2 S12 129,052 10,076 39,226 82,390 20,779 0
R2 S13 129,052 10,076 39,226 82,390 20,779 0
R2 S14 129,052 10,076 39,226 82,390 20,779 0
R2 S15 0 0 0 0 0 0
R2 S16 0 0 0 0 0 0
R2 S17 161,315 12,595 49,038 102,993 25,971 0
R2 S18 161,315 12,595 49,038 102,993 25,971 0
R2 S19 129,052 10,076 39,226 82,390 20,779 0
R2 S20 129,052 10,076 39,226 82,390 20,779 0
R3 S1 53,372 108,625 37,829 207,119 33,572 63,602
R3 S2 42,691 86,900 30,261 165,693 26,851 50,875
R3 S3 0 0 0 0 0 0
R3 S4 53,372 108,625 37,829 207,119 33,572 63,602
R3 S5 42,691 86,900 30,261 165,693 26,851 50,875
R3 S6 0 0 0 0 0 0
R3 S7 53,372 108,625 37,829 207,119 33,572 63,602
R3 S8 42,691 86,900 30,261 165,693 26,851 50,875
R3 S9 53,372 108,625 37,829 207,119 33,572 63,602
R3 S10 42,691 86,900 30,261 165,693 26,851 50,875
R3 S11 0 0 0 0 0 0
R3 S12 53,372 108,625 37,829 207,119 33,572 63,602
R3 S13 42,691 86,900 30,261 165,693 26,851 50,875
R3 S14 0 0 0 0 0 0
R3 S15 53,372 108,625 37,829 207,119 33,572 63,602
R3 S16 42,691 86,900 30,261 165,693 26,851 50,875
R3 S17 53,372 108,625 37,829 207,119 33,572 63,602
R3 S18 42,691 86,900 30,261 165,693 26,851 50,875
R3 S19 53,372 108,625 37,829 207,119 33,572 63,602
R3 S20 42,691 86,900 30,261 165,693 26,851 50,875

Procurement and relief

The 39 suppliers that have participated in previous disasters were incorporated into the analysis. The cost per relief item per supplier at stage one was obtained from records of previous purchases, while the cost of purchase at stage two was assumed to be 20% more expensive. The cost of partnering with a supplier during disaster relief was assumed based on the frequency of participation in previous disasters as the information was privileged. Minimum order size was assumed to be only 1% of the supply capacity of the organization and procurement budget was obtained from reports from previous disasters (SEGOB 2008). Table 5 introduces the characteristics of the suppliers incorporated in the analysis, which include the variety of relief items offered and supplier size.

Table 5.

Characteristics of the suppliers analyzed

ID Products Size ID Products Size ID Products Size
1 4 Large 14 1 Medium 27 1 Medium
2 1 Medium 15 1 Medium 28 1 Medium
3 1 Small 16 1 Medium 29 1 Medium
4 1 Medium 17 1 Medium 30 1 Small
5 1 Medium 18 1 Medium 31 1 Medium
6 1 Medium 19 1 Large 32 1 Large
7 2 Large 20 1 Small 33 1 Large
8 2 Small 21 1 Medium 34 1 Large
9 1 Medium 22 2 Large 35 1 Large
10 1 Medium 23 3 Large 36 1 Large
11 1 Large 24 1 Large 37 1 Large
12 1 Large 25 1 Medium 38 1 Medium
13 1 Medium 26 2 Small 39 1 Medium

Source Compiled by author with information from DICONSA

The relief items are the components of the food kit distributed by authorities in disasters for four people for four days (SEGOB 2012).

Relief agencies

Human and material resources available for disaster response were collected from FOI requests, transparency websites and reports from Red Cross. Table 6 shows the eight organizations that acknowledged participating in operational activities during the disaster, their personnel available, their wages and their vehicles available. The vehicles included were assumed to have a capacity of 2 tons.

Table 6.

Resources of the organizations included

Organization Staff (people) Vehicles (truck) Wages (MXN) Organization Staff (people) Vehicles (truck) Wages (MXN)
DICONSA 54 22 62,330 Red Cross 72 185 56,410
DIF 72 11 65,283 SEDENA 502 182 644,300
IMSS 30 0 23,504 SEMAR 1324 41 1,699,310
Civil Protection 28 4 21,937 SSM 65 0 50,926

Source Compiled by author with information from each organization

Distribution network

The facilities used were obtained from DICONSA, geo-referenced and identified using Google Earth®, and they were located in the network of the country using TransCAD® as shown in Fig. 1.

Fig. 1.

Fig. 1

Location of potential supply facilities

Similarly, supplier warehouses were mapped using layers from INEGI with TransCAD®. The main supplier warehouses were used because these facilities were expected to be used to consolidate the volume of relief items required. Network analysis was performed to calculate distances between facilities, which were used to estimate transportation costs using fuel requirements.

Scenario development

The scenarios were based on information of the disasters affecting Mexico in September 2013. The simultaneous impact of Hurricane Ingrid, Hurricane Manuel, and heavy rainfall was reflected in the emergency declarations of Mexico from September 16th until the end of the month.

The potential scenarios were planned considering three hazards with different impact on different regions. Three levels of impact were included: regular impact (based on emergency declarations of the disasters from FONDEN (2013)), increased impact (increase of 25% over the recorded demand), and null impact (to account for the uncertainty of the hazard causing damage to the region). The probability of the scenarios was based on historical information. The variation of the impact of disaster for the development of scenarios has been used in past papers See Falasca and Zobel (2011), Balcik and Ak (2014). Using the database EM-DAT (EM-DAT 2021), a list of 149 disasters from 2000 to 2020 was included in the analysis. The list was filtered to include disasters that occurred and ended on the same months. That resulted in a total of 31 situations with 2 or more hazards affecting the country. The frequency of damage on the different regions was used to identify the probability of occurrence of disasters in each region shown in Table 2. Using the different combinations of impact on each scenario, normalizing the probabilities, and weighting them depending on the relative probability of occurrence of two (67.7%) or three simultaneous hazards (32.3%) obtained from the frequency from historical data, the final probabilities obtained are shown in Table 7.

Table 7.

Scenarios tested

Scenario R1 R2 R3 Probability Scenario R1 R2 R3 Probability
S1 I I I 0.005040 S11 R I N 0.056077
S2 I I R 0.015121 S12 R R I 0.045363
S3 I I N 0.018692 S13 R R R 0.136089
S4 I R I 0.015121 S14 R R N 0.168231
S5 I R R 0.045363 S15 R N I 0.047484
S6 I R N 0.056077 S16 R N R 0.142453
S7 I N I 0.015828 S17 N I I 0.007818
S8 I N R 0.047484 S18 N I R 0.023455
S9 R I I 0.015121 S19 N R I 0.023455
S10 R I R 0.045363 S20 N R R 0.070364

I Increased, R Regular, N None

Analysis of results

Results of the case study

The model introduced was programmed on GAMS 23.5.1® using the ε-constraint method with the COST objective function turned into a constraint. The model was solved using Cplex® for 100 iterations. The stopping criterion was a relative optimality gap smaller than 0.1 or after 14,400 s (Kappes et al. 2012; Chang et al. 2011). The software returned a total of 21 non-dominated solutions, i.e., solutions which are not improved in both cost and shortage level by any other solution in the feasible space. The solutions can be seen in Fig. 2, which shows the trade-off between both objective functions. Each one of the non-dominated solutions includes an entire policy to manage procurement, facility location, resource allocation, and relief distribution.

Fig. 2.

Fig. 2

Pareto frontier of the case study

Table 8 introduces a summary of the policies suggested by the optimization model. The importance of considering the resources required is noticeable in the table. As more employees are deployed for managing and delivering relief items, more items can be procured for delivery to victims. This highlights the importance of considering the interaction between human and material resources in disaster management models to augment decision-making, which is a dimension often overlooked in the literature. Another important finding is that the number of organizations deployed rely on the resources available and the level of service provided. This affects the complexity of the relief network and management of scarce resources.

Table 8.

Summary of results of the non-dominated solutions

ID Cost Shortage Supply facilities Agencies Suppliers Employees used (Max) Items procured (Max) Trips (Max)
ND1 320,999.99 554,862 2 2 1 83 94,901 16
ND2 641,999.98 534,616 2 3 2 143 195,852 27
ND3 962,999.98 502,430 2 3 2 143 197,295 28
ND4 1,283,999.96 488,456 2 4 3 188 292,287 31
ND5 1,605,000.00 468,264 5 4 4 168 302,186 28
ND6 1,925,999.99 443,838 4 4 4 188 330,967 36
ND7 2,567,999.98 437,426 12 5 6 242 427,547 37
ND8 4,172,999.97 367,664 11 6 6 631 564,082 119
ND9 5,456,950.40 363,276 17 4 7 1268 730,225 204
ND10 5,777,999.99 318,826 16 5 8 1291 694,560 204
ND11 6,741,000.00 315,014 18 4 8 1268 712,383 201
ND12 7,382,999.94 280,943 19 4 9 1268 752,032 207
ND13 7,703,999.98 268,023 18 4 9 1268 769,556 213
ND14 9,950,999.94 250,630 22 7 11 1763 960,109 310
ND15 12,518,999.99 199,142 27 7 14 1734 1,103,904 319
ND16 13,481,999.95 184,458 24 7 17 1763 1,198,847 324
ND17 14,184,320.02 176,136 30 8 25 1788 1,107,477 325
ND18 17,333,999.98 172,548 20 5 16 1686 1,265,192 321
ND19 17,975,999.67 171,545 26 8 20 1788 1,152,713 298
ND20 19,237,919.48 140,320 31 8 28 1788 1,203,903 325
ND21 19,867,589.33 134,592 31 8 27 1788 1,335,910 325

The different combinations found in the solutions show the way the model balance different decisions. For instance, ND17 and ND18 have different balances of pre-disaster and post-disaster procurement. ND17 has the largest number of items acquired at the second stage (over 90% of relief in that solution), whereas ND18 has the largest number of items procured prior to the disaster of all the non-dominated points (914,322). The former increases procurement cost but reduces transportation cost, as opposed to ND18. Service-oriented solutions require the involvement of more agencies, facilities, and suppliers, as expected. Overall, it would be complicated to satisfy the needs of the different disasters with the resources available, as the model was unable to provide solutions without shortage.

The model selected suppliers based on the demand, supplier characteristics and overall supply capacity. None of the solutions included all the suppliers available, showing preferences for some of them. Most solutions selected suppliers located toward the center of the country such as 4, 7, 29, and 33. The general frequency can be seen in Fig. 3.

Fig. 3.

Fig. 3

Frequency of selection of the facilities to serve as distribution centers

Figure 4 shows the opening frequency of each one of the facilities included in the analysis. Facilities in Chilpancingo, Zacatecas, and Veracruz are commonly opened in the results, with the facility in Zacatecas being opened in every single solution except for ND3. On the other hand, facilities in La Paz and Quintana Roo are never opened, whereas facilities in Mixteca and Hermosillo are opened just in a couple of the solutions. Given the distribution of the three regions affected the model supports the selection of facilities in the center of Mexico rather than facilities on the edges of the country.

Fig. 4.

Fig. 4

Frequency of selection of the facilities to serve as distribution centers

Figure 5 shows the percentage of activation of the agencies in the non-dominated solutions. The Red Cross, family services, DICONSA, and civil protection are activated in most of the solutions because of the combination of resources they bring to the field. Despite its cost, SEMAR is consistently selected on all the service-oriented solutions because of the large number of employees that can be allocated to relief activities.

Fig. 5.

Fig. 5

Frequency of deployment of the agencies

There are some interesting results in the second-stage variables as well. The restriction in the number of employees available forces the model to balance resources between distribution centers and relief distribution as shown in Fig. 6. The picture across all non-dominated solutions shows preference for using staff for relief distribution in most of the scenarios except for scenarios 17, 18, 19, and 20. Interestingly, in those scenarios, only regions two and three are affected, both of which have less demand than region one. When there is a disaster in the latter, the model focuses on using staff for distribution to facilitate reaching the affected people, whereas in the former less trips are required and more staff can be allocated to distribution centers to manage relief.

Fig. 6.

Fig. 6

Total trips and personnel allocated across solutions

The magnitude of delivery to each region can be seen in Fig. 7. It shows the average and maximum number of items sent per region on every solution. Evidently, demand on region 1 represents a significant proportion of the overall demand and the need for deliveries. Additionally, the difference between the average and maximum number of items send shows the range of variation across scenarios.

Fig. 7.

Fig. 7

Maximum and average relief sent per solution

That range is reflected on the number of items procured at the second stage as well with a significant variation across scenarios as shown in Fig. 8.

Fig. 8.

Fig. 8

Average and maximum number of items procured per scenario

Value of the stochastic solution

The use of a two-stage stochastic approach is based on its benefits to provide reliable solutions considering the conditions of disaster management operations. This approach is commonly evaluated using deterministic approaches such as the Expected Value of Perfect Information (EVPI) and the Value of the Stochastic Solution (VSS). These measures are used to explore the performance of the results of the model using the results of the recourse problem (RP). This section presents the results of the EVPI and VSS analysis.

EVPI is based on the idea of having accurate information about the situation, which in this case involves knowledge about the surge in demand caused by the different hazards. Assuming the availability of perfect information, it is possible to solve one optimization model for each scenario. The Wait-and-See (WS) solution is obtained by aggregating the expectation of all the scenarios given by zWS=sSπszsWS (Rodríguez-Espíndola et al. 2020). Hence, in this article 20 deterministic problems are solved for each epsilon value, weighted by their probability, and aggregated to obtain the WS value. EVPI is calculated with those values using the expression EVPI=zRP-zWS (Birge 1982).

The expected value problem (EV) is obtained when the stochastic parameters are replaced by their average values of to simplify the analysis. The problem becomes easier to solve, but the probability and information from the different scenarios is neglected. To evaluate the use of the EV solution, VSS is calculated (Rodríguez-Espíndola et al. 2020). The first-stage variables are pre-fixed using the results from the EV solution, and the simplified problem is solved to obtain the expected value of using the EV solution (EEV). VSS can be calculated using the expression VSS=zEEV-zRP (Birge 1982). Table 9 shows the summary of the results of the analysis.

Table 9.

Analysis of the stochastic value of the solutions

Solution RP* WS** EVPI EV EEV*** VSS
ND1 554,862 553,964 898 475,169 592,041 37,179
ND2 534,616 524,985 9631 475,169 592,041 57,425
ND3 502,430 499,122 3307 475,169 592,041 89,612
ND4 488,456 476,062 12,394 475,169 592,041 103,585
ND5 468,264 455,683 12,581 475,169 592,041 123,778
ND6 443,838 437,384 6453 475,169 592,041 148,204
ND7 437,426 410,651 26,775 357,117 592,041 154,615
ND8 367,664 324,965 42,700 338,154 592,041 224,377
ND9 363,276 286,612 76,664 250,113 459,517 96,241
ND10 318,826 269,890 48,937 239,041 445,858 127,032
ND11 315,014 231,158 83,856 207,427 381,993 66,980
ND12 280,943 213,634 67,310 194,497 352,381 71,438
ND13 268,023 205,404 62,619 174,431 324,949 56,927
ND14 250,630 145,985 104,645 118,105 242,295
ND15 199,142 113,363 85,778 96,323 199,486 345
ND16 184,458 104,998 79,460 85,014 182,247
ND17 176,136 59,302 116,834 56,490 98,672
ND18 172,548 77,359 95,190 66,230 134,297
ND19 171,545 73,166 98,379 62,483 133,523
ND20 140,320 59,133 81,187 56,490 98,666
ND21 134,592 59,328 75,264 53,585 82,226
Average 322,524 265,817 56,708 247,929 374,878 96,981
Minimum 134,592 59,133 898 53,585 82,226 345
Maximum 554,862 553,964 116,834 475,169 592,041 224,377

*Average optimality gap of 25.93%, **Average optimality gap of 0.75%, ***Average optimality gap of 19.61%

The objective was to minimize the shortage of products to reduce suffering. The EVPI values show that randomness plays an important role in the problem. The availability of perfect information would allow us to deliver over 56 thousand products in average. In the best-case scenario, perfect information would allow us to deliver 898 more items, whereas in the worst-case scenario that figure increases dramatically to 116,834. It is possible to notice that in most instances EEV values are higher that RP values. That is because using the EV solution prevents from minimizing shortage based on the value of each random variable. The results of the VSS show significant variation between the average (96,981), worst-case (224,377) and best-case scenario (345). The reason some EEV values go below the RP values is related to the optimality gap. In instances where the difference between the optimality gap of the RP problem and the optimality gap of the EEV problem was 12.4% or higher, that behavior was observed. That suggests the need to develop algorithms that can reduce the optimality gap in sensible solution times. Overall, the analysis shows that uncertainty is an important factor in the problem.

Results of the independent analysis of simultaneous disasters

Most models in the literature consider single disasters managed by a single organization, which ignores the challenges associated with having multiple agencies involved in different events. The case study presented in Sect. 4 is used to compare the performance of the model proposed with situations considering independent decision-making for each disaster.

The underpinning assumption in several disaster management models is that there is a focal disaster requiring all the support. That assumption can tempt regional civil protection authorities to produce plans looking at single disasters. Planning for each disaster independently, without considering other events, can affect the availability of resources that need to be shared. To explore those challenges, the first experiment is assuming each one of the hazards is planned for and managed independently. In the same way, all the resources are available to support in the focal disaster when authorities assume the occurrence of a single disaster, the first experiment involved creating one model for each disaster (using the demand of that region alone) and solving it under the assumption that all the resources are available. One model per region was solved for 50 iterations under the same conditions as the original model for comparability. The results of the three models were aggregated and are presented in Table 10, which shows the solutions obtained. Looking at the maximum number of employees available per scenario, there were only six feasible solutions requiring less employees than the number currently available (i.e., 1778). The reason is because the needs of the other events are not considered, which can complicate sharing resources. In reality, that would translate in requests for resources that would be denied because of the prior depletion of resources, or the sub-optimal split of resources. The feasible solutions are dominated by solutions from the model. For instance, solution R6 (the feasible solution with the lowest level of shortage) has nearly twice as many shortage as solution ND21 from Table 8. The reason is because the results are focusing on local optimums.

Table 10.

Details of the solutions from the aggregated planning of independent disasters

ID Cost Shortage Supply facilities Agencies Suppliers Max Employees available Maximum trips
R1 1,461,000 498,327 4 2 2 226 41
R2 2,922,000 432,582 7 3 5 406 74
R3 4,379,138 398,316 11 5 7 749 93
R4 5,844,000 340,642 9 6 9 1078 188
R5 7,304,999 318,282 11 6 12 1101 174
R6 8,765,999 265,749 11 5 15 1482 271
R7 11,688,000 253,010 15 7 15 2926 299
R8 13,140,810 209,382 11 4 14 2672 376
R9 14,610,000 173,982 22 7 19 2260 404
R10 17,532,000 145,501 27 8 24 2334 427
R11 18,992,999 117,026 13 5 16 3477 462
R12 20,453,999 101,271 17 5 17 3565 462
R13 23,375,734 79,451 26 3 20 3750 521
R14 24,795,579 68,816 27 6 19 3915 569
R15 27,705,017 59,148 29 8 24 4062 552
R16 29,213,981 58,653 31 8 29 4623 669
R17 30,678,135 50,940 30 8 35 4205 577
R18 32,129,358 46,714 30 8 35 4996 825
R19 33,601,645 43,056 30 8 38 4677 600
R20 36,519,176 35,624 30 8 39 5117 835
R21 38,428,723 28,085 31 8 39 5132 820
R22 39,674,911 22,485 31 8 39 5202 951
R23 40,600,826 16,631 31 8 39 5132 948
R24 41,557,575 12,423 31 8 39 5155 950
R25 44,976,049 11,338 31 8 39 5339 959
R26 48,051,764 10,218 31 8 39 5260 971

For further analysis, it is possible to look at a combination between integrated planning and independent response. This combination would allow collaborative planning to define the relief network considering the possibility of having multiple disasters but managing the response looking at the needs of individual local authorities. This can be achieved by solving the integrated model first to fix the results of the first-stage variables and then solving one model for each region to determine the value of the second-stage variables. That way, the same relief network is used to optimize independent second-stage decisions. The results of the analysis are shown in Table 11. The findings show that as each hazard is being handled independently at the second stage, several solutions become unfeasible because of the competition for resources (i.e., employees). The reason is because this approach can generate duplication of efforts on the second stage, and it is not considering the links between regions.

Table 11.

Solutions of the combination of integrated planning and independent response

Sol Cost Shortage Supply facilities Agencies Suppliers Max employees Max products purchased Maximum trips
ID1 0 592,042 0 0 0 0 0 0
ID2 3,433,967 455,961 7 4 3 657 272,664 69
ID3 10,329,225 378,282 17 4 4 3804 735,556 247
ID4 9,233,939 324,656 30 6 9 4041 893,540 478
ID5 12,481,346 270,992 18 4 6 3804 1,098,791 516
ID6 13,195,849 212,802 18 4 7 3804 1,187,284 553
ID7 20,907,317 174,835 30 7 15 5295 1,273,129 447
ID8 26,141,978 143,213 19 5 10 3879 1,332,622 553
ID9 31,715,539 89,802 30 7 27 5295 1,437,356 700
ID10 42,630,053 41,360 20 6 12 3948 1,571,201 490

As the solutions above would be difficult to use in practice, the next test was to allocate a part of the resources a priori to each area for comparison. Each disaster was assumed to be independent, but the split of resources was made before any decisions were defined. As each disaster is considered as an independent event, one model is solved for each disaster. Assuming that each disaster was equally important for authorities, each region was allocated a third of the resources including budget, vehicles, human resources, and quantity of relief items that could be obtained from suppliers. The comparison between the Pareto front of the model and the results of splitting results a priory for independent disasters can be seen in Fig. 9. It is possible to notice that the difference between both frontiers increases in more service-oriented solutions. The use of independent relief networks implies added cost and extra use of resources for operations looking to satisfy the demand as much as possible.

Fig. 9.

Fig. 9

Comparison of the Pareto front between the results of the model and independent disasters

Table 12 shows the comparison between the solution with lowest shortage in the model and the solution with lowest shortage from independent operations. The results show a consistent need for more complex relief networks requiring more suppliers and resources. As each one of the disasters was managed separately in the second instance, resources were allocated to satisfy local needs rather than taking advantage of pooling and sharing resources and facilities, which can provide advantages for operations (Balcik et al. 2019).

Table 12.

Comparison of the solutions with minimum expected shortage

Solution Cost Shortage Facilities Agencies deployed Suppliers used Max employees available Max trips
Model 19,867,589.33 134,592 31 8 27 1788 325
Independent 34,759,519.33 187,890 31 8 39 1788 323

Figure 10 represents shortage across regions and the contrast of cost between both solutions. The three regions were affected by disasters of different magnitude, where region one was the most affected. In the policy proposed by the model, although more than half of the shortage was suffered at region one, the model balances the resources to have levels of 22% of shortage in disaster two, and 23% in disasters one and three. In contrast, independent decision-making worked very well with lower levels of demand, achieving less than 3% and a little over 8% of shortage in regions two and three, respectively. Nevertheless, an expected level of shortage of nearly 48% for region one is troublesome for the most affected area. In summary, the effect of neglecting to consider the occurrence of simultaneous disasters in different areas includes the inability to reach better solutions, the potential to overestimate the resources available and the tendency to increase the number of stakeholders.

Fig. 10.

Fig. 10

Comparison of the levels of expected shortage per region between the results from the model and planning considering independent disasters

Overall, the results show a good level of performance of the model balancing resources for higher and lower levels of demand, trying to use them according to the magnitude, something that is not easily achievable with independent decision-making.

Sensitivity analysis

This article argues that humanitarian logistics formulations need to incorporate human resources because these affect operations performance in practice. To further understand the effect of that component, a sensitivity analysis is included to discuss its impact using the number of employees to show the effect of varying the level of staff on the performance of the system. Figure 11 shows the changes in the value of the minimization of shortage of items when more employees are made available.

Fig. 11.

Fig. 11

Levels of shortage with extra employees

The availability of extra staff has an impact in the level of shortage, as evidenced by the potential reduction in more than half of shortage when human resources are increased by 90% compared to the current situation. This result highlights that human resources are one of the critical factors that can affect the delivery of relief to disaster areas, a dimension commonly overlooked in the literature. In simultaneous disasters, the decision about the allocation of staff evolves from establishing who to send, to determine where to send them as well.

Discussion

Findings

This article proposes a formulation integrating multiple suppliers, multiple agencies and simultaneous disasters, an area currently understudied. The bi-objective model provides support for decision-making for logistics activities in settings with stochastic demand capable of optimizing the number of agencies deployed to reduce supply congestion in an environment subject to simultaneous disasters.

Planning for simultaneous disasters requires sharing suppliers, resources, and facilities. There is evidence of the benefits of sharing resources among multiple stakeholders (Balcik et al. 2019). The same concept applies for sharing resources among affected regions and crises. The effect that simultaneous disasters have on each other includes the need to share the same pot of resources among different events (Kappes et al. 2012), which effectively means response capabilities for each individual situation are reduced. The relief network needs to be carefully coordinated to allow authorities to stretch their resources to provide assistance in these instances. However, current formulations tend to neglect the inclusion of resources such as vehicles and staff (Rodríguez-Espíndola et al. 2018a). The results from the case study and the sensitivity analysis show the impact human resources can have on disaster operations, especially for developing countries with constrained resources (Julca 2012), such as the case of Mexico.

Supplier selection is a complex endeavor because of the need to balance coverage, supply capacity, delivery times, supply arrangements, and available resources (Aghajani et al. 2020). This is further complicated in simultaneous disasters because the importance of delivery times can promote the use of suppliers closer to one disaster area rather than supplier selection based on a holistic view of the situation across disasters. Additionally, competition for resources (e.g., relief items, vehicles) from different agencies might cause shortages (Balcik and Ak 2014). The results of this research agrees with previous research underscoring the importance of partnerships and agreements with suppliers for disaster response (Wang et al. 2019). Findings suggest that selecting suppliers with more reach and which are better located can be advantageous over multiple localized suppliers for disasters in areas largely separated. Similarly, larger facilities strategically located can be critical to reach different areas and simplify the relief network, leading to lower cost and better service when simultaneous events are considered. This was evident in the comparison between the results of the model and independent response, where it was possible to see the drawbacks of independent decision-making at the planning and response stages.

There is an interesting dynamic captured by the model that would not be evident in current models in the literature. In simultaneous events, resource management becomes a major concern (Doan and Shaw 2019) given varying magnitudes and the need to distribute resources among distinct disaster areas. Opening more facilities and procuring more items requires more investment, and it is more resource intensive as well. Nevertheless, results suggest that vehicles are not a major constraint in the case. The maximum number of trips required by the model was lower than the number of trips that could be done by vehicles available to the agencies deployed. Conversely, the challenge for decision-makers was the availability of human resources. Even when every agency was deployed, there was a shortage of employees for operational activities. On the other hand, the potential of the model to optimize the agencies deployed showed the possibility of reducing the number of participants involved in several solutions in case the decision-maker has more constraints in terms of jurisdiction or operational deployment. The Pareto frontier from the case shows the possibility of obtaining “acceptable” results with less agencies deployed, and the way the number and type of agencies involved should be decided based on their resources, the priorities from decision-makers, and the characteristics of the disasters. Overall, the results of the analysis provide evidence of the potential of the formulation proposed to manage multiple resources from different agencies accounting for the occurrence of simultaneous disasters.

Practical implications

The formulation proposed can serve as basis to inform disaster managers in countries similar to Mexico. The analysis of the case presented provides a set of implications for managers, such as:

  • Planning for simultaneous disasters provides clearer understanding of the real capabilities of the disaster management system and its limitations. It can avoid a false sense of security about resources available coming from the narrow perspective of single independent disasters.

  • Efficient operations require accounting for the characteristics, requirements, and priority of the disaster(s) to leverage the interaction of different stakeholders.

  • Relief delivery must look at the combination of human and material resources. Neglecting to consider any of them can lead to wasted or insufficient resources.

  • Agency deployment requires planning. The deployment of participants must be based on the situation(s) and requirements to avoid overcrowding and duplication of efforts, as human resources have a direct impact on the capabilities of the system and its performance.

Conclusions and future research

Despite the growing literature in humanitarian logistics, only a handful of articles are looking at the possibility of simultaneous disasters. This paper introduces a novel formulation incorporating the participation of multiple agencies and suppliers for the delivery of relief to disaster victims in multiple regions affected simultaneously, an approach never undertaken before. Although there are formulations emphasizing the importance of multiple suppliers or multiple participants, this is the first formulation integrating multiple suppliers, multiple agencies, and simultaneous disasters in the same model. The application to a case study in Mexico showed the capacity of the model to provide support, tailoring the response based on the scale of the disasters.

The ideas and rationale from this model can be used as the foundation for the development of new holistic decision-support systems integrating different logistics decisions in such a complex environment. Additionally, the results of the case study show the importance of considering suppliers, human resources, and critical facilities to achieve a satisfactory level of service for the victims. Disaster managers can benefit from this research through a well-defined disaster management structure and the impact of supplier selection and management. Aligned with current practices from countries such as the USA, practitioners can use this research to justify the analysis of simultaneous disasters as part of standard practice to have more robust disaster management systems.

Solving the model in a few hours because of the use of discrete variable is feasible at the preparedness stage, but it is desirable to reduce solution times through the development of heuristic algorithms in future work. The model introduced in this article provides support for decisions at the planning stage looking at participant, supplier, and facility selection; thus, it could be coupled with models for logistics decisions to provide integrated support for disaster response for multiple periods. In fact, the development of a dynamic model for multiple disasters to support disaster preparedness and response could help managing subsequent, compound, and simultaneous disasters. Given the uncertainty of simultaneous disasters, new formulations should explore the impact of stochastic supply. This article has shown the importance of looking at human resources for relief operations and the next step should consider incorporating uncertainty in the availability of these resources. The integration of technology with operational research is another interesting stream of research.

Appendix

Data description

The model includes information available to the stakeholders involved which is shared with the umbrella organization. These parameters can be clustered in six groups:

  • Procurement data The type of relief items deployed and their characteristics exist in the list of relief items authorized by authorities and from agreements with suppliers. Procurement costs (prior and after the disaster), partnership cost, minimum order sizes and supply capacity can also be obtained from agreements with contracted suppliers. The procurement budget can be obtained from disaster budgets facilitated by federal, regional or local governments.

  • Facility data Volumetric capacity of the facilities is information available in the list of pre-selected facilities developed by authorities. Facility costs include all preparations required for the use of the facility (e.g., cleaning, equipment required) and can be obtained from previous reports. Number of employees required per facility is information handled by authorities, usually stating the number of people required to handle a facility of a certain size. From that information, the space covered per employee can be estimated.

  • Agency data Costs of involving agencies are associated with wages recorded by them and can be obtained from them or through transparency websites. Availability of resources, such as employees and vehicles, can be obtained from their records as well.

  • Transportation data The cost of transporting relief items can be obtained from direct costs (fuel and vehicle depreciation) using the specification of the vehicles distances. The number of employees required for transportation is information handled by authorities, usually stating the number of people required to make relief distribution trips per vehicle. The capacity of each vehicle can be obtained from the specifications of each type of vehicle.

  • Adjusted parameters These parameters rely on the guidelines of each decision-maker and their preferences. The coverage of suppliers to facilities depends on time/distance constraints based on the location of the disaster and agreed lead-times. Analysis with GIS can be performed on routes based on the guidelines of the agencies. The number of trips per day relies on the preferred distances of coverage, lead times and working conditions determined by the decision-maker.

  • Scenario-dependent parameters These parameters rely on the characteristics of the scenarios analyzed, which are decided by authorities based on historical information and forecasting. Relief demand and the probability of the scenarios can be forecasted or obtained from previous reports. Priority of each disaster area per scenario is a parameter that can be adjusted by the decision-maker based on the characteristics and magnitude of the scenario to balance the use of resources among different regions. Simultaneous disasters differ in nature and intensity (Kappes et al. 2012). Hence, this parameter allows the prioritization of the use of resources to provide further support to the most heavily affected regions.

Case study demand

See Table 13.

Footnotes

Publisher's Note

Springer Nature remains neutral with regard to jurisdictional claims in published maps and institutional affiliations.

References

  1. Abounacer R, Rekik M, Renaud J. An exact solution approach for multi-objective location-transportation problem for disaster response. Comput Oper Res. 2014;41:83–93. doi: 10.1016/j.cor.2013.08.001. [DOI] [Google Scholar]
  2. Abualkhair H, Lodree EJ, Davis LB. Managing volunteer convergence at disaster relief centers. Int J Prod Econ. 2020;220:107399. doi: 10.1016/j.ijpe.2019.05.018. [DOI] [Google Scholar]
  3. Aghajani M, Torabi SA, Heydari J. A novel option contract integrated with supplier selection and inventory prepositioning for humanitarian relief supply chains. Socio-Econ Plan Sci. 2020;71:100780. doi: 10.1016/j.seps.2019.100780. [DOI] [Google Scholar]
  4. Akhtar P, Marr NE, Garnevska EV. Coordination in humanitarian relief chains: chain coordinators. J Hum Logist Supply Chain Manag. 2012;2:85–103. doi: 10.1108/20426741211226019. [DOI] [Google Scholar]
  5. Alem D, Clark A, Moreno A. Stochastic network models for logistics planning in disaster relief. Eur J Oper Res. 2016;255:187–206. doi: 10.1016/j.ejor.2016.04.041. [DOI] [Google Scholar]
  6. Alem D, Bonilla-Londono HF, Barbosa-Povoa AP, Relvas S, Ferreira D, Moreno A. Building disaster preparedness and response capacity in humanitarian supply chains using the Social Vulnerability Index. Eur J Oper Res. 2021;292:250–275. doi: 10.1016/j.ejor.2020.10.016. [DOI] [Google Scholar]
  7. Alexander D. Evaluation of civil protection programmes, with a case study from Mexico. Disaster Prev Manag Int J. 2015;24:263–283. doi: 10.1108/DPM-12-2014-0268. [DOI] [Google Scholar]
  8. Altay N. Capability-based resource allocation for effective disaster response. IMA J Manag Math. 2013;24:253–266. doi: 10.1093/imaman/dps001. [DOI] [Google Scholar]
  9. Anaya-Arenas AM, Renaud J, Ruiz A. Relief distribution networks: a systematic review. Ann Oper Res. 2014;223:53–79. doi: 10.1007/s10479-014-1581-y. [DOI] [Google Scholar]
  10. Ansell C, Boin A, Keller A. Managing transboundary crises: identifying the building blocks of an effective response system. J Conting Crisis Manag. 2010;18:195–207. doi: 10.1111/j.1468-5973.2010.00620.x. [DOI] [Google Scholar]
  11. Arif A, Wang Z, Chen C, Chen B. A stochastic multi-commodity logistic model for disaster preparation in distribution systems. IEEE Trans Smart Grid. 2020;11:565–576. doi: 10.1109/TSG.2019.2925620. [DOI] [Google Scholar]
  12. Balcik B, Ak D. Supplier selection for framework agreements in humanitarian relief. Prod Oper Manag. 2014;23:1028–1041. doi: 10.1111/poms.12098. [DOI] [Google Scholar]
  13. Balcik B, Beamon BM, Krejci CC, Muramatsu KM, Ramirez M. Coordination in humanitarian relief chains: practices, challenges and opportunities. Int J Prod Econ. 2010;126:22–34. doi: 10.1016/j.ijpe.2009.09.008. [DOI] [Google Scholar]
  14. Balcik B, Silvestri S, Rancourt M-È, Laporte G. Collaborative prepositioning network design for regional disaster response. Prod Oper Manag. 2019;28:2431–2455. doi: 10.1111/poms.13053. [DOI] [Google Scholar]
  15. Beamon BM, Balcik B. Performance measurement in humanitarian relief chains. Int J Public Sect Manag. 2008;21:4–25. doi: 10.1108/09513550810846087. [DOI] [Google Scholar]
  16. Behl A, Dutta P. Humanitarian supply chain management: a thematic literature review and future directions of research. Ann Oper Res. 2019;283:1001–1044. doi: 10.1007/s10479-018-2806-2. [DOI] [Google Scholar]
  17. Besiou M, Stapleton O, Van Wassenhove LN. System dynamics for humanitarian operations. J Hum Logist Supply Chain Manag. 2011;1:78–103. doi: 10.1108/20426741111122420. [DOI] [Google Scholar]
  18. Birge JR. The value of the stochastic solution in stochastic linear programs with fixed recourse. Math Program. 1982;24:314–325. doi: 10.1007/BF01585113. [DOI] [Google Scholar]
  19. Boin A, Lagadec P. Preparing for the future: critical challenges in crisis management. J Conting Crisis Manag. 2000;8:185. doi: 10.1111/1468-5973.00138. [DOI] [Google Scholar]
  20. Briskorn D, Kimms A, Olschok D. Simultaneous planning for disaster road clearance and distribution of relief goods: a basic model and an exact solution method. OR Spectr. 2020;42:591–619. doi: 10.1007/s00291-020-00589-7. [DOI] [Google Scholar]
  21. Celik E, Aydin N, Gumus A. A stochastic location and allocation model for critical items to response large-scale emergencies: a case of Turkey. Int J Optim Control Theor Appl. 2016;7:1–15. doi: 10.11121/ijocta.01.2017.00300. [DOI] [Google Scholar]
  22. Chang MS, Tseng YL, Chen JW. A scenario planning approach for the flood emergency logistics preparation problem under uncertainty. Transp Res Part E Logist Transp Rev. 2007;43:737–754. doi: 10.1016/j.tre.2006.10.013. [DOI] [Google Scholar]
  23. Chang Y, Wilkinson S, Potangaroa R, Seville E. Donor-driven resource procurement for post-disaster reconstruction: Constraints and actions. Habitat Int. 2011;35:199–205. doi: 10.1016/j.habitatint.2010.08.003. [DOI] [Google Scholar]
  24. Charles A, Lauras M. An enterprise modelling approach for better optimisation modelling: application to the humanitarian relief chain coordination problem. OR Spectr. 2011;33:815–841. doi: 10.1007/s00291-011-0255-2. [DOI] [Google Scholar]
  25. Chen C, Ne FY, Sembiring M. Simultaneous disasters in Southeast Asia. Is risk outpacing resilience? S. Rajaratnam School of International Studies; 2018. [Google Scholar]
  26. Chen J, Liang L, Yao D-Q. Pre-positioning of relief inventories: a multi-product newsvendor approach. Int J Prod Res. 2018;56:6294–6313. doi: 10.1080/00207543.2018.1470342. [DOI] [Google Scholar]
  27. Cozzolino A. Humanitarian logistics. Berlin: Springer; 2012. Humanitarian logistics and supply chain management; pp. 5–16. [Google Scholar]
  28. Doan XV, Shaw D. Resource allocation when planning for simultaneous disasters. Eur J Oper Res. 2019;274:687–709. doi: 10.1016/j.ejor.2018.10.015. [DOI] [Google Scholar]
  29. Doerner KF, Gutjahr WJ, Nolz PC. Multi-criteria location planning for public facilities in tsunami-prone coastal areas. OR Spectr. 2009;31:651–678. doi: 10.1007/s00291-008-0126-7. [DOI] [Google Scholar]
  30. Duhamel C, Santos AC, Brasil D, Châtelet E, Birregah B. Connecting a population dynamic model with a multi-period location-allocation problem for post-disaster relief operations. Ann Oper Res. 2016;247:1–21. doi: 10.1007/s10479-015-2104-1. [DOI] [Google Scholar]
  31. Elçi Ö, Noyan N. A chance-constrained two-stage stochastic programming model for humanitarian relief network design. Transp Res Part B Methodol. 2018;108:55–83. doi: 10.1016/j.trb.2017.12.002. [DOI] [Google Scholar]
  32. EM-DAT (2019) Advanced search. http://www.emdat.be/advanced_search/index.html
  33. EM-DAT . Advanced search. Brussels, Belgium: Université Catholique de Louvain; 2021. [Google Scholar]
  34. Falasca M, Zobel CW. A two-stage procurement model for humanitarian relief supply chains. J Hum Logist Supply Chain Manag. 2011;1:151. doi: 10.1108/20426741111188329. [DOI] [Google Scholar]
  35. FEMA (2003) Federal emergency management agency strategic plan fiscal years 2003–2008. p 61
  36. FEMA (2012) Crisis response and disaster resilience 2030: forging strategic action in an age of uncertainty
  37. FONDEN (2013) Insumos autorizados por declaratoria de emergencia 2013. http://www.proteccioncivil.gob.mx/en/ProteccionCivil/2013
  38. Foroughi A, Moghaddam BF, Behzadi MH, Sobhani FM. Developing a bi-objective resilience relief logistic considering operational and disruption risks: a post-earthquake case study in Iran. Environ Sci Pollut Res. 2022;29:56323. doi: 10.1007/s11356-022-18699-w. [DOI] [PubMed] [Google Scholar]
  39. Gonçalves P, Castañeda J. Stockpiling supplies for disaster response: an experimental analysis of prepositioning biases. Prod Plan Control. 2018;42:585–589. [Google Scholar]
  40. Gutjahr WJ, Noyan N, Vandaele N, Van Wassenhove LN. Innovative approaches in humanitarian operations. OR Spectr. 2020;42:585–589. doi: 10.1007/s00291-020-00598-6. [DOI] [PMC free article] [PubMed] [Google Scholar]
  41. Haimes YY. Strategic preparedness for recovery from catastrophic risks to communities and infrastructure systems of systems. Risk Anal. 2012;32:1834–1845. doi: 10.1111/j.1539-6924.2012.01930.x. [DOI] [PubMed] [Google Scholar]
  42. Holguín-Veras J, Jaller M, Wachtendorf T. Comparative performance of alternative humanitarian logistic structures after the Port-au-Prince earthquake: ACEs, PIEs, and CANs. Transp Res Part A Policy Pract. 2012;46:1623–1640. doi: 10.1016/j.tra.2012.08.002. [DOI] [Google Scholar]
  43. Hu S, Dong ZS. Supplier selection and pre-positioning strategy in humanitarian relief. Omega. 2019;83:287–298. doi: 10.1016/j.omega.2018.10.011. [DOI] [Google Scholar]
  44. Hu S-L, Han C-F, Meng L-P. Stochastic optimization for joint decision making of inventory and procurement in humanitarian relief. Comput Ind Eng. 2017;111:39–49. doi: 10.1016/j.cie.2017.06.029. [DOI] [Google Scholar]
  45. Huong NTT, Yen ND. The Pascoletti–Serafini scalarization scheme and linear vector optimization. J Optim Theory Appl. 2014;162:559–576. doi: 10.1007/s10957-013-0294-8. [DOI] [Google Scholar]
  46. Jacob KG, Charles AH. Stochastic game theory: for playing games, not just for doing theory. Proc Natl Acad Sci USA. 1999;96:10564. doi: 10.1073/pnas.96.19.10564. [DOI] [PMC free article] [PubMed] [Google Scholar]
  47. Jensen LM, Hertz S. The coordination roles of relief organisations in humanitarian logistics. Int J Logist Res Appl. 2016;19:465–485. doi: 10.1080/13675567.2015.1124845. [DOI] [Google Scholar]
  48. Jerolleman A, Laska S, Torres J. Lessons from co-occurring disasters: COVID-19 and eight hurricanes. Berlin: Natural Hazards Center, University of Colorado Boulder; 2021. [Google Scholar]
  49. Julca A. Natural disasters with un-natural effects: why? J Econ Issues. 2012;46:499–510. doi: 10.2753/JEI0021-3624460225. [DOI] [Google Scholar]
  50. Kappes MS, Keiler M, von Elverfeldt K, Glade T. Challenges of analyzing multi-hazard risk: a review. Nat Hazards. 2012;64:1925–1958. doi: 10.1007/s11069-012-0294-2. [DOI] [Google Scholar]
  51. Klibi W, Ichoua S, Martel A. Prepositioning emergency supplies to support disaster relief: a case study using stochastic programming. Inf Syst Oper Res. 2018;56:50–81. [Google Scholar]
  52. Lars G. Humanitarian logistics: context and challenges. Forced Migr Rev. 2003;18:6–8. [Google Scholar]
  53. Lei L, Pinedo M, Qi L, Wang S, Yang J. Personnel scheduling and supplies provisioning in emergency relief operations. Ann Oper Res. 2015;235:487–515. doi: 10.1007/s10479-015-1990-6. [DOI] [Google Scholar]
  54. Liu Y, Tian J, Feng G, Hu Z. A relief supplies purchasing model via option contracts. Comput Ind Eng. 2019;137:106009. doi: 10.1016/j.cie.2019.106009. [DOI] [Google Scholar]
  55. Lu C-C, Ying K-C, Chen H-J. Real-time relief distribution in the aftermath of disasters—a rolling horizon approach. Transp Res Part E Logist Transp Rev. 2016;93:1–20. doi: 10.1016/j.tre.2016.05.002. [DOI] [Google Scholar]
  56. McMahon J. Disaster planners face a new normal: simultaneous catastrophes. Chicago: FORBES; 2021. [Google Scholar]
  57. Muggy L, Jessica LHS. Game theory applications in humanitarian operations: a review. J Hum Logist Supply Chain Manag. 2014;4:4–23. doi: 10.1108/JHLSCM-07-2013-0026. [DOI] [Google Scholar]
  58. Nagurney A, Salarpour M, Daniele P. An integrated financial and logistical game theory model for humanitarian organizations with purchasing costs, multiple freight service providers, and budget, capacity, and demand constraints. J Prod Econ. 2019;212:212. doi: 10.1016/j.ijpe.2019.02.006. [DOI] [Google Scholar]
  59. Nazemi N, Parragh SN, Gutjahr WJ. Bi-objective facility location under uncertainty with an application in last-mile disaster relief. Ann Oper Res. 2021;319:1689. doi: 10.1007/s10479-021-04422-4. [DOI] [PMC free article] [PubMed] [Google Scholar]
  60. Nezhadroshan AM, Fathollahi-Fard AM, Hajiaghaei-Keshteli M. A scenario-based possibilistic-stochastic programming approach to address resilient humanitarian logistics considering travel time and resilience levels of facilities. Int J Syst Sci Oper Logist. 2021;8:321–347. [Google Scholar]
  61. Nikkhoo F, Bozorgi-Amiri A, Heydari J. Coordination of relief items procurement in humanitarian logistic based on quantity flexibility contract. Int J Disaster Risk Reduct. 2018;31:331–340. doi: 10.1016/j.ijdrr.2018.05.024. [DOI] [Google Scholar]
  62. Noyan N, Kahvecioğlu G. Stochastic last mile relief network design with resource reallocation. OR Spectr. 2018;40:187–231. doi: 10.1007/s00291-017-0498-7. [DOI] [Google Scholar]
  63. Ordaz M, Salgado-Gálvez M, Huerta B, Rodríguez JC, Avelar C. Considering the impacts of simultaneous perils: the challenges of integrating earthquake and tsunamigenic risk. Disaster Prev Manag Int J. 2019;28:823–837. doi: 10.1108/DPM-09-2019-0295. [DOI] [Google Scholar]
  64. Özdamar L, Ekinci E, Küçükyazici B. Emergency logistics planning in natural disasters. Ann Oper Res. 2004;129:217–245. doi: 10.1023/B:ANOR.0000030690.27939.39. [DOI] [Google Scholar]
  65. Pradhananga R, Mutlu F, Pokharel S, Holguin-Veras J, Seth D. An integrated resource allocation and distribution model for pre-disaster planning. Comput Ind Eng. 2016;91:229–238. doi: 10.1016/j.cie.2015.11.010. [DOI] [Google Scholar]
  66. Rodríguez-Espíndola O, Albores P, Brewster C. Dynamic formulation for humanitarian response operations incorporating multiple organisations. Int J Prod Econ. 2018;204:83–98. doi: 10.1016/j.ijpe.2018.07.023. [DOI] [Google Scholar]
  67. Rodríguez-Espíndola O, Albores P, Brewster C. Disaster preparedness in humanitarian logistics: a collaborative approach for resource management in floods. Eur J Oper Res. 2018;264:978–993. doi: 10.1016/j.ejor.2017.01.021. [DOI] [Google Scholar]
  68. Rodríguez-Espíndola O, Alem D, Pelegrin Da Silva L. A shortage risk mitigation model for multi-agency coordination in logistics planning. Comput Ind Eng. 2020;148:106676. doi: 10.1016/j.cie.2020.106676. [DOI] [Google Scholar]
  69. Rottkemper B, Fischer K, Blecken A, Danne C. Inventory relocation for overlapping disaster settings in humanitarian operations. OR Spectr. 2011;33:721–749. doi: 10.1007/s00291-011-0260-5. [DOI] [Google Scholar]
  70. Santos JR, Herrera LC, Yu KDS, Pagsuyoin SAT, Tan RR. State of the art in risk analysis of workforce criticality influencing disaster preparedness for interdependent systems. Risk Anal. 2014;34:1056–1068. doi: 10.1111/risa.12183. [DOI] [PubMed] [Google Scholar]
  71. Sarma D, Das A, Dutta P, Bera UK. A cost minimization resource allocation model for disaster relief operations with an information crowdsourcing-based MCDM approach. IEEE Trans Eng Manag. 2020;69:1–21. [Google Scholar]
  72. Seaberg D, Devine L, Zhuang J. A review of game theory applications in natural disaster management research. Nat Hazards J Int Soc Prev Mitig Nat Hazards. 2017;89:1461. [Google Scholar]
  73. SEGOB (2006) ACUERDO por el que se emite el Manual de Organización y Operación del Sistema Nacional de Protección Civil. México, p 112
  74. SEGOB (2008) Tercer informe de gobierno. In: Protection C (ed) Mexico
  75. SEGOB (2012) ACUERDO que establece los Lineamientos del Fondo para la Atención de Emergencias FONDEN. p 30
  76. Shamsi N, Torabi S, Shakouri H. An option contract for vaccine procurement using the SIR epidemic model. Eur J Oper Res. 2018;267:1122–1140. doi: 10.1016/j.ejor.2017.12.013. [DOI] [Google Scholar]
  77. Shan X, Zhuang J. Cost of equity in homeland security resource allocation in the face of a strategic attacker. Risk Anal. 2013;33:1083–1099. doi: 10.1111/j.1539-6924.2012.01919.x. [DOI] [PubMed] [Google Scholar]
  78. Sharifyazdi M, Navangul KA, Gharehgozli A, Jahre M. On- and offshore prepositioning and delivery mechanism for humanitarian relief operations. Int J Prod Res. 2018;56:6164–6182. doi: 10.1080/00207543.2018.1477260. [DOI] [Google Scholar]
  79. Sheu JB. Post-disaster relief-service centralized logistics distribution with survivor resilience maximization. Transp Res Part B Methodol. 2014;68:288–314. doi: 10.1016/j.trb.2014.06.016. [DOI] [Google Scholar]
  80. Shokr I, Torabi SA. An enhanced reverse auction framework for relief procurement management. Int J Disaster Risk Reduct. 2017;24:66–80. doi: 10.1016/j.ijdrr.2017.05.019. [DOI] [Google Scholar]
  81. Sosa-Rodríguez F (2006) Coordinating risk mitigation efforts: National Civil Protection System (SINAPROC).
  82. Takeda M, Helms M. “Bureaucracy, meet catastrophe”: analysis of the tsunami disaster relief efforts and their implications for global emergency governance. Int J Public Sect Manag. 2006;19:204–217. doi: 10.1108/09513550610650446. [DOI] [Google Scholar]
  83. Thompson KM, Duintjer Tebbens RJ. Framework for optimal global vaccine stockpile design for vaccine-preventable diseases: application to Measles and Cholera vaccines as contrasting examples. Risk Anal. 2016;36:1487–1509. doi: 10.1111/risa.12265. [DOI] [PubMed] [Google Scholar]
  84. Torabi S, Shokr I, Tofighi S, Heydari J. Integrated relief pre-positioning and procurement planning in humanitarian supply chains. Transp Res Part E Logist Transp Rev. 2018;113:123–146. doi: 10.1016/j.tre.2018.03.012. [DOI] [Google Scholar]
  85. Toyasaki F, Arikan E, Silbermayr L, Falagara Sigala I. Disaster relief inventory management: horizontal cooperation between humanitarian organizations. Prod Oper Manag. 2017;26:1221–1237. doi: 10.1111/poms.12661. [DOI] [Google Scholar]
  86. Trias APL, Cook ADB. Future directions in disaster governance: insights from the 2018 Central Sulawesi Earthquake and Tsunami response. Int J Disaster Risk Reduct. 2021;58:102180. doi: 10.1016/j.ijdrr.2021.102180. [DOI] [Google Scholar]
  87. UNISDR (2019) Global assessment report on Disaster Risk Reduction
  88. Velasquez GA, Mayorga ME, Cruz EAR. Prepositioning inventory for disasters: a robust and equitable model. OR Spectr. 2019;41:757–785. doi: 10.1007/s00291-019-00554-z. [DOI] [Google Scholar]
  89. Wachira G. Conflicts in Africa as compound disasters: complex crises requiring comprehensive responses. J Conting Crisis Manag. 1997;5:109–117. doi: 10.1111/1468-5973.00042. [DOI] [Google Scholar]
  90. Wachtendorf T, Kendra J (2004) Considering convergence, coordination, and social capital in disasters
  91. Wang X, Fan Y, Liang L, De Vries H, Van Wassenhove LN. Augmenting fixed framework agreements in humanitarian logistics with a bonus contract. Prod Oper Manag. 2019;28:1921–1938. doi: 10.1111/poms.13024. [DOI] [Google Scholar]
  92. Wassenhove LNV. Humanitarian aid logistics: supply chain management in high gear. J Oper Res Soc. 2006;57:475–489. doi: 10.1057/palgrave.jors.2602125. [DOI] [Google Scholar]
  93. Wenger D, Quarantelli EL, Dynes R (1986) Disaster analysis: emergency management offices and arrangements. University of Delaware, Disaster Research Center
  94. Zhang J-H, Li J, Liu Z-P. Multiple-resource and multiple-depot emergency response problem considering secondary disasters. Expert Syst Appl. 2012;39:11066–11071. doi: 10.1016/j.eswa.2012.03.016. [DOI] [Google Scholar]

Articles from Or Spectrum are provided here courtesy of Nature Publishing Group

RESOURCES